> A risk target is the level of risk that an owner or a regulator sets as the line a piece of equipment or a system should stay under.

- Label: Fact
- Type: Glossary term
- Published: 2026-11-14T11:13:54+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-14
- Topics: LNG, Refining, Upstream and offshore
- Canonical: https://beacon.winda.ai/glossary/risk-target/

Inspection and other measures are then planned so that the estimated risk does not cross it. A 1992 US national laboratory paper on risk-based inspection of nuclear plant components framed it as the answer to the question of how much inspection is enough: a total target risk is shared out among components, and inspection has to keep each component's probability of rupture below its share [1]. API's catalog entry for API RP 581 says an inspection is recommended as risk approaches a risk tolerance or risk target [2].

It is the line on the risk scale that triggers action. It is a choice about acceptable risk, not a measured limit such as a minimum wall thickness [1].

Who sets the line differs [3][4][5]:

- **Operators.** Pipeline operators told the US National Transportation Safety Board (NTSB) that the ability to set a target risk level is one advantage of probabilistic risk models [3].
- **US process safety rules.** The US Chemical Safety and Hazard Investigation Board (CSB) noted that the US process safety management and risk management program rules do not require risk to be reduced to a specific target such as ALARP, as low as reasonably practicable [4].
- **A regulator's numbers.** For land-use planning advice around major hazard sites, the UK Health and Safety Executive (HSE) draws contours at individual risk levels of 10, 1 and 0.3 chances per million per year of receiving a dangerous dose [5]. These are planning levels, not inspection targets.

## Sources

1. [Risk Based ASME Code Requirements (B. F. Gore, T. V. Vo, K. R. Balkey), PNL-SA-21211, OSTI 7129942, Pacific Northwest Laboratory, US Department of Energy, via OSTI.gov](https://www.osti.gov/servlets/purl/7129942)
2. [2025 Publications Catalog (entry for API RP 581), American Petroleum Institute (API)](https://www.api.org/-/media/files/publications/2025-catalog/2025_pubs%20catalog.pdf)
3. [Integrity Management of Gas Transmission Pipelines in High Consequence Areas, Safety Study NTSB/SS-15/01, US National Transportation Safety Board (NTSB)](https://www.ntsb.gov/safety/safety-studies/Documents/SS1501.pdf)
4. [Investigation Report: Catastrophic Rupture of Heat Exchanger (Seven Fatalities), Tesoro Anacortes Refinery, Anacortes, Washington, April 2, 2010, Report 2010-08-I-WA, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/7/tesoro_anacortes_2014-may-01.pdf)
5. [HSE's land use planning methodology, UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/landuseplanning/methodology.htm)