# How is a refinery turnaround planned?

> A refinery turnaround is planned over about 1 to 3 years. Planners set the timing, collect and screen work requests into a fixed scope, take modifications through management of change, order long-lead equipment, book contractors, and build schedules and procedures. The US Energy Information Administration (EIA) describes the basic scope as settled about 10 to 12 months before shutdown.

- Label: Fact
- Type: Explainer
- Published: 2026-11-14T12:02:06+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-14
- Topics: Refining
- Canonical: https://beacon.winda.ai/library/turnaround-planning/

## Why does it matter?

At a refinery in Richmond, California, recommendations to replace a carbon steel crude unit line in sulfidation service were denied for the 2007 and 2011 turnarounds, and the line ruptured on 6 August 2012 [2]. The US Chemical Safety and Hazard Investigation Board (CSB) found that the turnaround planning group judged requests against fixed criteria, and that inspection data taken on more corrosion-resistant fittings suggested the line could run until 2016 [2]. Nineteen employees were caught in the vapor cloud, and about 15,000 people from nearby communities sought medical treatment [2]. Scope decisions are hard to reverse later: EIA notes that once labor, equipment and materials are committed, changing a turnaround plan is costly [1].

## What are the main planning milestones?

EIA's 2007 report set out a generic timeline for a major fluid catalytic cracking (FCC) turnaround held every 5 years [1]. The table restates it, with the points where US process safety management (PSM) rules apply.

| Time before shutdown | Main decisions |
|---|---|
| About 30 to 36 months | Decide whether new technology or long-lead equipment is included; new vessels, compressors or turbines can take 2 years or more to design and build, and special cranes must be reserved [1] |
| About 24 months | Define and approve the project concept and upgrades; start engineering for modifications and their management of change (MOC) review [1] |
| About 18 months | Inspect equipment and review systems to define the work in detail; buy long-lead materials; begin contractor negotiations [1] |
| About 10 to 12 months | Settle the basic scope of maintenance and minor modifications; contract outside shops for work on compressors, turbines, control and relief valves, exchangers and critical piping [1] |
| At least 6 months | Complete final engineering and operating plans for each change so the MOC review can finish [1] |
| Final months | The turnaround organization takes over schedules and often sets up on site; crude purchases and product supply are adjusted [1]; shutdown procedures are reviewed before the event, as the Center for Chemical Process Safety (CCPS) recommends [5] |

Without major new equipment, EIA says main planning starts about 2 years ahead [1]. At large refineries, EIA notes, the team that runs shutdowns can be a standing group that moves from one unit's turnaround to the next, using scheduling software that can coordinate thousands of jobs [1].

## How is the work scope built and screened?

Requests reach the planners from several directions, including inspection and metallurgy recommendations, reliability programs and improvement projects [1][2]. At Richmond, a document of predetermined criteria set which items were accepted automatically; less urgent work, and work that could be done with the unit running or at the next turnaround, was left out by default [2].

The CSB found three weaknesses in how that screening worked [2]:

- **Data that could not show the risk.** Thickness readings came from high-silicon fittings that corroded slowly; no condition monitoring location was placed on the low-silicon component that failed [2].
- **A rule that blocked data gathering.** Discretionary work needed hard data from the equipment, even when its purpose was to produce that data through 100 percent component inspection based on industry guidance [2].
- **No owner for the exception route.** An informal appeal to the unit manager existed but was never used, and no senior manager was assigned to see the sulfidation recommendations into the scope [2].

During the 2011 turnaround, thinning in a 12-inch section of the same line was severe enough to need immediate replacement, but only the parts with supporting data were replaced [2]. After the rupture, inspecting all 4,600 crude unit piping components susceptible to sulfidation found 4 more with higher corrosion rates than the piping beside them [2].

## What must be ready before the shutdown?

- **Changes.** Changes made during a turnaround, other than replacement in kind, go through MOC, with drawings and procedures updated before startup [4].
- **Procedures.** Written procedures must cover normal shutdown and startup following a turnaround, and operating procedures must be certified annually [4][5]. At Superior, Wisconsin, the shutdown procedure used for the 2018 turnaround reversed the pressure balance that the FCC licensor's guidance required [3].
- **Contractors and permits.** The PSM contractor paragraph covers turnaround work; employers must evaluate contractors' safety performance and tell them of the process hazards, and hot work needs a permit [4].
- **Startup checks.** A facility modified enough to change its process safety information needs a pre-startup safety review before highly hazardous chemicals are introduced [4].

## Where integrity problems show up

| Element or step | Integrity link | In the Library |
|---|---|---|
| Scope criteria | Recommendations to fully inspect or replace the section that later failed were rejected under the criteria [2] | [How is inspection scope set for a turnaround?](/library/turnaround-inspection-scope/) |
| Inspection data behind scope decisions | Readings on slow-corroding fittings were applied to the whole line, including a faster-corroding component [2] | [What are condition monitoring locations (CMLs)?](/library/condition-monitoring-locations/) |
| Findings during the turnaround | Severe thinning found in 2011 led to partial replacement only [2] | [What is sulfidation (high-temperature sulfur corrosion)?](/library/sulfidation/) |
| Condition data between turnarounds | The CSB recommended that slide valve monitoring data be reviewed quarterly to support decisions such as shortening the turnaround cycle [3] | [What is mechanical integrity (MI)?](/library/mechanical-integrity/) |
| Outside shop work | Relief valves, control valves, exchangers and critical piping are contracted out about 10 to 12 months ahead [1] | [What does a pressure relief valve do?](/library/pressure-relief-valve/) |
| Modifications and startup | MOC before the change and a pre-startup safety review before restart [4] | [What is a pre-startup safety review (PSSR)?](/library/pre-startup-safety-review/) |

Sources: EIA, SR/OOG/2007-01 [1]; CSB Richmond report, 2015 [2]; CSB report No. 2018-02-I-WI, 2022 [3]; 29 CFR 1910.119 [4].

## Sources

1. [Refinery Outages: Description and Potential Impact on Petroleum Product Prices (SR/OOG/2007-01), US Energy Information Administration (EIA)](https://www.eia.gov/analysis/requests/2007/sroog200701.pdf)
2. [Final Investigation Report: Chevron Richmond Refinery Pipe Rupture and Fire, US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/17/Chevron_Final_Investigation_Report_2015-01-28.pdf?15397), 2015-01-28
3. [Investigation Report: FCC Unit Explosion and Asphalt Fire at Husky Superior Refinery, Superior, WI (Report No. 2018-02-I-WI), US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/20/Husky_Superior_Refinery_Report_2022-12-23_(1)1.pdf?16884), 2022-12-23
4. [29 CFR 1910.119, Process safety management of highly hazardous chemicals (paragraphs (f), (h), (i), (k), (l) and Appendix C), eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119)
5. [Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918), US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/Publications/OSHA3918.pdf)

Published by Winda Beacon (https://beacon.winda.ai).