# What are condition monitoring locations (CMLs)?

> A condition monitoring location (CML) is a marked area on piping or a pressure vessel where wall thickness or other condition readings are repeated. Comparing readings taken at the same spots gives corrosion rates and remaining life. API 570 and API 510 call for them; they are also called thickness monitoring locations (TMLs).

- Label: Fact
- Type: Explainer
- Published: 2026-11-14T11:53:52+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-14
- Topics: LNG, Refining, Upstream and offshore
- Canonical: https://beacon.winda.ai/library/condition-monitoring-locations/

## Why does it matter?

On June 21, 2019, a carbon steel elbow in a hydrofluoric acid (HF) alkylation unit at a Philadelphia refinery ruptured, leading to a fire and explosions [1]. The US Chemical Safety and Hazard Investigation Board (CSB) found that the piping circuit had grown from 41 CMLs in 2002 to 141 by 2019, yet none sat on the elbow that failed [1]. The elbow's steel was high in nickel and copper, it corroded faster than the pipe around it, and it was down to 0.011 inch (about 0.28 mm) from an original 0.322 inch (about 8.2 mm) [1]. The CSB concluded that inspecting all the carbon steel components exposed to HF corrosion in the unit might have revealed it [1].

## How are CMLs chosen?

Plants first split piping into circuits: sections with similar process conditions, the same material and the same expected damage [1]. CMLs are then set within each circuit.

- **By damage pattern.** As the CSB describes API 570, a circuit with uniform corrosion can be followed with fewer CMLs, while localized corrosion needs more [1]. A handful of points can stand for a whole circuit only when its metal loss is roughly even [2].
- **At turbulent spots.** CMLs are most often placed on elbows and fittings, where turbulence usually causes the fastest metal loss [2].
- **At known weak spots.** The US Occupational Safety and Health Administration (OSHA), describing API 570, adds injection and mixing points and dead legs, with the number of CMLs set by safety impact, expected corrosion rates and how complex the system is [3].
- **By written procedure.** Under US process safety management (PSM) rules, OSHA expects an employer's own procedures to fix the number and position of thickness locations for each vessel and piping section; adopting API 510 wholesale does not meet that requirement [4].

Each CML can stand for up to four reading points around the pipe [1]. API's 2025 catalog lists API 570, 5th edition (February 2024), for piping and API 510, 11th edition (October 2022), for pressure vessels [6].

## What is recorded at each CML?

OSHA's refinery inspection checklist asks whether each sampled piping circuit's records show [4]:

- the installation date, specifications and materials of construction; [4]
- the original thickness, and the location, date and result of every later reading; [4]
- the retirement thickness; [4]
- the piping service class, earlier repairs and replacements, and relevant operating changes. [4]

From successive readings an inspection database tracks corrosion rates and projects remaining life [2]. Readings that make no physical sense, such as a wall measured thicker than before, have to be retested and resolved; OSHA's refinery inspections found cases where they were ignored [3][4].

## Where integrity problems show up

| What it finds well | What it can miss or get wrong | In the Library |
|---|---|---|
| Uniform metal loss across a circuit, followed at a modest number of points [1][2] | A component that corrodes faster because of its chemistry, such as the high nickel and copper elbow in HF service at Philadelphia in 2019 [1] | [Corrosion circuit](/glossary/corrosion-circuit/) |
| Metal loss at turbulent elbows and fittings [2] | Low-silicon straight pipe in hot sulfur service: at a Richmond, California, refinery, 19 CMLs missed the component that ruptured in 2012 [2] | [What is sulfidation (high-temperature sulfur corrosion)?](/library/sulfidation/) |
| Known weak spots: injection and mixing points, dead legs [3] | Very local thinning between reading points; a UK relief line tested at four locations ruptured (HSE alert, 2019) [5] | [Injection point](/glossary/injection-point/), [Dead leg](/glossary/dead-leg/) |
| Corrosion rates and remaining life at each point over time [2][4] | Corrosion faster than expected that is not acted on, and unresolved anomalous readings, both found in OSHA's refinery inspections [3] | Corrosion rate and remaining life calculator |
| Findings entered as CML data [2] | Findings kept only as notes: at Richmond, a 2002 reading of about one-third wall loss was never followed up because no CML was added [2] | [What is an inspection data management system (IDMS)?](/library/inspection-data-management-system/) |

Sources: CSB report No. 2019-04-I-PA, 2022 [1]; CSB final report on the 2012 Richmond refinery fire, 2015 [2]; OSHA 3918, 2017 [3]; UK Health and Safety Executive (HSE) safety alert CEMHD2-2019 [5].

## Sources

1. [Fire and Explosions at Philadelphia Energy Solutions Refinery Hydrofluoric Acid Alkylation Unit, Investigation Report No. 2019-04-I-PA, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/20/PES_Final_Report_Published_October_2022_r1.pdf?16845), 2022-10-11
2. [Final Investigation Report: Chevron Richmond Refinery Pipe Rupture and Fire, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/17/Chevron_Final_Investigation_Report_2015-01-28.pdf?15397), 2015-01-28
3. [Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918), US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/Publications/OSHA3918.pdf)
4. [CPL 03-00-004, Petroleum Refinery Process Safety Management National Emphasis Program, US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/enforcement/directives/cpl-03-00-004)
5. [Catastrophic rupture of dead-leg pipe-work (Safety alert, Bulletin No. CEMHD2-2019), UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/safetybulletins/catastrophic-rupture-dead-leg-pipe-work.htm), 2019-08-20
6. [2025 Publications Catalog (entries for API 570 and API 510) (API 570, 5th edition, February 2024; API 510, 11th edition, October 2022), American Petroleum Institute (API)](https://www.api.org/-/media/files/publications/2025-catalog/2025_pubs%20catalog.pdf)
7. [Corrosion Sensors for Structural Health Monitoring of Oil and Natural Gas Infrastructure: A Review (R. F. Wright et al.), Sensors 19(18):3964, MDPI, via PubMed Central](https://pmc.ncbi.nlm.nih.gov/articles/PMC6767297/), 2019-09-13

Published by Winda Beacon (https://beacon.winda.ai).