# What should an inspection plan contain?

> An inspection plan sets out, for each equipment item, which damage to look for, where, by which method and when, and how results are recorded and used. US process safety rules (29 CFR 1910.119(j)) require written procedures and documented inspections; UK pressure systems law requires a written scheme of examination.

- Label: Fact
- Type: Explainer
- Published: 2026-11-13T15:18:43+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-13
- Topics: LNG, Refining, Upstream and offshore
- Canonical: https://beacon.winda.ai/library/inspection-plan/

## Why does it matter?

On 2 April 2010 a heat exchanger ruptured at a refinery in Anacortes, Washington, and the explosion and fire that followed killed seven workers [1]. The US Chemical Safety and Hazard Investigation Board (CSB) found that none of the damage mechanism reviews carried out over the previous 20 years had identified high temperature hydrogen attack (HTHA) in those exchangers, because they relied on design data rather than measured process conditions, so the exchangers were never inspected for it [1]. A plan can only send inspectors to damage that someone has first identified. The CSB added that early HTHA is very hard to detect, so inspection alone cannot be relied on to control it [1].

## What goes into an inspection plan?

| Element | What it records | Public basis |
|---|---|---|
| Scope and identity | Which items are covered, each with its own identifier and drawing references | UK written scheme content [3] |
| Expected damage | The credible damage mechanisms for each item, judged on actual process conditions rather than design data | CSB on Anacortes [1] |
| Method and coverage | The technique, the exact inspection points and how much of the item is examined | US Occupational Safety and Health Administration (OSHA) refinery findings on thickness points [4]; UK Health and Safety Executive (HSE) on dead legs [5] |
| Timing | Maximum interval, next due date, and any examination needed before first use or after repairs to critical parts | US process safety rule [2]; UK written scheme content [3] |
| Preparation and access | The measures needed to prepare the system for safe examination; in-service or out-of-service examination | UK written scheme content [3] |
| Evaluation and follow-up | How results are judged and how equipment outside acceptable limits is dealt with | US process safety rule [2] |
| People and procedures | Training for the people who maintain the equipment and the written procedures they follow | US process safety rule [2] |
| Records | Date, inspector's name, equipment identifier, what was done and the results | US process safety rule [2]; UK examination reports [6] |
| Review | When and why the plan itself is revised | HSE guidance [3] |

The US rule sets the minimum record for each inspection: the date, the name of the person who did it, the equipment's serial number or other identifier, a description of the inspection or test, and its results [2]. In the UK, each examination report must also state the date after which the system may not run without a further examination [6].

## How is an inspection plan built?

1. **List the equipment.** A physical inventory gives each item's location and responsible department, with a field record of size, coating, access, weld seams, openings and alterations [7].
2. **Rank it.** Items are grouped by what their failure would mean for people, regulatory duties and production [7].
3. **Identify the damage.** Each item or circuit gets its credible damage mechanisms, judged on actual operating conditions [1].
4. **Choose methods and coverage.** Inspection is most thorough where several defect types are suspected, the item is critical and there is no inspection history, and lightest for less critical items already inspected [7].
5. **Set the timing.** The US rule asks for inspection frequencies in line with manufacturers' recommendations and good engineering practice, shortened where operating experience shows the need [2]. See How are inspection intervals set for vessels, piping and tanks?
6. **Inspect, record and evaluate.** Baseline results go into each item's file, and engineers use them to set the frequency and extent of reinspection [7].

## Is an inspection plan the same as a written scheme or an RBI assessment?

Not quite. Under UK pressure systems law, the owner or user decides the scope of the written scheme of examination and a competent person draws up or certifies its content [3].

## Where integrity problems show up

| What it finds well | What it can miss or get wrong | In the Library |
|---|---|---|
| **Set thickness points** for each vessel and piping section [4] | OSHA cited procedures that did not fix the number and location of thickness points, or say how to handle odd data such as readings that increase over time [4] | [Thickness measurement location](/glossary/thickness-measurement-location/) · What are condition monitoring locations (CMLs)? |
| **External surfaces** in routine scope [4] | Corrosion under insulation: OSHA cited a sulfur unit where it was not inspected [4] | [What is corrosion under insulation (CUI)?](/library/corrosion-under-insulation/) |
| **Coverage rules** for high-risk features [5] | Spot readings at four points missed local corrosion in a UK relief line that ruptured in 2019 [5] | [Dead leg](/glossary/dead-leg/) |
| **Plan updates** when knowledge changes | Research published in 2003 on nickel and copper in steel for hydrofluoric acid service did not lead to inspection of every component in an existing Philadelphia unit before its 2019 rupture [8] | What is management of change (MOC)? |

Sources: CSB reports on Anacortes (2014) [1] and Philadelphia (2022) [8]; OSHA 3918, 2017 [4]; HSE safety alert CEMHD2-2019 [5].

## Sources

1. [Investigation Report: Catastrophic Rupture of Heat Exchanger (Seven Fatalities), Tesoro Anacortes Refinery, Report No. 2010-08-I-WA, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/6/Tesoro_Anacortes_2014-May-01.pdf?15244)
2. [29 CFR 1910.119, Process safety management of highly hazardous chemicals, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119)
3. [Safety of pressure systems: Pressure Systems Safety Regulations 2000, Approved Code of Practice and guidance (L122, second edition), UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/pubns/priced/l122.pdf)
4. [Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918), US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/Publications/OSHA3918.pdf)
5. [Catastrophic rupture of dead-leg pipe-work (Safety alert, Bulletin No. CEMHD2-2019), UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/safetybulletins/catastrophic-rupture-dead-leg-pipe-work.htm), 2019-08-20
6. [The Pressure Systems Safety Regulations 2000 (SI 2000/128), regulations 8 and 9, legislation.gov.uk, The National Archives (UK)](https://www.legislation.gov.uk/uksi/2000/128/regulation/9)
7. [Organizing A Vessel, Tank, and Piping Inspection Program (National Board Technical Series, first published in the National Board BULLETIN, July 1991), The National Board of Boiler and Pressure Vessel Inspectors (NBBI)](https://www.nationalboard.org/Index.aspx?pageID=164&ID=185)
8. [Investigation Report: Fire and Explosions at Philadelphia Energy Solutions Refinery Hydrofluoric Acid Alkylation Unit, Report No. 2019-04-I-PA, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/20/PES_Final_Report_Published_October_2022_r1.pdf?16845), 2022-10-11

Published by Winda Beacon (https://beacon.winda.ai).