# What are long-lead items?

> Long-lead items are equipment, materials or services that must be bought well before they are needed because delivery takes a long time. The US Department of Energy (DOE) uses this definition in Order 413.3B, where ordering them before construction is approved requires a separate decision known as Critical Decision 3A (CD-3A).

- Label: Fact
- Type: Explainer
- Published: 2026-11-13T09:39:01+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-13
- Canonical: https://beacon.winda.ai/library/long-lead-items/

## Why does it matter?

When a long-lead item sits on the critical path, each week it arrives late can push the project finish date back by a week. The US Government Accountability Office (GAO) defines the critical path as the longest chain of linked activities in a schedule and states that a one-week slip on it moves the finish by one week unless the time is recovered [3]. GAO also warns that showing a supplier delivery as one fixed date, instead of the steps from order to receipt, can understate procurement risk [3]. In oil and gas, the International Association of Oil & Gas Producers (IOGP) started Joint Industry Programme 33 (JIP33) in 2016 in response to industry-wide cost and schedule overruns of more than 40% [4].

## How do public rules define a long-lead item?

This page uses US public-sector rules to define terms, because they are published in full. In a January 2020 newsletter, DOE's Office of Project Management quoted the definition in Order 413.3B: equipment, services or materials bought well ahead of need because of long delivery times [1]. When such a purchase happens before Critical Decision 3 (approval to start construction or execution), DOE calls the step CD-3A and requires a stand-alone decision by the Project Management Executive, outside the normal sequence of critical decisions [1].

The same article sets limits: the federal project director has to weigh design maturity and project risk, a budget document has to request the funds, and the requirements are the same whatever the item costs [1]. A public overview from Fermilab, a DOE national laboratory, adds that CD-3 can be split into CD-3a, CD-3b and so on, so that time-sensitive items whose design is complete go first [2].

## Where does the lead time go?

Lead time is the sum of several steps. The US Federal Acquisition Regulation (FAR) tells contracting officers to consider production time, transportation time and the administrative time to obtain and evaluate offers and award a contract when they set a delivery schedule [5]. For engineered equipment, supplier documents and factory inspections add further steps [6].

| Step | What happens | Public reference |
|---|---|---|
| Inquiry and award | Request for quotation, evaluation of offers, award | FAR 11.402(a) [5] |
| Supplier documents | Drawings and data sent to the purchaser for information or for acceptance, on agreed dates | JIP33 Information Requirements Specification [6] |
| Fabrication | Supplier production, shown in the schedule as its own activity | FAR 11.402(a) [5]; GAO [3] |
| Inspection and testing | Hold and witness points for the purchaser, set by the order's quality requirements | JIP33 Quality Requirements Specification [6] |
| Transport | Shipment to site | FAR 11.402(a) [5] |

Sources: FAR Part 11, as amended to March 2026 [5]; IOGP JIP33 FAQs [6]; GAO-16-89G, 2015 [3].

DOE describes the items behind its own long-lead purchases as specialty equipment from a constrained supply chain with few vendors [1]. In oil and gas, IOGP lists shorter lead times among the expected benefits of standard procurement specifications [6].

## Why are some items ordered before the design is final?

Because the delivery time does not fit into the time left after final design. DOE's project management risk committee restated in 2020 that long-lead purchases are made only when the project timeline needs them, and only after design maturity and risk have been weighed [1]. On oil and gas projects that use JIP33 specifications, IOGP states that the contractor typically issues the equipment request for quotation during front-end engineering design (FEED) or early execution [6].

An early order fixes choices that later work depends on: the specification, the options selected on the data sheet, the quality requirements and the list of supplier documents [6]. If the equipment is changed afterwards in a process covered by the process safety management (PSM) standard of the US Occupational Safety and Health Administration (OSHA), the change goes through management of change and the process safety information has to be updated [7].

## How are long-lead items scheduled and tracked?

GAO's schedule guide calls for an integrated master schedule that covers all government, contractor, subcontractor and key vendor work [3]. It recommends showing a purchased item as a sequence of activities from order to receipt, with the supplier's production as a fabrication activity, so progress can be tracked and risk applied [3]. GAO advises against using fixed time lags to stand in for procurement, because lags cannot be updated with progress [3].

Total float is how far an activity can slip before the finish date moves, and the critical path is usually the path with the least float [3]. A long-lead item becomes critical when its chain of ordering, fabrication, testing, delivery and installation is the longest in the schedule. Following each step after the order is placed is the job of expediting.

## Where integrity problems show up

| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| Ordering equipment before the design is final | DOE requires design maturity and risk to be weighed first [1]; in a PSM-covered process, a later change to the equipment needs management of change and updated process safety information [7] | What is management of change (MOC)? |
| Writing quality and inspection requirements into the order | OSHA PSM requires new equipment, as built, to suit the process it will serve [7]; JIP33 quality requirements set the purchaser's hold and witness points [6] | What is an inspection and test plan (ITP)? |
| Requiring material data, design codes and manufacturer's instructions from the supplier | Process safety information must include materials of construction and design codes, and it sets the limits for judging equipment deficiencies; inspection frequency must be consistent with the manufacturer's recommendations [7] | What should an inspection plan contain? |
| Recording the serial number of the delivered item | Every inspection record must identify the equipment by serial number or another identifier [7] | [What is an asset register and what data should it hold?](/library/asset-register/) |
| Requiring pressure ratings and material records for valves and flanges on gas transmission lines | Such records must be traceable, verifiable and complete and kept as long as the line exists; without them the operator must verify the properties by testing [8] | [What is material traceability?](/library/material-traceability/) |

Sources: DOE, 2020 [1]; IOGP JIP33 FAQs [6]; 29 CFR 1910.119 paragraphs (d), (j) and (l) [7]; 49 CFR 192.607 [8].

## Sources

1. [Promoting Project Management Excellence (newsletter), January 2020: Critical Decision 3A, Long-Lead Procurement (D. Chisenhall), US Department of Energy (DOE), Office of Project Management](https://www.energy.gov/media/203759)
2. [Critical decision overview, Fermi National Accelerator Laboratory (US DOE national laboratory), Office of Project Support Services](https://opss.fnal.gov/?p=174)
3. [Schedule Assessment Guide: Best Practices for Project Schedules (GAO-16-89G), copy hosted by NASA, US Government Accountability Office (GAO)](https://s3vi.ndc.nasa.gov/ssri-kb/static/resources/674404.pdf)
4. [JIP33: About us, International Association of Oil & Gas Producers (IOGP)](https://jip33.iogp.org/about/)
5. [FAR Part 11, Describing Agency Needs (11.401 and 11.402), Acquisition.gov, Federal Acquisition Regulation (FAC 2026-01, effective 2026-03-13)](https://www.acquisition.gov/far/part-11), 2026-03-13
6. [JIP33 FAQs, International Association of Oil & Gas Producers (IOGP)](https://jip33.iogp.org/about/faq/)
7. [29 CFR 1910.119, Process safety management of highly hazardous chemicals, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-29/section-1910.119)
8. [49 CFR 192.607, Verification of Pipeline Material Properties and Attributes: Onshore steel transmission pipelines, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/section-192.607)

Published by Winda Beacon (https://beacon.winda.ai).
