What is material traceability?

·15 sources

Short answer

Material traceability is the ability to link each installed component to its material identity and the documents that prove it, from the mill to final use. The link usually runs through a heat or batch number and the material certificate. For US gas transmission pipelines, 49 CFR 192.607 requires material records that are traceable, verifiable and complete.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

The operator's records described the pipe that ruptured at San Bruno, California, in September 2010 as seamless pipe of a stated grade; the US National Transportation Safety Board (NTSB) found welded pipe made of six short pieces, some of which met no known specification 1. The wrong description had been taken in 1977 from a 1956 accounting voucher rather than from engineering records, and was loaded into the operator's mapping database in 1998 1. The rupture and fire killed eight people and destroyed 38 homes 1. In January 2011 the NTSB urged a search for pipeline records that are "traceable, verifiable, and complete", wording the US Pipeline and Hazardous Materials Safety Administration (PHMSA) later built into its 2019 gas transmission rule 1,2,3.

ASTM describes the goal as keeping a metal's identity from melting to its final application 8. The US nuclear quality rule, a public model, keeps identity by heat, part or serial number, on the item or in records traceable to it, through fabrication, installation and use, to stop wrong material being used 7. EU pressure equipment guidance allows means from stamping or color coding to procedural controls, scaled to the risk of mixing grades 9.

Link in the chainWhat carries the identityTypical record
Melt of steel (heat)Heat numberMill test certificate
Product (plate, pipe, fitting, forging)Stamped, stenciled or color-coded markingCertificate and packing list
Fabricated pieceMarking transferred to each cut pieceCutting list, weld map
Installed locationTag, line or segment numberAs-built drawings
Operating plantEquipment recordProcess safety information on materials of construction

Sources: ASTM E1476 8; 10 CFR 50 Appendix B, Criterion VIII 7; EU Pressure Equipment Directive Guidelines G-04 and G-05, adopted 2016 9,10; 29 CFR 1910.119(d)(3) 13.

What do US pipeline rules require?

PHMSA's 2019 final rule, effective 1 July 2020, responded to NTSB recommendations and covers gas transmission pipe that lacks certain material or operating records 3. For transmission pipe installed after that date, records of wall thickness, diameter, seam type, strength and chemistry must be kept for the pipeline's life 4. Under 49 CFR 192.607, such records must be traceable, verifiable and complete; if not, the properties must be verified by tests when pipe is exposed, with sampling programs where needed 2.

PHMSA's 2012 advisory bulletin explains the three words 6:

TermWhat PHMSA meant (2012)Example given
TraceableClearly linked to original information; transcribed copies may contain errorsPipe mill records, purchase requisitions, as-built documents
VerifiableConfirmed by a separate, complementary documentPurchase order checked against a test of a coupon from the same pipe
CompleteFinalized (signed, dated) and linked to a specific segmentPressure test record naming segment, tester, duration and readings

How is traceability kept during fabrication and maintenance?

In fabrication, marking is carried over to each piece cut from a marked product, and the maker must be able to produce the documents and certificate for a specific item on request 9,10. Under US process safety management rules, process safety information must state materials of construction, and spare parts must suit the process 13. US federal purchasing rules treat false identification of a grade or lot number as a sign of a counterfeit item 14.

Maintenance can also break the chain. At a Texas City, Texas, refinery in 2005, identical-looking elbows were refitted with a carbon steel one where low-alloy steel was needed; the US Chemical Safety and Hazard Investigation Board (CSB) then called for parts and their locations to be tagged before removal and checked after refitting 11.

What happens when records are missing?

For pipelines, failure-pressure and crack-growth analyses must use documented properties; until missing data are obtained under 192.607, the operator must apply conservative assumed values, for example for toughness 5. In refineries, the CSB noted in 2015 that original mill data are often unavailable for older plants, so confirming the chemistry of each carbon steel component means taking metal shavings for laboratory analysis or measuring the thickness of every component 12.

