# How does procurement work on oil and gas projects?

> Procurement on an oil and gas project turns engineering requirements into equipment and materials that are bought, inspected, delivered and documented. The steps run from requisition and supplier selection through solicitation, technical and commercial evaluation, purchase order, expediting and inspection to document handover. Companies set their own procedures; some use IOGP's standardized JIP33 procurement specifications.

- Label: Fact
- Type: Explainer
- Published: 2026-11-13T09:44:04+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-13
- Canonical: https://beacon.winda.ai/library/procurement-in-oil-and-gas/

## Why does it matter?

The International Association of Oil & Gas Producers (IOGP) started Joint Industry Programme 33 (JIP33) in 2016 in response to industry-wide cost and schedule overruns of more than 40%, and aimed it at the specifications used to buy equipment [1]. Until then, IOGP notes, each order came with its own operator requirements, frequently running to hundreds of pages and varying even between one company's projects [1]. Procurement also carries safety duties: US process safety rules require new equipment, as fabricated, and later spare parts and maintenance materials to be suitable for their service [7].

## What are the steps in project procurement?

No single public rule sets the steps for a private oil and gas project. World Bank rules, used here only for definitions, describe the procurement process as running from identifying a need through planning, specifications, selection and contract award to contract management [9]. Research by the Construction Industry Institute (CII) on industrial projects describes materials management systems that tie together take-off, vendor evaluation, purchasing, expediting, warehousing and distribution [4][5].

| Step | What happens | Source | In the Library |
|---|---|---|---|
| 1. Define the requirement | Engineering lists quantities and writes specifications and data sheets | [4][9] | [What is a material take-off (MTO)?](/library/material-take-off/), [What is a material requisition?](/library/material-requisition/) |
| 2. Choose who may bid | Suppliers are evaluated or prequalified | [4][5][8] | [How are suppliers prequalified for oil and gas projects?](/library/supplier-prequalification/) |
| 3. Solicit offers | The buyer issues a request for bids, quotations or proposals with the specification package | [2][8] | [ITB vs RFQ vs RFP in oil and gas procurement](/library/itb-rfq-rfp/) |
| 4. Evaluate | Technical evaluation first, then the commercial comparison of acceptable bids | [9] | [What is technical bid evaluation in oil and gas?](/library/technical-bid-evaluation/) |
| 5. Award and expedite | The order is placed, then followed to protect delivery dates | [4][5] | [What is expediting in project procurement?](/library/expediting/) |
| 6. Inspect and receive | Surveillance and inspection at the supplier, then quality control on receipt | [1][6] | What is an inspection and test plan (ITP)? |
| 7. Hand over information | Supplier documents and data go to the owner for operation and maintenance | [1][3] | What is vendor document management? |

Timing of the take-off shows up in waste. CII research summarized in 1999 found that bulk material surplus can usually be held to 1% or less when take-off uses final design drawings, but can pass 10% when take-off is done earlier, and that an effective materials management system cuts the surplus of bulk materials from 5% to 10% down to about 1% to 3% [6].

## Who takes part in procurement on an oil and gas project?

Engineering, procurement and construction (EPC) projects run for long periods and involve project owners, contractors, subcontractors and vendors [10]. Under a lump-sum turnkey contract the contractor is responsible for executing the project, and a 2021 study notes that owners can use this form to pass project risk to the contractor [10]. Which party buys which items, and who approves the technical evaluation, is set by each contract.

CII's 1999 guidance puts responsibility for conforming to the requirements on the supplier, with the buyer setting the level of surveillance and inspection and checking quality on receipt [6]. JIP33's quality requirements specification states the supplier's quality system and the purchaser's involvement in inspection and testing [1].

## How do requirements and documents travel with an order?

JIP33 packages purchase requirements into four documents: a supplement to an industry standard, an information requirements specification listing the documents and data the supplier must deliver, a quality requirements specification, and a procurement data sheet for project choices [1]. IOGP advises naming the specifications in the basis of design, then carrying them through front-end engineering design (FEED), execution and the tendering packages [2]. As of October 2026, JIP33 reports 60 published specifications intended to cover about 80% of procurement scope; companies add requirements for the rest [1][2].

At the other end, IOGP's CFIHOS (Capital Facilities Information Handover Specification) standardizes how operators, contractors, manufacturers and suppliers hand over data and documents so a facility can be operated, maintained and decommissioned [3]. In plants covered by US process safety management, that information includes each item's materials of construction and design codes, and a pre-startup safety review must confirm that equipment matches the design specifications [7].

