# How do you design equipment so it can be inspected?

> Designing for inspectability means building in the access, openings, drains and monitoring points that later inspection needs. It also means avoiding features, such as dead legs and poorly sealed insulation, that hide damage. For new US gas transmission lines, 49 CFR 192.150 requires a design that lets in-line inspection tools pass through.

- Label: Fact
- Type: Explainer
- Published: 2026-11-13T09:26:54+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-13
- Topics: LNG, Pipelines, Refining
- Canonical: https://beacon.winda.ai/library/design-for-inspectability/

## Why does it matter?

At a Sunray, Texas, refinery in 2007, water collected in a control station that had been left connected but unused for about 15 years, froze, cracked an elbow and released liquid propane at about 4,500 pounds per minute, which ignited [1]. The US Chemical Safety and Hazard Investigation Board (CSB) found that the idle station formed a dead leg, and that a 2006 drawing update had identified only the dead legs that were obvious to the eye, not ones created by closed valves [1]. Three workers were seriously burned and the refinery shut down [2]. OSHA's refinery inspections found related gaps, including insulated equipment that was never checked for corrosion under insulation [3].

## Which design features make inspection possible?

| Feature | What it allows later | Public anchor |
|---|---|---|
| Access openings, drains and vents on pressure vessels | Internal examination, and safe draining and venting first | HSE vessel design guidance [4] |
| Piping routed with safe access for operation, inspection and maintenance | Reaching lines, supports and welds without improvised access | HSE pipework guidance [5] |
| Free drainage, with no pockets or dead legs in hazardous service | No trapped water, condensate or deposits where damage can grow | HSE [5][6] |
| Weatherproofed insulation, and an inspection program for insulated piping | Less corrosion under insulation, and planned checks where it can occur | HSE [5]; OSHA [3] |
| Condition monitoring locations at susceptible points such as injection points, mixing points and dead legs | Thickness trending where thinning is most likely | OSHA, citing API 570 as an example of good practice [3] |
| Pipelines that pass in-line inspection tools | Internal inspection along the full length | 49 CFR 192.150 for gas, 195.120 for hazardous liquids [7][8] |
| Liquid removal and corrosion monitoring points on new gas transmission lines | Checking internal corrosion where it is most likely | 49 CFR 192.476 [9] |
| Relief devices and emergency valves placed where people can reach them | Testing, maintenance and safe operation in an emergency | OSHA [3] |

## How do dead legs, insulation and poor access hide damage?

**Dead legs.** CSB defines a dead leg as piping that stays connected to the process but has no flow through it [1]. At Sunray, CSB concluded that water in the propane most likely sank into the idle station and collected there [1]. HSE guidance for hazardous fluids calls for piping without dead legs and designed to drain, and for avoiding pockets where corrosive condensate can form [5]. OSHA notes that API 570, an example of good practice, places monitoring points at dead legs because they are prone to damage [3].

**Insulation.** HSE warns that badly installed insulation creates ideal conditions for corrosion and needs weatherproofing against moisture and spills [5]. In its refinery emphasis program, begun in 2007, OSHA cited sites that did not inspect for corrosion under insulation, and listed poor design that lets moisture collect and insulation that holds water among the contributing factors [3].

**Access.** OSHA's inspectors also found relief devices in inaccessible places, a bypass valve that could only be reached by crawling across a pipe rack, and emergency isolation valves placed where operators would be in harm's way [3].

## When in a project is inspectability decided?

Mostly during layout and routing in front-end engineering design (FEED) and detailed design, when vessel nozzles, pipe routes, insulation systems and pipeline fittings are fixed [4][5]. For US pipelines, the piggability rules apply to each new transmission line and to replacements of line pipe, valves and fittings, with exceptions such as manifolds, station piping, gathering lines and pipe sizes for which no tool is commercially available [7]. The hazardous liquid rule has a parallel list [8].

Changes during operation count too. When a gas transmission operator changes a line's configuration, it must assess the effect on internal corrosion downstream and provide for liquid removal and monitoring as needed [9]. At Sunray, no management of change review was done when the control station was taken out of service in the 1990s [1]. See [Concept, pre-FEED, FEED and detailed design: what happens in each phase?](/library/project-design-phases/).

## Where integrity problems show up

| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| Leaving unused piping connected instead of removing or isolating it | A dead leg where water can collect, freeze or corrode [1][5] | [Dead leg](/glossary/dead-leg/) |
| Insulating without weatherproofing or a way for water to drain | Corrosion that stays hidden under the insulation [3][5] | [What is corrosion under insulation (CUI)?](/library/corrosion-under-insulation/) |
| Not defining monitoring locations at susceptible points | Thinning that goes unmeasured; OSHA cited missing ultrasonic thickness testing and uninspected location points [3] | What are condition monitoring locations (CMLs)? |
| Building a pipeline with bends, valves or taps that block inspection tools | A line that cannot be inspected internally and needs other methods [7] | How are unpiggable pipelines inspected? |
| Omitting access openings or drains on a vessel | Internal condition that cannot be examined directly [4] | [How are pressure vessels inspected?](/library/pressure-vessel-inspection/) |
| Placing relief devices out of reach | Testing and maintenance that are harder to carry out [3] | What does a pressure relief valve do? |

Sources: CSB report on the 2007 Sunray, Texas, refinery fire (2008) [1]; OSHA 3918, 2017 [3]; HSE COMAH technical measures documents (2025) [4][5]; 49 CFR 192.150 [7].

## Sources

1. [Investigation Report: LPG Fire at Valero-McKee Refinery (Four Injured, Total Refinery Evacuation, and Extended Shutdown), Report No. 2007-05-I-TX, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/20/CSBFinalReportValeroSunray.pdf?13739)
2. [Valero McKee Refinery Propane Fire (investigation page and recommendations), US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/valero-mckee-refinery-propane-fire/)
3. [Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918), US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/Publications/OSHA3918.pdf)
4. [Design Codes: Plant (COMAH Technical Measures Document), UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/comah/sragtech/techmeasplant.htm), 2025-08-19
5. [Design Codes: Pipework (COMAH Technical Measures Document), UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/comah/sragtech/techmeaspipework.htm), 2025-08-19
6. [Corrosion / selection of materials (COMAH Technical Measures Document), UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/comah/sragtech/techmeasmaterial.htm), 2025-08-19
7. [49 CFR 192.150, Passage of internal inspection devices, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/section-192.150)
8. [49 CFR 195.120, Passage of internal inspection devices, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/section-195.120)
9. [49 CFR 192.476, Internal corrosion control: Design and construction of transmission line, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/section-192.476)

Published by Winda Beacon (https://beacon.winda.ai).