Where integrity problems show up

Decision or step at this stageWhat it affects laterIn the Library
Copying pipe data into records without checking the originalAt San Bruno, records showed seamless pipe; the operator later found other 30-inch segments listed as seamless or with wrong wall thickness 1San Bruno pipeline rupture (2010): lessons for pipeline integrity
Keeping strength and toughness records for the pipe as installedWithout traceable, verifiable and complete records, failure-pressure and crack analyses use conservative assumptions 5What is fitness-for-service (API 579-1/ASME FFS-1)?
Keeping mill chemistry with each carbon steel componentLow-silicon parts corrode faster in sulfidation service; without mill data, finding them needs laboratory analysis or a full thickness survey 12What is sulfidation (high-temperature sulfur corrosion)?
Tagging alloy parts and their positions before removalA swapped carbon steel elbow failed by high temperature hydrogen attack after about 3 months 11What is high temperature hydrogen attack (HTHA)?
Keeping welding and testing records for each weldPHMSA asked operators of large pipelines built in 2008 and 2009 to review welding procedures and testing records to find defective girth welds 15What is weld mapping and weld traceability?

Sources: NTSB/PAR-11/01, 2011 1; 49 CFR 192.712 5; CSB final report on the 2012 Richmond refinery fire, 2015 12; CSB Safety Bulletin 2005-04-B, 2006 11; PHMSA Advisory Bulletin ADB-10-03, 2010 15.

Common questions

Is material traceability the same as weld traceability?
No. Material traceability follows the metal from the mill to its installed place; [weld traceability](/library/weld-traceability/) links each weld to its welder, procedure and inspection results. PHMSA's 2010 bulletin on girth weld failures asked operators to review both material specifications and welding and testing records.
Does every item need to be traced to one specific delivery?
Not always. EU pressure equipment guidance says identity need not always be tied to a specific delivery, and that the system is meant to match the risk of mixing grades. When it is not, a recall or safeguard action may have to cover every product made from the same grade.

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.Pacific Gas and Electric Company Natural Gas Transmission Pipeline Rupture and Fire, San Bruno, California, September 9, 2010 (NTSB/PAR-11/01) · US National Transportation Safety Board (NTSB)
  2. 2.49 CFR 192.607, Verification of Pipeline Material Properties and Attributes: Onshore steel transmission pipelines · eCFR, US Office of the Federal Register
  3. 3.Pipeline Safety: Safety of Gas Transmission Pipelines: MAOP Reconfirmation, Expansion of Assessment Requirements, and Other Related Amendments (final rule), 84 FR 52180 · US Pipeline and Hazardous Materials Safety Administration (PHMSA), via Federal Register
  4. 4.49 CFR 192.67, Records: Material properties · eCFR, US Office of the Federal Register
  5. 5.49 CFR 192.712, Analysis of predicted failure pressure and critical strain level · eCFR, US Office of the Federal Register
  6. 6.Pipeline Safety: Verification of Records (Advisory Bulletin ADB-2012-06), 77 FR 26822 · US Pipeline and Hazardous Materials Safety Administration (PHMSA), via Federal Register (govinfo) ·
  7. 7.10 CFR Part 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants · eCFR, US Office of the Federal Register
  8. 8.ASTM E1476-04(2022), Standard Guide for Metals Identification, Grade Verification, and Sorting (product page) (E1476-04 (reapproved 2022)) · ASTM International
  9. 9.Guideline G-04 (form CLAP X140): ESR on materials, traceability, Directive 2014/68/EU · Working Group Pressure (WGP), European Commission; copy published by UNM, France
  10. 10.Guideline G-05 (form CLAP X141): EST on materials, inspection documents, Directive 2014/68/EU · Working Group Pressure (WGP), European Commission; copy published by UNM, France
  11. 11.Safety Bulletin No. 2005-04-B, BP Texas City, TX Refinery Fire: Positive Material Verification: Prevent Errors During Alloy Steel Systems Maintenance · US Chemical Safety and Hazard Investigation Board (CSB) ·
  12. 12.Final Investigation Report: Chevron Richmond Refinery Pipe Rupture and Fire · US Chemical Safety and Hazard Investigation Board (CSB) ·
  13. 13.29 CFR 1910.119, Process safety management of highly hazardous chemicals · eCFR, US Office of the Federal Register