# What is a material requisition?

> A material requisition describes what a project must buy: the items, quantities and specifications, and the checks and documents due from the supplier. On oil and gas orders that use Joint Industry Programme 33 (JIP33) specifications, the request for quotation adds technical, data sheet, quality and information requirements to the commercial terms.

- Label: Fact
- Type: Explainer
- Published: 2026-11-13T09:39:01+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-13
- Canonical: https://beacon.winda.ai/library/material-requisition/

## Why does it matter?

Oil and gas operators have historically sent suppliers a different set of requirements with each order, often hundreds of pages long, according to the International Association of Oil & Gas Producers (IOGP) [1]. IOGP started JIP33 in 2016 in response to industry-wide cost and schedule overruns of more than 40% [1]. The requisition is where those requirements are chosen. What it asks the supplier to prove and to deliver also becomes part of the record that a plant's process safety information and inspection program rely on later [7].

## What does a material requisition contain?

No single public template exists, so this page uses two public references. The US Federal Acquisition Regulation (FAR) sets how a buyer describes a need, and IOGP's JIP33 shows how oil and gas equipment orders are structured [2][3]. Under FAR, a requirement is stated as far as practicable in terms of the function to be performed, the performance required or the essential physical characteristics, and voluntary consensus standards are used instead of buyer-unique ones where they exist [3].

| Part of the requisition | What it states | Public reference |
|---|---|---|
| Items and quantities | What is needed and how much, usually counted in the material take-off | Construction Industry Institute (CII), 1987 [5] |
| Technical requirements | Function, performance or physical characteristics, based on industry standards plus any supplementary requirements | FAR 11.002 and 11.101 [3]; JIP33 technical requirements specification [2] |
| Data sheet | Project choices among defined options, for example material class and quality specification level for a ball valve | JIP33 procurement data sheet [2] |
| Quality requirements | The supplier's quality management system, inspection and testing, and hold and witness points, at one of four risk levels | JIP33 quality requirements specification [2] |
| Supplier documents and data | Each deliverable and its timing, marked for information, for acceptance or not required | JIP33 information requirements specification [2] |
| Delivery | The required date; FAR treats time of delivery as an essential contract element that must be realistic | FAR 11.401 [3] |

Sources: FAR Part 11, as amended to March 2026 [3]; IOGP JIP33 FAQs [2]; CII tutorial abstract, 1987 [5].

## Where does the requisition sit in the procurement sequence?

Research by the Construction Industry Institute (CII) describes materials management as one linked chain: take-off, requisitioning, purchasing, expediting, warehousing and issue of materials to the crafts, for both bulk materials and engineered equipment [5]. The requisition is the hand-off from the people who define the need to the people who buy it.

In US federal terms, an acquisition begins when the need is established and includes describing the requirement [4]. The request sent to suppliers is a solicitation: any request to submit offers or quotations [4]. Once a supplier is chosen, the order becomes a contract, and FAR lists purchase orders among the forms a contract can take [4].

On oil and gas projects that use JIP33, IOGP states that the contractor prepares the complete request for quotation, typically during front-end engineering design (FEED) or early execution [2]. The package combines the contract or purchase order terms with the four JIP33 documents described above [2]. How the offers are then compared is covered in [What is technical bid evaluation in oil and gas?](/library/technical-bid-evaluation/).

## How do standard specifications change the requisition?

With JIP33, the purchaser does not write new technical or quality requirements for each order. It selects and configures options from defined templates [2]. Project-specific additions go into a section for purchase-order-specific information requirements, which IOGP says is ideally kept to a minimum [2].

The specifications sit on top of international standards, such as those of the American Petroleum Institute (API), the American Society of Mechanical Engineers (ASME) and the International Organization for Standardization (ISO), and replace the separate procurement specifications that each operator used before [2]. IOGP states that JIP33 aims to cover about 80% of procurement scope and that the documents are revised in step with their parent standards, typically about every five years [2]. A supplier that wants to deviate on a live project raises it with its client [2].

The same preference appears in US federal rules: agencies have to use voluntary consensus standards where they exist, rather than government-unique standards, unless that is impractical or inconsistent with law [3].

## Where integrity problems show up

| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| Stating the material grade for the service | Material that does not match the service can fail early: at Texas City, Texas, in 2005, a carbon steel elbow in hydrogen piping that called for 1.25% chromium steel ruptured after about three months [6] | What is positive material identification (PMI)? |
| Requiring material certificates and records | On gas transmission pipelines, records of diameter, wall thickness, seam type and grade must be traceable, verifiable and complete for the life of the line; without them the operator must verify by testing [8] | [What is material traceability?](/library/material-traceability/) |
| Setting quality, inspection and test requirements | In a process under the US Occupational Safety and Health Administration (OSHA) process safety management (PSM) standard, new equipment as built must suit the process it will serve [7] | What is an inspection and test plan (ITP)? |
| Requiring data sheets, design codes and the manufacturer's instructions | Process safety information must include materials of construction and design codes, and inspection frequency must be consistent with the manufacturer's recommendations [7] | What should an inspection plan contain? |
| Requisitioning spare parts and maintenance materials | Under PSM, maintenance materials and spare parts must also suit the process they are used in [7] | What is mechanical integrity (MI)? |

Sources: US Chemical Safety and Hazard Investigation Board (CSB) safety bulletin 2005-04-B, 2006 [6]; 29 CFR 1910.119 paragraphs (d) and (j) [7]; 49 CFR 192.607 [8].

## Sources

1. [JIP33: About us, International Association of Oil & Gas Producers (IOGP)](https://jip33.iogp.org/about/)
2. [JIP33 FAQs, International Association of Oil & Gas Producers (IOGP)](https://jip33.iogp.org/about/faq/)
3. [FAR Part 11, Describing Agency Needs (11.002, 11.101, 11.401), Acquisition.gov, Federal Acquisition Regulation (FAC 2026-01, effective 2026-03-13)](https://www.acquisition.gov/far/part-11), 2026-03-13
4. [FAR 2.101, Definitions (acquisition, solicitation, contract), Acquisition.gov, Federal Acquisition Regulation (FAC 2026-01, effective 2026-03-13)](https://www.acquisition.gov/far/2.101), 2026-03-13
5. [Materials Management Microcomputer Tutorial, Users Manual (Construction Industry Institute, 1987): abstract record, US National Institute of Standards and Technology (NIST), FireDOC](https://firedoc.nist.gov/article/gXcyXYQBWEcjUZEYp66o)
6. [Safety Bulletin No. 2005-04-B: BP Texas City, TX Refinery Fire, Positive Material Verification: Prevent Errors During Alloy Steel Systems Maintenance, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/20/RHUBulletin1.pdf?13897), 2006-10-12
7. [29 CFR 1910.119, Process safety management of highly hazardous chemicals, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-29/section-1910.119)
8. [49 CFR 192.607, Verification of Pipeline Material Properties and Attributes: Onshore steel transmission pipelines, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/section-192.607)