# What is an inspection and test plan (ITP)?

> An inspection and test plan (ITP) lists, in sequence, every inspection and test for an item and who must take part in each. For each step it names the procedure, acceptance criteria and record, and marks each party's role: hold, witness, review or monitor. The supplier, purchaser and any independent inspector sign the steps assigned to them.

- Label: Fact
- Type: Explainer
- Published: 2026-11-13T15:18:43+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-13
- Canonical: https://beacon.winda.ai/library/inspection-and-test-plan/

## Why does it matter?

A pressure vessel is ready for its hydrostatic test but the purchaser's inspector has not arrived; whether the shop may start depends on how the inspection and test plan marks that step. If it is a hold point, work stops until the named party has inspected or agreed, and the US nuclear quality rule, one public model, requires such hold points to be written into the work documents [1]. In oil and gas equipment purchasing, the industry's standardized procurement specifications place the purchaser's hold and witness points in a quality requirements document issued with the request for quotation [3]. Unplanned and unrecorded checks let defects pass: the US National Transportation Safety Board (NTSB) found no records of radiography or pressure testing for the 1956 pipeline work that failed at San Bruno, California, in 2010 [7]. The US National Institute of Standards and Technology (NIST) noted in its 1990 pressure vessel guidelines that poor quality control during manufacture can erode the safety margin built into the design and can lie behind problems that appear later in service [13].

## What does an ITP contain?

NASA's hardware quality rules describe the content in general terms: they expect work instructions to give the sequence of steps, the procedures and process specifications to use, inspection and test methods, acceptance criteria, and the hold and inspection points of both the supplier and the buyer [2]. The US nuclear rule expects inspection and test records to name the inspector, the type of observation, the result and whether it was acceptable [1]. A guide reviewed by the UK Chartered Quality Institute's construction group notes that there are no standard ITP codes, that each organization sets its own, and that an ITP can state how much each party checks, such as 100% witnessing by a main contractor and 10% inspection by the client [5].

**Example:**
Illustrative example, not from any real project, code or standard. Key: P perform, H hold, W witness, R review, M monitor.

| Step | Activity | Reference document | Record | Manufacturer | Purchaser | Independent inspector |
|---|---|---|---|---|---|---|
| 1 | Review procedures and drawings | Purchase order, code, drawings | Approved document list | P | R | R |
| 2 | Check material certificates and marking | Material specification | [Mill test certificates](/library/mill-test-certificate/), receiving record | P | R | M |
| 3 | Alloy check on alloy parts | PMI procedure | PMI report | P | W | M |
| 4 | Weld with qualified procedures and welders | Welding procedures and qualifications | Weld map | P | R | M |
| 5 | Post-weld heat treatment | Heat treatment procedure | Time and temperature chart | P | R | R |
| 6 | Nondestructive examination | NDE procedures | NDE reports | P | R | W |
| 7 | Hydrostatic test | Test procedure | Test record and chart | P | H | H |
| 8 | Final inspection and data report | Code, drawings | Dimensional report, data report | P | W | H |

## What are hold, witness, review and monitor points?

| Point | What it means | Can work go on without the party? | Public description |
|---|---|---|---|
| Hold (H) | The next step waits until the named party inspects or gives consent | No | 10 CFR 50 Appendix B, Criterion X [1]; NASA mandatory inspection points [2] |
| Witness (W) | The named party is invited to watch a test or process | Set by the contract and the ITP's own rules [5] | NASA process and test witnessing [2] |
| Review (R) | The party checks documents or records, such as certificates or test data | Yes, unless also marked as a hold [5] | NASA documentation and production record review [2] |
| Monitor (M) or surveillance | Periodic or sample checks on how work is done | Yes | Process monitoring [1]; surveillance [2][5] |

On oil and gas orders that use the standardized procurement specifications of JIP33, a program the International Association of Oil & Gas Producers (IOGP) started in 2016, the quality requirements specification sets the purchaser's level of involvement in inspection and testing [3][4]. It offers four conformity assessment levels, which JIP33 says follow a conformity assessment table in ISO 29001 [3].

## Who prepares and signs an ITP?

The organization doing the work usually prepares the ITP and checks every item itself; in the CQI guide that organization, frequently the trade contractor, is the one that owns the ITP [5]. The buyer chooses its own points: under NASA's rules the buyer selects mandatory inspection points, while the supplier, who controls the schedule, usually says when they fall due [2]. A third party is independent of both supplier and buyer [2]; for ASME code items, the Authorized Inspector certifies the manufacturer's data report [6]. Buyer surveillance adds to the supplier's own responsibility for a conforming product and does not replace it [2].

