What is a material requisition?

·8 sources

Short answer

A material requisition describes what a project must buy: the items, quantities and specifications, and the checks and documents due from the supplier. On oil and gas orders that use Joint Industry Programme 33 (JIP33) specifications, the request for quotation adds technical, data sheet, quality and information requirements to the commercial terms.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

Oil and gas operators have historically sent suppliers a different set of requirements with each order, often hundreds of pages long, according to the International Association of Oil & Gas Producers (IOGP) 1. IOGP started JIP33 in 2016 in response to industry-wide cost and schedule overruns of more than 40% 1. The requisition is where those requirements are chosen. What it asks the supplier to prove and to deliver also becomes part of the record that a plant's process safety information and inspection program rely on later 7.

What does a material requisition contain?

No single public template exists, so this page uses two public references. The US Federal Acquisition Regulation (FAR) sets how a buyer describes a need, and IOGP's JIP33 shows how oil and gas equipment orders are structured 2,3. Under FAR, a requirement is stated as far as practicable in terms of the function to be performed, the performance required or the essential physical characteristics, and voluntary consensus standards are used instead of buyer-unique ones where they exist 3.

Part of the requisitionWhat it statesPublic reference
Items and quantitiesWhat is needed and how much, usually counted in the material take-offConstruction Industry Institute (CII), 1987 5
Technical requirementsFunction, performance or physical characteristics, based on industry standards plus any supplementary requirementsFAR 11.002 and 11.101 3; JIP33 technical requirements specification 2
Data sheetProject choices among defined options, for example material class and quality specification level for a ball valveJIP33 procurement data sheet 2
Quality requirementsThe supplier's quality management system, inspection and testing, and hold and witness points, at one of four risk levelsJIP33 quality requirements specification 2
Supplier documents and dataEach deliverable and its timing, marked for information, for acceptance or not requiredJIP33 information requirements specification 2
DeliveryThe required date; FAR treats time of delivery as an essential contract element that must be realisticFAR 11.401 3

Sources: FAR Part 11, as amended to March 2026 3; IOGP JIP33 FAQs 2; CII tutorial abstract, 1987 5.

Where does the requisition sit in the procurement sequence?

Research by the Construction Industry Institute (CII) describes materials management as one linked chain: take-off, requisitioning, purchasing, expediting, warehousing and issue of materials to the crafts, for both bulk materials and engineered equipment 5. The requisition is the hand-off from the people who define the need to the people who buy it.

In US federal terms, an acquisition begins when the need is established and includes describing the requirement 4. The request sent to suppliers is a solicitation: any request to submit offers or quotations 4. Once a supplier is chosen, the order becomes a contract, and FAR lists purchase orders among the forms a contract can take 4.

On oil and gas projects that use JIP33, IOGP states that the contractor prepares the complete request for quotation, typically during front-end engineering design (FEED) or early execution 2. The package combines the contract or purchase order terms with the four JIP33 documents described above 2. How the offers are then compared is covered in What is technical bid evaluation in oil and gas?.

How do standard specifications change the requisition?

With JIP33, the purchaser does not write new technical or quality requirements for each order. It selects and configures options from defined templates 2. Project-specific additions go into a section for purchase-order-specific information requirements, which IOGP says is ideally kept to a minimum 2.

The specifications sit on top of international standards, such as those of the American Petroleum Institute (API), the American Society of Mechanical Engineers (ASME) and the International Organization for Standardization (ISO), and replace the separate procurement specifications that each operator used before 2. IOGP states that JIP33 aims to cover about 80% of procurement scope and that the documents are revised in step with their parent standards, typically about every five years 2. A supplier that wants to deviate on a live project raises it with its client 2.

The same preference appears in US federal rules: agencies have to use voluntary consensus standards where they exist, rather than government-unique standards, unless that is impractical or inconsistent with law 3.

Where integrity problems show up

Decision or step at this stageWhat it affects laterIn the Library
Stating the material grade for the serviceMaterial that does not match the service can fail early: at Texas City, Texas, in 2005, a carbon steel elbow in hydrogen piping that called for 1.25% chromium steel ruptured after about three months 6What is positive material identification (PMI)?
Requiring material certificates and recordsOn gas transmission pipelines, records of diameter, wall thickness, seam type and grade must be traceable, verifiable and complete for the life of the line; without them the operator must verify by testing 8What is material traceability?
Setting quality, inspection and test requirementsIn a process under the US Occupational Safety and Health Administration (OSHA) process safety management (PSM) standard, new equipment as built must suit the process it will serve 7What is an inspection and test plan (ITP)?
Requiring data sheets, design codes and the manufacturer's instructionsProcess safety information must include materials of construction and design codes, and inspection frequency must be consistent with the manufacturer's recommendations 7What should an inspection plan contain?
Requisitioning spare parts and maintenance materialsUnder PSM, maintenance materials and spare parts must also suit the process they are used in 7What is mechanical integrity (MI)?

Sources: US Chemical Safety and Hazard Investigation Board (CSB) safety bulletin 2005-04-B, 2006 6; 29 CFR 1910.119 paragraphs (d) and (j) 7; 49 CFR 192.607 8.

Common questions

Is a material requisition the same as a purchase order?
No. The requisition describes the need inside the buying organization. A purchase order is an order to a supplier that becomes a binding contract once accepted or performed, and FAR counts it as a contract.
Who prepares the requisition on an oil and gas project?
On projects that use JIP33, IOGP states that the engineering, procurement and construction contractor prepares the complete request for quotation. See [ITB vs RFQ vs RFP in oil and gas procurement](/library/itb-rfq-rfp/) for the types of request.
What happens when a supplier cannot meet the requisition?
On JIP33 orders, IOGP says a deviation on a live project is discussed directly with the client. How queries and deviations are handled during bidding is covered in [What are technical queries and deviations in a bid?](/library/technical-queries-deviations/).

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.JIP33: About us · International Association of Oil & Gas Producers (IOGP)
  2. 2.JIP33 FAQs · International Association of Oil & Gas Producers (IOGP)
  3. 3.FAR Part 11, Describing Agency Needs (11.002, 11.101, 11.401) · Acquisition.gov, Federal Acquisition Regulation (FAC 2026-01, effective 2026-03-13) ·
  4. 4.FAR 2.101, Definitions (acquisition, solicitation, contract) · Acquisition.gov, Federal Acquisition Regulation (FAC 2026-01, effective 2026-03-13) ·
  5. 5.Materials Management Microcomputer Tutorial, Users Manual (Construction Industry Institute, 1987): abstract record · US National Institute of Standards and Technology (NIST), FireDOC
  6. 6.Safety Bulletin No. 2005-04-B: BP Texas City, TX Refinery Fire, Positive Material Verification: Prevent Errors During Alloy Steel Systems Maintenance · US Chemical Safety and Hazard Investigation Board (CSB) ·
  7. 7.29 CFR 1910.119, Process safety management of highly hazardous chemicals · eCFR, US Office of the Federal Register
  8. 8.49 CFR 192.607, Verification of Pipeline Material Properties and Attributes: Onshore steel transmission pipelines · eCFR, US Office of the Federal Register