# What is front-end engineering design (FEED)?

> Front-end engineering design (FEED) turns a selected concept into a defined scope, design basis and cost estimate for an investment decision. It sits between concept selection (pre-FEED) and detailed design. No single code governs FEED; in US plants covered by process safety management, its outputs supply the information required by 29 CFR 1910.119(d).

- Label: Fact
- Type: Explainer
- Published: 2026-11-13T09:26:54+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-13
- Topics: LNG, Pipelines, Refining
- Canonical: https://beacon.winda.ai/library/front-end-engineering-design/

## Why does it matter?

NASA's systems engineering handbook, drawing on a Defense Acquisition University figure, notes that design may use only about 15% of a system's life-cycle cost while committing about 75% of it, and adds that the split varies from project to project [1]. The US Department of Energy (DOE) says in its capital project order that value reviews held early in a project give the largest cost reductions [2]. In an oil, gas or chemical project, FEED is where many of these commitments are made, including the material choices, corrosion margins and records that integrity teams rely on for decades [6][9].

## Where does FEED sit in a project?

Capital projects move through phases separated by approval points, often called gates [2]. The Construction Industry Institute (CII) at the University of Texas at Austin groups front end planning into feasibility, concept and detailed scope, and describes it as the work that confirms the investment, sets the design basis and defines how the project will be executed [3]. In oil and gas use, a pre-FEED study compares options and picks one, and FEED then develops only that option [4] (see [Concept, pre-FEED, FEED and detailed design: what happens in each phase?](/library/project-design-phases/)).

A DOE-supported FEED for a carbon capture system at a US power plant, which followed a completed pre-FEED study, was set up to deliver the design, cost and performance data needed to start project financing, the engineering and material balances needed for permits, and a final schedule [4]. The decision at the end of FEED is whether to commit to detailed design, procurement and construction [2][4].

## What does a FEED study produce?

Deliverables vary by project and contract. A public example, a DOE-funded FEED for carbon capture at a US coal-fired power plant (2020 to 2021), was split into a design basis, preliminary engineering, detailed engineering inside and outside the battery limits, supporting studies, a cost assessment and a permitting pathway [5]. Its milestones included a design basis document, a hazard and operability (HAZOP) review and a constructability review before the final FEED package [5].

In US processes covered by the Occupational Safety and Health Administration (OSHA) process safety management (PSM) standard, the employer must compile written process safety information before any process hazard analysis [6]. Many items on that list are first created in FEED:

| Typical FEED output | Process safety information item it supplies, 29 CFR 1910.119 | In the Library |
|---|---|---|
| Process flow diagrams with heat and material balances | Block flow or simplified process flow diagram, (d)(2)(i)(A); material and energy balances, required for processes built after May 26, 1992, (d)(3)(i)(G) | [Process flow diagram (PFD) vs P&ID: what is the difference?](/library/pfd-vs-pid/) |
| Operating envelope | Safe upper and lower limits for temperature, pressure, flow or composition, (d)(2)(i)(D) | [What are integrity operating windows (IOWs)?](/library/integrity-operating-windows/) |
| Piping and instrumentation diagrams | P&IDs, (d)(3)(i)(B) | [What is a piping and instrumentation diagram (P&ID)?](/library/piping-and-instrumentation-diagram/) |
| Materials selection, equipment datasheets and line list | Materials of construction, (d)(3)(i)(A) | How are materials selected for oil and gas equipment?, [What is an equipment datasheet?](/library/equipment-datasheet/) |
| Relief and flare system design | Relief system design and design basis, (d)(3)(i)(D) | What does a pressure relief valve do? |
| Design basis and specifications | Design codes and standards employed, (d)(3)(i)(F) | What is a design basis? |

Source: 29 CFR 1910.119(d), eCFR, 22 Oct 2026 [6]. The first column is Beacon's mapping of common FEED outputs to the regulation's list.

## How is FEED different from detailed design?

FEED decides what will be built and roughly what it will cost; detailed design produces the documents used to buy and build it [2][4]. DOE describes final design as the stage that prepares final drawings, technical specifications and bid documents, including testing requirements and acceptance criteria, after which scope changes need a compelling reason [2]. DOE sets its cost and schedule baseline only when the design is mature: at least 90% complete for a new nuclear facility, and mature enough for 70 to 90% confidence on other projects [2]. Long-lead purchases can still be approved earlier (see [What are long-lead items?](/library/long-lead-items/)).