## Where integrity problems show up

| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| Reviewing material certificates before use | New line pipe tested up to 15% below its reported yield strength [9] | [What is a mill test certificate (EN 10204 3.1 and 3.2)?](/library/mill-test-certificate/) |
| Alloy check for critical alloy parts, also after maintenance | A carbon steel elbow refitted in hot hydrogen service ruptured after about 3 months [10] | What is positive material identification (PMI)? |
| Reviewing heat treatment records | Cracking concentrates at welds without post-weld heat treatment in amine and wet hydrogen sulfide service [11]; at Anacortes, Washington (2010), hydrogen attack was found only near such welds [12] | [What is post-weld heat treatment (PWHT)?](/library/post-weld-heat-treatment/) |
| Witnessing or reviewing nondestructive examination | Some failed girth welds on new pipelines had testing procedures not optimized or not completed [8] | [Radiographic vs ultrasonic testing for welds](/library/radiography-vs-ultrasonic/) |
| Holding for the pressure test and keeping its record | No pressure test record existed for the 1956 San Bruno work; NTSB said such a test might have ruptured the defective pipe at installation [7] | What is a hydrostatic test? |
| Closing out records at the end | Construction records feed later safety assessment of the equipment [11] | [What documents are handed over when a project is completed?](/library/handover-documentation/) |

Sources: PHMSA Advisory Bulletins ADB-09-01, 2009 [9] and ADB-10-03, 2010 [8]; CSB Safety Bulletin 2005-04-B, 2006 [10]; CSB Anacortes report, 2014 [12]; OSHA Technical Manual, Section IV, Chapter 3 [11]; NTSB/PAR-11/01, 2011 [7].

## Sources

1. [10 CFR Part 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-10/chapter-I/part-50/appendix-Appendix%20B%20to%20Part%2050)
2. [NPR 8735.2C, Hardware Quality Assurance Program Requirements for Programs and Projects (updated with Change 2), US National Aeronautics and Space Administration (NASA)](https://nodis3.gsfc.nasa.gov/npg_img/N_PR_8735_002C_/N_PR_8735_002C_.pdf)
3. [JIP33 Frequently Asked Questions, International Association of Oil & Gas Producers (IOGP), JIP33](https://jip33.iogp.org/about/faq/)
4. [About JIP33, International Association of Oil & Gas Producers (IOGP), JIP33](https://jip33.iogp.org/about/)
5. [How to write an inspection and test plan (M. Buss; reviewed for the CQI Construction Special Interest Group), Designing Buildings Wiki, on behalf of the Chartered Quality Institute (CQI) Construction Special Interest Group](https://www.designingbuildings.co.uk/wiki/How_to_write_an_inspection_and_test_plan)
6. [The Authorized Inspector's Responsibility for Dimensional Inspection (National Board BULLETIN, Classic Series), National Board of Boiler and Pressure Vessel Inspectors](https://www.nationalboard.org/Index.aspx?pageID=164&ID=223)
7. [Pacific Gas and Electric Company Natural Gas Transmission Pipeline Rupture and Fire, San Bruno, California, September 9, 2010 (NTSB/PAR-11/01), US National Transportation Safety Board (NTSB)](https://www.ntsb.gov/investigations/AccidentReports/Reports/PAR1101.pdf)
8. [Pipeline Safety: Girth Weld Quality Issues Due to Improper Transitioning, Misalignment, and Welding Practices of Large Diameter Line Pipe (Advisory Bulletin ADB-10-03), 75 FR 14243, US Pipeline and Hazardous Materials Safety Administration (PHMSA), via Federal Register (govinfo)](https://www.govinfo.gov/content/pkg/FR-2010-03-24/html/2010-6528.htm), 2010-03-24
9. [Pipeline Safety: Potential Low and Variable Yield and Tensile Strength and Chemical Composition Properties in High Strength Line Pipe (Advisory Bulletin ADB-09-01), 74 FR 23930, US Pipeline and Hazardous Materials Safety Administration (PHMSA), via Federal Register (govinfo)](https://www.govinfo.gov/content/pkg/FR-2009-05-21/html/E9-11815.htm), 2009-05-21
10. [Safety Bulletin No. 2005-04-B, BP Texas City, TX Refinery Fire: Positive Material Verification: Prevent Errors During Alloy Steel Systems Maintenance, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/UserFiles/file/RHUBulletin.pdf), 2006-10-12
11. [OSHA Technical Manual, Section IV, Chapter 3: Pressure Vessel Guidelines, US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/otm/section-4-safety-hazards/chapter-3)
12. [Investigation Report: Catastrophic Rupture of Heat Exchanger (Seven Fatalities), Tesoro Anacortes Refinery, Anacortes, Washington, April 2, 2010 (Report 2010-08-I-WA), US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/6/Tesoro_Anacortes_2014-May-01.pdf?15244)
13. [NIST Special Publication 780, Guidelines for Pressure Vessel Safety Assessment (S. Yukawa), US National Institute of Standards and Technology (NIST)](https://nvlpubs.nist.gov/nistpubs/Legacy/SP/nistspecialpublication780.pdf)

Published by Winda Beacon (https://beacon.winda.ai).