ExxonMobil sanctions $12.5 billion Longtail, the first Stabroek development built to produce gas and condensate rather than oil

·3 sources

ExxonMobil took a final investment decision on Longtail, the eighth development on Guyana's Stabroek block, and plans to spend $12.5 billion on an FPSO designed for 1.2 bcf/d of gas and up to 250,000 b/d of condensate, with start-up expected in 2030. It is the block's first project targeting non-associated gas, and where that gas ends up is still open: piping it to shore depends on future investment decisions, market demand and infrastructure.

By , Editor·Researched and drafted by

Where it stands

Longtail is sanctioned: ExxonMobil took the final investment decision after receiving government and regulatory approvals and plans to invest $12.5 billion, with start-up expected in 2030 1 2. The FPSO contractor has not been named in the announcement coverage; Oil & Gas Journal notes only that front-end engineering contracts for the Longtail FPSO were let on March 24, 2026 2. No decision has been announced on how Longtail's gas reaches a market: the company says it could be piped to shore, subject to future investment decisions, market demand and the necessary infrastructure 1.

What happened

ExxonMobil announced the decision on November 12 1. Longtail sits in the southeastern part of the Stabroek block and targets non-associated gas and condensate-rich reservoirs, the block's first development of that kind 1 2. The FPSO is designed to process 1.2 bcf/d of gas and produce up to 250,000 b/d of condensate, fed by about 45 subsea production and injection wells 1 2.

Ownership follows the rest of the block: ExxonMobil Guyana operates with 45 percent, Hess Guyana Exploration holds 30 percent and CNOOC Petroleum Guyana 25 percent 1 2. ExxonMobil produces about 900,000 b/d from four Stabroek developments and expects block capacity to pass 1 million b/d when the fifth, Uaru, starts up in the fourth quarter of 2026; Whiptail is slated for 2027 and Hammerhead for 2029 2. The block produced its billionth barrel earlier in 2026, less than seven years after Liza started in December 2019 2.

The decision follows a month of public argument over Stabroek gas. On October 13, Reuters reported that the ExxonMobil-led group expects to need about 2 bcf/d of gas for reinjection to meet crude targets at its approved projects, and that Guyana was weighing whether to cut Fulcrum LNG's planned 6 mtpa floating project to start at up to 3 mtpa, or to skip exports and use the gas for domestic power and petrochemicals, according to people close to the talks 3. The same report described Longtail and a ninth project, Haimara, as the developments expected to produce non-associated gas and condensate 3. An ExxonMobil spokesperson said then that gas development requires supply and demand to be developed at the same time 3.

Analysis

What it means

Longtail changes what Stabroek is. The block's producing FPSOs were built around crude; this one is designed around 1.2 bcf/d of non-associated gas, with condensate as the liquid product. For an integrity team that means a different profile: a larger high-pressure gas inventory on the topsides, gas processing and compression as the core of the plant, and subsea wells producing gas and condensate rather than oil. Contractors, inspection providers and insurers who know the block from its oil FPSOs should check the scope against the new design basis rather than assume it carries over.

The commercial gap is the gas outlet. ExxonMobil has committed $12.5 billion to a gas-led project without an announced route to market for the gas, while Reuters reports the group expects to need about 2 bcf/d for reinjection at its approved projects and the government is reconsidering the size of the LNG project that would buy Stabroek gas. The record does not yet say how much of Longtail's gas will be sold and how much kept in the ground; the condensate is the only product with a stated volume.

What to watch: Uaru's start-up this quarter, which is the next test of the operator's schedule on the block; the FPSO award and its builder; and the Guyanese government's decision on Fulcrum LNG's size, which will show whether Longtail gas is sold or kept in the reservoir.

Sources

  1. 1.ExxonMobil takes $12.5-billion FID on Longtail development offshore Guyana · World Oil ·
  2. 2.ExxonMobil takes FID for Longtail development offshore Guyana · Oil & Gas Journal ·
  3. 3.Guyana may scale back LNG plans as Exxon needs more gas for its wells, sources say · Reuters via BOE Report ·