# What is a turnaround (planned plant shutdown)?

> A turnaround is a scheduled, recurring shutdown of one or more process units to inspect, repair and replace equipment that cannot be worked on in service. Catalyst changes and upgrades are often done at the same time. In 2007 the US Energy Information Administration (EIA) reported key refinery units on 3 to 5 year cycles, offline for weeks to months.

- Label: Fact
- Type: Explainer
- Published: 2026-11-14T12:02:06+09:00
- By: Jun Zhong
- Researched and drafted by: Beacon's AI newsroom
- Checked by: Jun Zhong on 2026-11-14
- Topics: LNG, Refining
- Canonical: https://beacon.winda.ai/library/turnaround/

## Why does it matter?

EIA reported in 2007 that as many as 1,500 to 2,000 contract workers may arrive for a major refinery unit turnaround, and that it is not unusual for the number of people on site to more than triple [1]. Much of that work is done during shutdown and startup, which the US Chemical Safety and Hazard Investigation Board (CSB) calls transient operations because the process is changing state and can present hazards not seen in normal running [2]. In April 2018, a fluid catalytic cracking (FCC) unit at a refinery in Superior, Wisconsin, exploded while it was being shut down for a turnaround, with about 800 to 900 people on site; 36 workers were injured [2]. Turnarounds happen so rarely that the board operator on shift was shutting down that FCC unit for the first time [2].

## What work is done during a turnaround?

EIA describes two groups of work: maintenance that restores equipment, and improvements that can only be installed while a unit is down [1].

| Type of work | Examples |
|---|---|
| Routine inspection | Inspections for corrosion, wear, deposits and the condition of piping and electrical systems [1] |
| Special inspection | Checks on major vessels, pumps or rotating equipment where the last run showed something abnormal [1] |
| Repair and replacement | Worn parts, whole pumps, instruments [1] |
| Catalyst and process materials | Replacing catalyst used up during the run [1] |
| Improvement projects | New or upgraded equipment, some of which can change what the unit produces; EIA notes that many such changes can only be made during a shutdown [1] |

A turnaround can also run longer than planned: EIA notes that problems found once a unit is down can extend the outage [1]. Smaller planned shutdowns between turnarounds, which EIA calls "pit stops", have narrower scope [1].

## How often do turnarounds happen, and when?

- **Interval.** EIA's 2007 report gave 3 to 5 years for key fuel units and 4 to 5 years for major FCC turnarounds [1]. The Superior refinery's turnaround typically came once every five years [2].
- **Hitting the target.** In a survey of 28 FCC units cited by EIA, 22 targeted 4 to 5 years between turnarounds and 16 achieved it, and turnarounds ran an average of 5 days longer than planned [1].
- **Season.** EIA found outages most frequent in the first quarter and in the fall, when US demand for crude oil and products is at its seasonal low [1], and its 2018 outage report placed planned maintenance mainly in fall and winter, when transportation fuel demand is lower [3]. Its 2024 analysis said planned maintenance generally peaks in late February and March [4]. Since 1991, US refinery utilization has averaged 92% from May to September against 88% in the other months [5].
- **Labor.** Because contractors cannot staff several large turnarounds at once, refiners stagger them and avoid holidays and hunting season [1].

## What happens between shutdown and startup?

| Phase | What happens | US process safety rule that applies |
|---|---|---|
| Shutdown | Units are brought down and emptied in a planned order; at Superior this began with the alkylation unit three days before the FCC unit [2] | Written procedures for normal shutdown, 29 CFR 1910.119(f)(1) [6] |
| Cleaning | Hydrocarbons are removed, for example by steaming or chemical cleaning; Superior used vapor-phase chemical cleaning on its FCC unit for the first time in 2018 [2] | Same operating procedures; changes to them go through management of change [6] |
| Isolation and opening | Equipment is isolated and opened for entry | Safe work practices for lockout/tagout, confined space entry and opening process equipment, (f)(4) [6] |
| Inspection and repair | Contractors and inspectors work through the scope | Contractor rules cover turnaround work, (h)(1) [6]; hot work needs a permit, (k) [6] |
| Startup | Units are reassembled and restarted | Written procedures for startup following a turnaround, (f)(1)(i)(G); pre-startup safety review for modified facilities, (i) [6] |

A 2017 review of refinery inspections by the US Occupational Safety and Health Administration (OSHA) notes that the Center for Chemical Process Safety (CCPS) recommends reviewing shutdown procedures before a planned turnaround, instead of waiting for the routine annual review [7].

## Where integrity problems show up

| Element or step | Integrity link | In the Library |
|---|---|---|
| Inspection while equipment is open | Routine and special inspections for corrosion, wear and deposits are done during the turnaround window [1] | [How is inspection scope set for a turnaround?](/library/turnaround-inspection-scope/) |
| Return to service after findings | Erosion found on an FCC slide valve at the 2008 and 2013 turnarounds did not stop it going back into service; OSHA later cited the refinery, and the valve's erosion let air into the unit in 2018 [2] | Repair, replace or keep running: how are decisions on degraded equipment made? |
| Changes made during the shutdown | Any change other than replacement in kind goes through management of change, and drawings and procedures are updated before startup [6] | [What is management of change (MOC)?](/library/management-of-change/) |
| Startup | Startup after a turnaround needs written procedures, and modified facilities need a pre-startup safety review [6] | [What is a pre-startup safety review (PSSR)?](/library/pre-startup-safety-review/) |
| Shutdown procedure | The Superior shutdown procedure kept the regenerator at higher pressure than the reactor, the opposite of the technology licensor's guidance [2] | [What is process safety management (PSM)?](/library/process-safety-management/) |

Sources: EIA, SR/OOG/2007-01 [1]; CSB report No. 2018-02-I-WI, 2022 [2]; 29 CFR 1910.119 and Appendix C [6].

## Sources

1. [Refinery Outages: Description and Potential Impact on Petroleum Product Prices (SR/OOG/2007-01), US Energy Information Administration (EIA)](https://www.eia.gov/analysis/requests/2007/sroog200701.pdf)
2. [Investigation Report: FCC Unit Explosion and Asphalt Fire at Husky Superior Refinery, Superior, WI (Report No. 2018-02-I-WI), US Chemical Safety and Hazard Investigation Board (CSB)](https://www.csb.gov/assets/1/20/Husky_Superior_Refinery_Report_2022-12-23_(1)1.pdf?16884), 2022-12-23
3. [Planned Refinery Outages in the United States: Fourth-Quarter 2018, US Energy Information Administration (EIA)](https://www.eia.gov/petroleum/refinery/outage/pdf/refinery_outage.pdf)
4. [Reduced refinery activity puts upward pressure on gasoline and diesel prices (Today in Energy), US Energy Information Administration (EIA)](https://www.eia.gov/todayinenergy/detail.php?id=61543), 2024-03-06
5. [U.S. refineries have been running at very high rates in 2026 (Today in Energy), US Energy Information Administration (EIA)](https://www.eia.gov/todayinenergy/detail.php?id=68344), 2026-10-22
6. [29 CFR 1910.119, Process safety management of highly hazardous chemicals (paragraphs (f), (h), (i), (l) and Appendix C), eCFR, US Office of the Federal Register](https://www.ecfr.gov/current/title-29/subtitle-B/chapter-XVII/part-1910/subpart-H/section-1910.119)
7. [Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918), US Occupational Safety and Health Administration (OSHA)](https://www.osha.gov/Publications/OSHA3918.pdf)