# What documents are handed over when a project is completed?

> When a project is completed, the owner receives as-built drawings, equipment data and manuals, material certificates, and inspection and test records. Together they describe the facility as actually built. In US plants under the Occupational Safety and Health Administration's (OSHA) process safety rule, 29 CFR 1910.119, much of this information must be in place before start-up.

- Label: Fact
- Type: Explainer
- Published: 2026-11-13T09:39:01+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-13
- Topics: Pipelines, Refining
- Canonical: https://beacon.winda.ai/library/handover-documentation/

## Why does it matter?

A unit can be fully built and still not be ready for hazardous chemicals: under OSHA's process safety rule (29 CFR 1910.119), a pre-startup safety review must first confirm that it matches its design specifications and that its procedures are in place [1]. For a new facility the review also confirms that a process hazard analysis was done, and that analysis needs written process safety information first, such as materials of construction, piping and instrumentation diagrams (P&IDs) and the relief design basis [1]. Gaps left at handover can surface decades later: investigators found that the 1956 construction file for the gas pipeline segment that ruptured in San Bruno, California, in 2010 held cost accounting papers but no specifications, inspection records, as-built drawings or radiography reports [8].

## What is in a handover package?

Federal process safety and pipeline rules, the construction clauses of the Federal Acquisition Regulation (FAR), the Unified Facilities Guide Specifications (UFGS) for US military construction and the CFIHOS information handover specification each name parts of a handover package [1][2][5][6][7]. The table groups them by purpose.

| Document group | What it records | Named in |
|---|---|---|
| As-built and record drawings, including P&IDs | The facility as installed, with every change from the design | 29 CFR 1910.119(d)(3) and Appendix C [1]; FAR 52.236-21, Alternates I and II [5]; UFGS 01 78 00 [6] |
| Process safety information | Chemical hazards, process technology, materials of construction, electrical classification, relief and ventilation design, design codes, material and energy balances, safety systems | 29 CFR 1910.119(d) [1] |
| Tag and document registers | Every tag in the facility; every document with its number, title and revision | CFIHOS master tag and document registers [7] |
| Record of equipment and materials | Manufacturer, model, serial number, composition, size and where each item is used | UFGS 01 78 00 [6] |
| Quality records and certificates | Certifications of code-built vessels and verified materials of construction | 29 CFR 1910.119, Appendix C [1] |
| Pressure test records | Test medium, pressure, duration, pressure charts, leaks and failures | 49 CFR 192.517 [2] |
| Operating and maintenance information | Operation and maintenance manuals, spare parts data and warranties; operating, maintenance and emergency procedures | UFGS 01 78 00 [6]; 29 CFR 1910.119(i) [1] |

## Who prepares and checks the documents?

The contractor and its suppliers create most records; the owner sets out in the contract what it needs and reviews what arrives, and CFIHOS gives each party information management roles plus a joint project team [7]. In US military construction specifications, the contractor keeps the marked-up as-built set current every week and open to monthly government review, and part of a progress payment can be held back if it falls behind [6].

A US Environmental Protection Agency (EPA) training handout on asset management lists two controls for records of newly acquired assets: tie the inventory to commissioning or handover, and use contract retainage [13]. Under OSHA's rule, the owner of a covered process must also check that new equipment is suitable as fabricated and is installed to the design specifications and the manufacturer's instructions [1].

## When are handover documents delivered?

- **During construction.** As-built markups and the shared tag and document registers are updated as work proceeds [6][7].
- **Before start-up.** The pre-startup safety review checks construction against the design and confirms procedures and training; OSHA's nonmandatory guidance adds that P&IDs should be complete by then [1]. See [What is a pre-startup safety review (PSSR)?](/library/pre-startup-safety-review/).
- **At completion.** Federal construction contracts that call for record shop drawings require the final approved set, with all changes up to acceptance [5]. Under CFIHOS, as-built data and documents follow physical handover within a period set in the contract [7].
- **After start-up.** Changes pass through management of change, and OSHA's guidance says drawings and procedures are then updated so the revisions become permanent [1].

## Which handover records must be kept for the life of the asset?

| Record | How long | Rule |
|---|---|---|
| Gas pipeline pressure test records (tests under 192.505 to 192.507) | Useful life of the pipeline | 49 CFR 192.517(a) [2] |
| Diameter, wall thickness, seam type and grade of onshore steel gas transmission pipe, where the pipeline code calls for it | Life of the pipeline, traceable, verifiable and complete | 49 CFR 192.607(b) [4] |
| Date, location and description of repairs to hazardous liquid pipe | Useful life of the pipe | 49 CFR 195.404(c)(1) [3] |
| Hazardous liquid pipeline maps and records, including pipe diameter, grade, type and wall thickness | Kept current | 49 CFR 195.404(a) [3] |
| Damage mechanism review reports at California refineries | Life of the process unit | 8 CCR 5189.1(k)(14) [10] |

Sources: eCFR [2][3][4]; 8 CCR 5189.1 [10].

