LNG Canada partners take FID on Phase 2: two more trains at Kitimat for 28 million tonnes a year, fed by a Coastal GasLink expansion built on compression, not new pipe

·5 sources

Shell, Petronas, PetroChina, Mitsubishi and KOGAS took a final investment decision on September 28 to add two liquefaction trains, an LNG storage tank, a condensate tank, a loading berth and expanded utilities inside the existing Kitimat site, taking capacity from 14 to 28 million tonnes a year, with commercial operations expected in the early 2030s, per LNG Canada and Oil & Gas Journal. A day later TC Energy said Coastal GasLink Phase 2 will proceed: five new compressor stations and facility upgrades along the existing 670-kilometre route from Dawson Creek to nearly double the line's current throughput of about 2.1 Bcf/d, with construction from early 2027. Neither the partners nor TC Energy disclosed a total project cost.

Written by

Where it stands

The JGC Fluor joint venture, owned 50/50, received full notice to proceed for engineering, procurement, fabrication, construction and commissioning of Phase 2 after the FID, and Fluor will book its $7.5 billion share in the third quarter, per Fluor. LNG Canada keeps its equity lifting structure, under which each partner takes its proportionate share of LNG; Shell, at 40 percent, will receive nearly 6 million tonnes a year of additional LNG, per Oil & Gas Journal. The FID also triggers an equity option for five neighbouring First Nations to invest up to C$1 billion in an entity that will buy the Phase 2 storage tank, per LNG Canada. Reuters first reported on September 17 that the FID could come by early October. Status: monitoring.

What happened

LNG Canada says Phase 2 builds on a footprint and infrastructure designed from the outset for a four-train plant, which is why the expansion sits inside the current site rather than on new ground. Fluor says the same joint venture delivered Phase 1, which began producing LNG in June 2025 and was handed over in October 2025, and that Phase 2 will be built adjacent to the existing facility. Peak construction is expected to bring up to 4,000 workers to Kitimat and about 2,100 to the Coastal GasLink compressor sites, per LNG Canada and TC Energy. Shell told Oil & Gas Journal that Kitimat is positioned to supply cost-competitive gas to Asia, and cited its own outlook for global LNG demand rising about 60 percent by 2040.

The pipeline arrangement shifts construction risk away from the pipeline owner. Under commercial agreements announced earlier this year, LNG Canada leads construction as Phase 2 execution manager, while Coastal GasLink remains owner, operator and permit holder, and TC Energy says the structure limits the pipeline's capital commitments and exposure to cost and schedule overruns. TC Energy, a co-owner of Coastal GasLink, will operate the Phase 2 infrastructure, with in-service anticipated in the early 2030s. Beacon notes the practical consequence: the party that bears overrun risk on the compressor build is the same joint venture that needs the gas, which aligns schedule incentives but concentrates cost exposure with the five LNG partners.

Analysis

What it means

Kitimat ships to Asia across the Pacific with no chokepoint between plant and buyer, and the partners have chosen to double a node that has operated for only about 15 months since first LNG in June 2025. For integrity managers, the gas side of the expansion is compression on pipe already in the ground: TC Energy says Phase 2 nearly doubles Coastal GasLink capacity without building any additional pipeline, so the expansion's integrity case rests on the existing line's design margin and in-service inspection record, neither of which the releases discuss. For investors, the partners have committed without a published capex figure; Fluor's $7.5 billion half of the EPC scope is the only hard number, and the Coastal GasLink construction start in early 2027 is the first schedule test.