# Risk-based inspection vs time-based inspection

> Time-based inspection examines equipment at fixed intervals, usually set by equipment type or a maximum in a code or rule. Risk-based inspection (RBI) sets each item's interval, method and location from its probability and consequence of failure, so intervals can shorten or lengthen. Where rules set maximum intervals, as in US pipeline rules, RBI works inside them.

- Label: Fact
- Type: Explainer
- Published: 2026-11-13T03:06:14+09:00
- Updated: 2026-11-14T15:00:00+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-13
- Topics: Pipelines, Refining, Upstream and offshore
- Canonical: https://beacon.winda.ai/library/rbi-vs-time-based-inspection/

## Why does it matter?

For covered US gas transmission pipeline segments, the maximum reassessment interval is 7 calendar years, with a possible 6-month extension on notice; within that cap, an operator using pressure tests or in-line inspection bases each interval on the segment's identified threats and the results of its last assessment and risk analysis, or on the intervals set in the American Society of Mechanical Engineers (ASME) standard B31.8S [4]. Hazardous liquid pipeline segments that could affect high consequence areas are assessed at five-year intervals of no more than 68 months, set according to the risk each segment poses [5]. In the UK, a written scheme of examination, drawn up or certified by a competent person, fixes the nature and frequency of examination [3]. The Health and Safety Executive (HSE) guidance on those rules lets separate parts of one system run on separate intervals, according to how much risk each part carries [1]. The practical question is rarely RBI or a time limit; it is how risk sets the interval inside the limit.

## Time-based vs risk-based inspection at a glance

| | Time-based inspection | Risk-based inspection |
|---|---|---|
| What sets the interval | A fixed period by equipment type, or a maximum in a code or rule; older UK law, for example, put most steam plant on a 14-month cycle [1][7] | An estimate of risk, the probability of failure multiplied by its consequences [8] |
| What it plans | Mainly when; scope rests on codes, experience and judgement [8] | Which items get the inspection effort, in proportion to their share of the risk, and how often and how well each is inspected [8] |
| Use of condition | Work is scheduled at regular intervals whatever the equipment's actual condition [2] | Condition and history feed the interval; in the UK the competent person reviews it after an examination and may change it, for instance to examine ageing plant more often [1] |
| Data needed | Service age, or the date of the last examination [2] | UK guidance has the interval weigh the item's record and present condition, operating conditions, fluid quality, the owner's inspection standards and any on-line monitoring [1]; PNNL's pilot work also counted and located welds, from plant documents checked on walkdowns [8] |
| Unfamiliar equipment | The period set for its equipment type, as older UK law did for some kinds of plant [1] | Little failure data, so likelihood is uncertain; a 2026 study of an industrial electrolyzer built a model meant to be updated as field data arrive [2] |
| After each inspection | The next date follows the set period [2] | Results revise the estimate: inspection and repair lower the modeled failure probability at each cycle [8] |
| Main weakness | Programs built on experience and judgement consider risk only implicitly [8] | Only as good as its inputs: a ranking that assumes constant failure rates ignores damage that grows with time in service [2] |
| Typical documents | American Petroleum Institute (API) 570 service classes with maximum thickness measurement intervals, as summarized by the Occupational Safety and Health Administration (OSHA) [7]; US pipeline maximum reassessment intervals [4][5] | API RP 580 and RP 581 [10] |

Sources: HSE L122, 2014 [1]; OSHA 3918, 2017 [7]; Pacific Northwest Laboratory (PNNL), 1992 [8]; Collina and others, 2026 [2]; 49 CFR 192.939 and 195.452 [4][5]; API 2025 catalog [10].

## When is time-based inspection used?

- **Where a rule sets fixed or maximum periods.** US pipeline integrity rules set maximum reassessment intervals [4][5].
- **As a ceiling inside an inspection code.** OSHA's 2017 review describes API 570 as grouping piping into service classes, each with a maximum thickness measurement interval, with the actual interval set by the inspector or piping engineer within that limit [7].
- **As a starting guide.** HSE notes that the competent person may still look to the maximum periods that earlier UK law set for some kinds of equipment when drawing up a scheme, where they fit the system [1].
- **Historically, as the default.** A 1992 Pacific Northwest Laboratory (PNNL) paper for an ASME task force noted that in-service inspection programs were built mainly on experience and engineering judgement and took account of risk only implicitly, if at all [8].