Regulators can reach into the front end too. In UK waters, the operator of a new offshore production installation must send the regulator a design notification before the field development plan, early enough for comments to shape the design [8]. It describes the chosen concept and the options considered, the standards and design philosophy, and an initial list of safety and environmental critical elements [8].

## Where integrity problems show up

| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| Choosing carbon steel or a higher-chromium steel for hot, sulfur-bearing streams | Corrosion rate for decades: carbon steel with under 0.10% silicon can thin by sulfidation up to 16 times faster; steels with at least 9% chromium are inherently safer [9] | [What is sulfidation (high-temperature sulfur corrosion)?](/library/sulfidation/) |
| Setting a corrosion allowance from an expected corrosion rate | The extra wall that remaining-life estimates draw down; OSHA cited refineries whose actual rates exceeded expected rates [7][10] | [Corrosion allowance](/glossary/corrosion-allowance/) |
| Recording the relief system design basis | Whether later changes can be checked against it; OSHA found many refineries lacked this record [10] | What does a pressure relief valve do? |
| Designing a new gas transmission line to pass in-line inspection tools | Whether the line can be inspected from inside; required by 49 CFR 192.150, with listed exceptions [11] | What is in-line inspection (ILI) and pigging? |
| Configuring a new onshore gas transmission line so liquids do not collect | Internal corrosion risk and room for monitoring devices; required by 49 CFR 192.476 since May 2007 [12] | [What is corrosion monitoring and which methods are used?](/library/corrosion-monitoring/) |
| Listing safety and environmental critical elements (UK offshore) | The equipment whose performance is verified and inspected in operation [8] | What are safety and environmental critical elements (SECEs)? |

Sources: CSB report on the 2012 Richmond, California, refinery fire (2015) [9]; HSE (2025) [7]; OSHA 3918 (2017) [10]; 49 CFR 192.150 and 192.476 [11][12]; SI 2015/398 [8].

## Sources

1. [SEH 2.5 Cost Effectiveness Considerations (NASA Systems Engineering Handbook, NASA/SP-2016-6105 Rev2), US National Aeronautics and Space Administration (NASA)](https://www.nasa.gov/reference/2-5-cost-effectiveness-considerations/)
2. [DOE O 413.3C, Program and Project Management for the Acquisition of Capital Assets, US Department of Energy (DOE), Office of Project Management](https://www.energy.gov/documents/doe-o-413-3-cprogram-and-project-management-acquisition-capital-assets2026-07-23pdf)
3. [Front End Planning: Your Key to a Successful Project (WS213-01), Construction Industry Institute (CII), University of Texas at Austin](https://www.construction-institute.org/front-end-planning-your-key-to-a-successful-project), 2014-07-01
4. [Front-End Engineering and Design: Project Tundra Carbon Capture System (project information page, FE0031845), US DOE National Energy Technology Laboratory (NETL)](https://netl.doe.gov/projects/project-information.aspx?p=fe0031845)
5. [Full-Scale FEED Study for a 816 MWe Capture Plant at the Prairie State Generating Company Using Mitsubishi Heavy Industries of America Technology (K. C. O'Brien, University of Illinois), DOE/NETL 2020 Integrated Review Meeting, US DOE National Energy Technology Laboratory (NETL)](https://netl.doe.gov/sites/default/files/netl-file/20CCUS_OBrien.pdf), 2020-08-17
6. [29 CFR 1910.119, Process safety management of highly hazardous chemicals, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-29/section-1910.119)
7. [Corrosion / selection of materials (COMAH Technical Measures Document), UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/comah/sragtech/techmeasmaterial.htm), 2025-08-19
8. [The Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015 (SI 2015/398), regulation 15 and Schedule 5, as made, legislation.gov.uk, UK National Archives](https://www.legislation.gov.uk/uksi/2015/398/schedule/5/made)
9. [Final Investigation Report: Chevron Richmond Refinery Pipe Rupture and Fire (Report No. 2012-03-I-CA), US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/17/Chevron_Final_Investigation_Report_2015-01-28.pdf?15397), 2015-01-28
10. [Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918), US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/Publications/OSHA3918.pdf)
11. [49 CFR 192.150, Passage of internal inspection devices, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/section-192.150)
12. [49 CFR 192.476, Internal corrosion control: Design and construction of transmission line, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/section-192.476)

Published by Winda Beacon (https://beacon.winda.ai).
