QatarEnergy signs 20-year deal for up to 3 mtpa from Woodside's Louisiana LNG as it extends force majeure on its own cargoes to year-end
QatarEnergy signed a 20-year agreement on October 29 to buy up to 3 million tonnes a year of LNG free on board from Woodside's Louisiana LNG, under construction near Lake Charles, with volumes starting at Train 2 start-up, expected in 2030, and reaching the full amount at Train 3. With last week's Cheniere deal it now has 7 mtpa of US supply agreed, while it has extended force majeure on its own shipments to the end of December, per The National citing Edison.
By Jun Zhong, Editor·Researched and drafted by Beacon's AI newsroom
Where it stands
The agreement is a signed, long-term sale and purchase agreement, not a heads of agreement: Woodside will supply up to 3 mtpa for 20 years, free on board, from its share of Louisiana LNG HoldCo volumes 1. Deliveries begin when Train 2 starts up and rise to 3 mtpa when Train 3 starts up; QNA expects first deliveries in 2030 1 2. The price formula has not been disclosed in the coverage Beacon read. Separately, QatarEnergy has extended force majeure on its own shipments to the end of December from early December, according to Italy's Edison, and buyers in Pakistan and Bangladesh were told their notices also run to year-end 2.
What happened
Louisiana LNG, in Calcasieu Parish near Lake Charles, is a three-train, 16.5 mtpa project that took its final investment decision in April 2025 and targets first LNG in 2029; the site has room for two more trains and is permitted for 27.6 mtpa in total 1. Uniper is the only other offtaker Offshore Energy names 1. Woodside chief executive Liz Westcott called the deal "a strong vote of confidence in Louisiana LNG" 1 2.
The deal follows by a week QatarEnergy's agreements with Cheniere for 4 mtpa through 2054, bringing its agreed US volumes to 7 mtpa; QatarEnergy also holds a stake in Golden Pass, which began exports in March 2. Chief executive Saad Al Kaabi said the additional volumes make QatarEnergy "the largest buyer of LNG from the US," that he expects more long-term deals with US and other suppliers by year-end at volumes "much higher" than 7 mtpa, and that buying LNG needs no capital spending and is much cheaper than building pipelines or new trains 2.
The purchases come while QatarEnergy's own exports remain constrained. An Iranian strike knocked out about 17 percent of Qatar's LNG capacity; Al Kaabi said the two damaged trains would take about three years to repair, though The National's own summary gives up to five years 2. He said undamaged facilities could restart within a week of a peace deal if ships were available, and ruled out pipelines that bypass Hormuz because any regional infrastructure could be targeted 2. Petrobangla says it is buying spot cargoes at significant cost, and Europe's TTF benchmark rose above €95/MWh this week, near its highest since December 2022 2.
Cheniere, the counterparty to last week's deal, on October 29 raised its full-year 2026 adjusted EBITDA guidance to $8.75 billion to $9.25 billion from $7.9 billion to $8.4 billion, citing Middle East disruption that lifted demand for US cargoes, per The National 2.
What it means
The world's largest LNG exporter is now also building a US purchase book, 7 mtpa signed in eight days and more promised by year-end. None of it arrives before 2030, so these contracts do nothing for this winter: the year-end force majeure, and any extension into 2027, matters more to buyers in Pakistan, Bangladesh and Europe than the signing does. Al Kaabi's statement that no Hormuz bypass pipelines will be built tells buyers the route risk is being managed by diversifying supply sources, not by building around the strait.
For Louisiana LNG, the contract ties a state-owned buyer's volumes to Train 2 and Train 3 start-up dates, so construction progress, commissioning and the reliability of early operation now carry contractual weight with a buyer that has its own outages to cover. Integrity and project teams on Gulf Coast liquefaction builds should expect buyers to scrutinize commissioning schedules and early-life reliability more closely as Qatar-linked volumes enter US order books.
What to watch: whether QatarEnergy extends force majeure past December; the further US deals Al Kaabi said he expects by year-end; and Louisiana LNG's progress toward first LNG in 2029, which sets when Qatar's volumes can begin.