# What is management of change (MOC)?

> Management of change (MOC) is a written procedure for reviewing and approving changes to process chemicals, technology, equipment or procedures in advance. US process safety rules (29 CFR 1910.119(l) and 40 CFR 68.75) apply it to these changes, and to facility changes, except a replacement in kind: one that satisfies the design specification.

- Label: Fact
- Type: Explainer
- Published: 2026-11-14T11:57:56+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-14
- Topics: LNG, Refining
- Canonical: https://beacon.winda.ai/library/management-of-change/

## Why does it matter?

At an olefins plant in Geismar, Louisiana, a reboiler ruptured in 2013, killing 2 workers; 167 injuries were reported [3]. The US Chemical Safety and Hazard Investigation Board (CSB) traced the hazard to block valves installed in 2001: the change review was carried out only after the valves were in service, and it did not identify that they could cut the reboiler off from its pressure relief valve [3]. A similar pattern appears in the 1974 explosion at Flixborough, England, where a temporary bypass pipe was fitted with no drawing, limited calculations and no pressure test; 28 workers died [4].

## What counts as a change?

The US Occupational Safety and Health Administration (OSHA) process safety management standard requires MOC for changes to process chemicals, technology, equipment and procedures, and for facility changes that affect a covered process [1]. The only exemption is a replacement in kind, which paragraph (b) defines as "a replacement which satisfies the design specification" [1]. The Environmental Protection Agency (EPA) Risk Management Program uses the same wording in 40 CFR 68.75 [2].

| Type of change | Examples in public sources | How it is treated |
|---|---|---|
| New or altered equipment | Valves added to reboiler piping (Geismar, 2001); a bypass pipe between two reactors [4] | MOC before the work [3][4] |
| Operating conditions | Running outside the set limits for pressure, temperature or flow | MOC review and approval [1] |
| Temporary change | Temporary bypasses; at California refineries, temporary pipe repairs | MOC with a time limit and a return to the original design [1][7] |
| Work done during a shutdown | Anything other than a replacement in kind made during a turnaround | Through MOC before startup [1] |
| Organization and staffing | At California refineries: staffing cuts, changes to shift length, or added duties of 15% or more | A separate organizational change assessment [7] |
| Like-for-like replacement | A part that meets the design specification | Replacement in kind; no MOC [1] |

Sources: 29 CFR 1910.119 and Appendix C [1]; CSB [3]; HSE [4]; California Title 8, Section 5189.1 [7].

OSHA's nonmandatory guidance in Appendix C warns that temporary changes have caused several catastrophes and tend to become permanent unless their time limit is set and monitored [1].

## What must an MOC review cover?

Paragraph (l)(2) lists five points to address before any change: its technical basis, its effect on safety and health, changes to operating procedures, the time it needs, and who must authorize it [1]. Paragraphs (l)(3) to (l)(5) then require that affected operators, maintenance workers and contract employees are informed and trained before startup, and that process safety information (PSI) and procedures are updated [1]. A modification that changes PSI also needs a pre-startup safety review, which confirms that MOC requirements were met [1][2].

Appendix C suggests a change form covering, among other items, inspection and testing, piping and instrument diagrams (P&IDs), maintenance procedures, training and the duration of temporary changes [1]. A checklist signed by an authorized person may suit a minor, well-understood change; a complex design change may call for a formal hazard evaluation approved by operations, maintenance and safety [1]. UK HSE guidance adds that a change can affect plant far from where it is made, and that written rules should decide what level of hazard and operability study (HAZOP) a modification gets [5].

## Where do MOC programs fail?

The Geismar case shows three failure points [3]. The valves went in during a shutdown in early 2001, the pre-startup review was signed on 1 February, but the MOC was opened only on 2 March and approved on 6 April. The reviewers answered a yes, no or not-applicable checklist without identifying the overpressure hazard, and the P&IDs did not show the new valves. The CSB concluded that MOC must be done before a change is made in the field and should not be treated as paperwork [3].

The problem is not rare. In the first year of OSHA's refinery National Emphasis Program, management of change was one of five elements that together accounted for nearly 80% of the violations found [8]. In an HSE analysis of 34 control system incidents, 20% of the primary causes were changes made after commissioning [6]. Sites in OSHA's Voluntary Protection Programs (VPP) track overdue, open and approved MOCs; one set a maximum of 180 days for any temporary MOC [9].

## Where integrity problems show up

| Element or step | Integrity link | In the Library |
|---|---|---|
| Reviewing overpressure protection | At Geismar the new valves could isolate a reboiler from its relief valve, and the review did not catch it [3] | [What does a pressure relief valve do?](/library/pressure-relief-valve/) |
| Updating process safety information | PSI includes materials of construction, P&IDs and relief design basis, and must be updated after a change [1]; the Geismar P&IDs did not show the new valves [3] | [What is process safety management (PSM)?](/library/process-safety-management/) |
| Updating inspection and test plans | Appendix C lists inspection and testing, and mechanical integrity programs, among the items a change review should address [1] | [What is mechanical integrity (MI)?](/library/mechanical-integrity/) |
| Damage mechanism review before a major change | California refineries must review or carry out a damage mechanism review before a major change and file its findings with the MOC [7] | [What is a damage mechanism review?](/library/damage-mechanism-review/) |
| Operating outside set limits | Appendix C treats operation outside established pressure, temperature or flow limits as a change needing review [1] | [What are integrity operating windows (IOWs)?](/library/integrity-operating-windows/) |
| Temporary repairs | California refinery MOC procedures must cover temporary repairs, including temporary pipe repairs [7] | [What is fitness-for-service (API 579-1/ASME FFS-1)?](/library/fitness-for-service/) |
| Changes to control and safety systems | 20% of primary causes in HSE's control system incident analysis were changes after commissioning [6] | [What is a safety instrumented system (SIS)?](/library/safety-instrumented-system/) |

Sources: 29 CFR 1910.119 [1]; CSB Geismar case study, 2016 [3]; HSE HSG238 [6]; California Title 8, Section 5189.1 [7].

## Sources

1. [29 CFR 1910.119, Process safety management of highly hazardous chemicals, paragraphs (b), (d), (i), (l) and Appendix C, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119)
2. [40 CFR 68.75, Management of change, and 68.77, Pre-startup review, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-C/part-68/subpart-D)
3. [Williams Geismar Olefins Plant Reboiler Rupture and Fire, Geismar, Louisiana, Case Study No. 2013-03-I-LA, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/6/Williams_Case_Study_2016-10-19.pdf?15713)
4. [Flixborough (Nypro UK) Explosion 1st June 1974, UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/comah/sragtech/caseflixboroug74.htm)
5. [Plant modification / Change procedures (COMAH technical measures), UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/comah/sragtech/techmeasplantmod.htm)
6. [Out of control: Why control systems go wrong and how to prevent failure, HSG238, second edition, UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/pubns/priced/hsg238.pdf)
7. [California Code of Regulations, Title 8, Section 5189.1, Process Safety Management for Petroleum Refineries, California Department of Industrial Relations](https://www.dir.ca.gov/title8/5189_1.html)
8. [Refinery NEP First Year Inspection Results, US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/sites/default/files/nep_first_year_findings_16apr2009.pdf)
9. [The Use of Metrics in Process Safety Management (PSM) Facilities, Fact Sheet FS-3896, US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/sites/default/files/publications/OSHA3896.pdf)