## Where integrity problems show up

| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| Pressure test records kept with medium, pressure, duration and charts | Crack analyses of gas transmission pipe can use a past pressure test to size the largest flaw that could have survived it | What is a hydrostatic test?, [What is fitness-for-service (API 579-1/ASME FFS-1)?](/library/fitness-for-service/) |
| Material certificates and verified materials of construction kept with the quality records | Where federal rules require it, onshore gas transmission operators whose material records are not traceable, verifiable and complete must test the pipe to confirm its properties | [What is material traceability?](/library/material-traceability/) |
| A pre-service thickness survey included in the package | Corrosion rates based on nominal instead of measured thickness can carry large errors from mill tolerances | Baseline inspection |
| P&IDs, process flow diagrams, heat and material balances and piping specifications handed over | These are inputs for defining corrosion circuits and for damage mechanism reviews | [What is a corrosion loop?](/library/corrosion-loop/) |
| Relief system design and design basis included in process safety information | OSHA's refinery inspections found written process safety information that did not reflect missing relief devices, undersized relief valves or wrong set points | What does a pressure relief valve do? |

Sources: 49 CFR 192.712(d) [12]; 29 CFR 1910.119, Appendix C [1]; 49 CFR 192.607(c) [4]; AIChE, 2011 [9]; Cal/OSHA, undated [14]; 8 CCR 5189.1(k) [10]; OSHA 3918, 2017 [11].

## Sources

1. [29 CFR 1910.119, Process safety management of highly hazardous chemicals (including Appendix C, nonmandatory compliance guidelines), eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119)
2. [49 CFR 192.517, Records, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/subtitle-B/chapter-I/subchapter-D/part-192/subpart-J/section-192.517)
3. [49 CFR 195.404, Maps and records, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/subtitle-B/chapter-I/subchapter-D/part-195/subpart-F/section-195.404)
4. [49 CFR 192.607, Verification of Pipeline Material Properties and Attributes: Onshore steel transmission pipelines, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/subtitle-B/chapter-I/subchapter-D/part-192/subpart-L/section-192.607)
5. [48 CFR 52.236-21, Specifications and Drawings for Construction (Federal Acquisition Regulation), eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-48/chapter-1/subchapter-H/part-52/subpart-52.2/section-52.236-21)
6. [UFGS 01 78 00, Closeout Submittals (Unified Facilities Guide Specifications), US Army Corps of Engineers, Naval Facilities Engineering Systems Command and Air Force Civil Engineer Center, via the Whole Building Design Guide](https://www.wbdg.org/FFC/DOD/UFGS/UFGS%2001%2078%2000.pdf)
7. [CFIHOS Scope and Procedures (C-TP-001) (Version 2.0), JIP36 CFIHOS, International Association of Oil & Gas Producers (IOGP)](https://www.jip36-cfihos.org/wp-content/uploads/2024/11/v.2.0-CFIHOS-Scope-and-Procedure.docx), 2024-10-31
8. [Pacific Gas and Electric Company Natural Gas Transmission Pipeline Rupture and Fire, San Bruno, California, September 9, 2010 (NTSB/PAR-11/01), US National Transportation Safety Board (NTSB)](https://www.ntsb.gov/investigations/AccidentReports/Reports/PAR1101.pdf)
9. [The Importance of Mechanical Integrity Inspection for Successful Capital Projects (paper 84b, abstract), P. F. Schubert, American Institute of Chemical Engineers (AIChE), 2011 Spring Meeting and 7th Global Congress on Process Safety](https://proceedings.aiche.org/conferences/aiche-spring-meeting-and-global-congress-on-process-safety/2011/proceeding/paper/84b-importance-mechanical-integrity-inspection-successful-capital-projects-0)
10. [California Code of Regulations, Title 8, Section 5189.1, Process Safety Management for Petroleum Refineries, California Department of Industrial Relations](https://www.dir.ca.gov/title8/5189_1.html)
11. [Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918), US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/Publications/OSHA3918.pdf)
12. [49 CFR 192.712, Analysis of predicted failure pressure and critical strain level, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/subtitle-B/chapter-I/subchapter-D/part-192/subpart-M/section-192.712)
13. [Asset Management 101 (webinar handout), US Environmental Protection Agency (EPA)](https://www.epa.gov/sites/default/files/2021-02/documents/asset_management_101_webinar_handout.pdf), 2021-01-21
14. [PSM - Refining Damage Mechanisms 101 (J. Riley), presentation, California Division of Occupational Safety and Health (Cal/OSHA), Pressure Vessel Unit](https://www.dir.ca.gov/dosh/pressure-vessels/documents/PSM-Damage-Mechanism-Requirements.pdf)

Published by Winda Beacon (https://beacon.winda.ai).