## Where integrity problems show up

| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| Alloy components are verified on receipt but not after later handling | At a refinery in Texas City, Texas, in 2005, a carbon steel elbow fitted during maintenance where 1.25% chromium steel was required failed by high temperature hydrogen attack after fewer than 3,000 hours; the site's procedure verified alloy parts at warehouse receipt and issue, not during maintenance [11] | What is positive material identification (PMI)? |
| Spare parts and maintenance materials are bought | US process safety rules require them to be suitable for the process application [7] | [What is material traceability?](/library/material-traceability/) |
| Material records are left out of the information requirements | Where required, US onshore steel gas transmission operators without traceable, verifiable and complete records must verify material properties through tests and examinations [13] | What is a mill test certificate (EN 10204 3.1 and 3.2)? |
| Post-weld heat treatment is dropped from a purchase specification | OSHA guidance reports cracking in amine and wet hydrogen sulfide service at or near welds, less often where welds were heat treated [12] | What is post-weld heat treatment (PWHT)? |
| Vendor documents are not handed over | Process safety information must include materials of construction and design codes [7] | [What documents are handed over when a project is completed?](/library/handover-documentation/) |

Sources: CSB Safety Bulletin 2005-04-B, 2006 [11]; 29 CFR 1910.119(d), (j)(6) [7]; 49 CFR 192.607 [13]; OSHA Technical Manual, Section IV, Chapter 3 [12].

## Sources

1. [JIP33 About us, International Association of Oil & Gas Producers (IOGP), Joint Industry Programme 33](https://jip33.iogp.org/about/)
2. [JIP33 FAQs, International Association of Oil & Gas Producers (IOGP), Joint Industry Programme 33](https://jip33.iogp.org/about/faq/)
3. [About CFIHOS, International Association of Oil & Gas Producers (IOGP), Joint Industry Programme 36 (CFIHOS)](https://www.jip36-cfihos.org/about/)
4. [Costs and Benefits of Materials Management Systems (Publication 7-1), catalog record and abstract, Construction Industry Institute (CII), via NIST FireDOC](https://firedoc.nist.gov/article/l3cyXYQBWEcjUZEYo6tK)
5. [Project Materials Management Handbook, catalog record and abstract, Construction Industry Institute (CII), via NIST FireDOC](https://firedoc.nist.gov/article/gncyXYQBWEcjUZEYp66p)
6. [Procurement and Materials Management: A Guide to Effective Project Execution (IR7-3), abstract and key findings, Construction Industry Institute (CII)](https://construction-institute.org/procurement-and-materials-management-a-guide-to-effective-project-execution)
7. [29 CFR 1910.119, Process safety management of highly hazardous chemicals, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119)
8. [Procurement Regulations for IPF Borrowers (Seventh Edition), The World Bank](https://thedocs.worldbank.org/en/doc/c84273d1b230aeb2b0b8134de5dc8cd7-0290012025/original/Procurement-Regulations-7th-Edition-Sep-2025.pdf)
9. [Procurement Guidance: Evaluating Bids and Proposals, Including Use of Rated Criteria for Procurement of Goods, Works, and Non-Consulting Services (Third Edition), The World Bank](https://thedocs.worldbank.org/en/doc/9dcb7971706bf29b2732779c39922b77-0290012025/original/Evaluating-Bids-and-Proposals-with-Rated-Criteria-Feb-4-2025.pdf)
10. [AI and Text-Mining Applications for Analyzing Contractor's Risk in Invitation to Bid (ITB) and Contracts for Engineering Procurement and Construction (EPC) Projects (S.J. Choi, S.W. Choi, J.H. Kim, E.-B. Lee), Energies 14(15), 4632, MDPI (peer-reviewed journal); authors at Pohang University of Science and Technology (POSTECH)](https://doi.org/10.3390/en14154632), 2021-07-30
11. [Safety Bulletin No. 2005-04-B, BP Texas City, TX Refinery Fire: Positive Material Verification: Prevent Errors During Alloy Steel Systems Maintenance, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/20/RHUBulletin.pdf), 2006-10-12
12. [OSHA Technical Manual, Section IV, Chapter 3: Pressure Vessel Guidelines, US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/otm/section-4-safety-hazards/chapter-3)
13. [49 CFR 192.607, Verification of pipeline material properties and attributes: Onshore steel transmission pipelines, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/subtitle-B/chapter-I/subchapter-D/part-192/subpart-L/section-192.607)
14. [Attributes of Materials Management Systems (SD-1), abstract and key findings, Construction Industry Institute (CII)](https://www.construction-institute.org/attributes-of-materials-management-systems)