## When is risk-based inspection used?

- **To prioritize many items.** API's catalog entry for its RBI software lists the program's aims as screening units for high risk, estimating a risk value for each item, ranking equipment and designing an effective inspection program [10].
- **Under UK pressure systems law.** The written scheme sets what is examined and how often [3], and HSE's guidance asks for enough examinations to catch deterioration early, with intervals that may differ from part to part by risk [1].
- **Under US process safety rules.** Inspection frequency must follow manufacturers' recommendations and good engineering practice, and be shorter if operating experience shows the need (29 CFR 1910.119(j)(4)) [6]; OSHA names API 580 among examples of good practice for vessel and piping inspection [7].
- **On new kinds of plant.** A 2026 open-access study adapted the API 580 approach to a hydrogen-fuelled glass plant, ranking its components, including a 3 MW electrolyzer, to decide where maintenance should go first [2].

## A common mix-up

RBI is not simply a way to stretch intervals. In PNNL's 1992 pilot on a nuclear plant's emergency feedwater system, the risk ranking lifted one low-pressure, low-temperature run of suction piping to the middle of the list, because its failure alone could disable the whole system [8]. In the UK, a competent person who judges that waiting for the scheduled date would add significant risk should revise the scheme and set an earlier date [1]. Nor does a longer interval take effect at once: a review that changes the frequency does not move the due date already written in the last examination report, which stands unless it is formally postponed [1].

## Where integrity problems show up

| Decision | Data it depends on | What goes wrong without it |
|---|---|--- |
| Ranking equipment with little history | Failure and consequence data that match the real equipment and its scale | Collina and others, 2026: leaks from the hydrogen separator of an industrial-scale electrolyzer gave larger hazard distances than published laboratory-scale studies [2] |
| Extending an interval | Inspection results, damage rates and a competent person's review of the written scheme | HSE: a change of frequency does not move an examination date already set; only a formal postponement can [1][3] |
| Fixing a pipeline reassessment interval | Identified threats and the results of the last assessment | US rules require intervals based on threats or risk, within 7 calendar years for gas and 68 months for liquids [4][5] |
| Keeping a fixed regime on fast, local damage | Mechanism-specific locations and coverage | UK refinery, 2019: regular thickness checks at four points missed very local corrosion in a relief line, which ruptured; HSE asks that frequency and scrutiny reflect aggressive local damage [9] |
| Building a program from experience alone | Explicit estimates of probability and consequence | PNNL, 1992: such programs considered risk at best implicitly [8] |

Sources: HSE L122, 2014 [1]; Pressure Systems Safety Regulations (PSSR) 2000, regulation 8 [3]; 49 CFR 192.939 and 195.452(j) [4][5]; HSE safety alert CEMHD2-2019 [9]; PNNL, 1992 [8]; Collina and others, 2026 [2].

## Sources

1. [Safety of pressure systems: Pressure Systems Safety Regulations 2000, Approved Code of Practice and guidance (L122, second edition), UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/pubns/priced/l122.pdf)
2. [Toward the application of the Risk-Based Maintenance approach to a hydrogen-fueled manufacturing plant (G. Collina and others), International Journal of Hydrogen Energy 238, 155318, open access under CC BY 4.0, Elsevier, via OSTI.gov (co-authored by the US National Laboratory of the Rockies)](https://www.osti.gov/pages/servlets/purl/3364031)
3. [The Pressure Systems Safety Regulations 2000 (SI 2000/128), regulation 8, legislation.gov.uk, The National Archives](https://www.legislation.gov.uk/uksi/2000/128/regulation/8)
4. [49 CFR 192.939, What are the required reassessment intervals?, eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/section-192.939)
5. [49 CFR 195.452, Pipeline integrity management in high consequence areas, paragraph (j), eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-49/section-195.452)
6. [29 CFR 1910.119, Process safety management of highly hazardous chemicals, paragraph (j)(4), eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119)
7. [Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918), US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/sites/default/files/publications/OSHA3918.pdf)
8. [Risk Based ASME Code Requirements (B. F. Gore, T. V. Vo, K. R. Balkey), PNL-SA-21211, OSTI 7129942, Pacific Northwest Laboratory, US Department of Energy, via OSTI.gov](https://www.osti.gov/servlets/purl/7129942)
9. [Catastrophic rupture of dead-leg pipe-work (Safety alert, Bulletin No. CEMHD2-2019), UK Health and Safety Executive (HSE)](https://www.hse.gov.uk/safetybulletins/catastrophic-rupture-dead-leg-pipe-work.htm), 2019-08-20
10. [2025 Publications Catalog (entries for RP 580 and RP 581, and API RBI software) (RP 580, 4th edition, August 2023; RP 581, 3rd edition, April 2016), American Petroleum Institute (API)](https://www.api.org/-/media/files/publications/2025-catalog/2025_pubs%20catalog.pdf)