What are as-built drawings?
As-built drawings are construction drawings marked up to show what was actually installed, including every change from the design. The final clean set is often called record drawings. In US process plants, the Occupational Safety and Health Administration's (OSHA) process safety rule requires piping and instrumentation diagrams (P&IDs), and its guidance says as-built drawings should be verified and kept.
By Jun Zhong, Editor·Researched and drafted by Beacon's AI newsroom·Checked by Jun Zhong, Editor·Last checked ·Next review
Why does it matter?
In the Merrimack Valley, Massachusetts, in 2018, the plans for a gas main replacement did not show the regulator sensing lines; the old main was abandoned with the lines still connected, and fires and explosions followed that damaged 131 structures 5. The National Transportation Safety Board (NTSB) found that the sensing lines were missing from both the isometric drawings and the geographic information system (GIS) records the field engineer relied on, and it urgently recommended that the operator's parent company make all records of its gas systems traceable, reliable and complete 5. In refineries, OSHA found during a national inspection program that many sites had not kept accurate, complete and up-to-date P&IDs 4.
How are as-built drawings made?
During construction, the contractor keeps a working copy of the contract drawings on site and marks each deviation on it as it happens. Deviations come from contract changes, answers to requests for information, owner direction, contractor-designed details and site conditions that differ from those expected 1. US military construction specifications require this markup set to be brought up to date every week, and at completion it becomes the basis for the record drawings 1.
Federal construction contracts add a related term. Shop drawings are the contractor's detailed drawings of how items will be fabricated, assembled and installed; where a contract calls for record shop drawings, the contractor must hand over the final approved set with all changes up to completion and acceptance 2.
In process plant handover the term usually covers the whole information set. The CFIHOS handover specification defines as-built information as data and documents that accurately reflect the plant at handover, and has the contractor fold as-built changes into drawings and registers within an agreed period after physical handover 9. OSHA's nonmandatory guidance says as-built drawings, certifications of code-built vessels and materials of construction should be verified and kept with the quality assurance records 3.
As-built, shop and record drawings: what is the difference?
| Contract drawings | Shop drawings | As-built drawings | Record drawings | |
|---|---|---|---|---|
| Prepared by | The owner, issued with the construction contract | The contractor, its subcontractors or suppliers | The contractor, on site, during construction | The contractor or the designer, at completion |
| What they show | The intended design | How items will be fabricated, assembled and installed | Actual conditions and each deviation from the contract drawings | The final compilation of actual conditions taken from the as-builts |
| Usual form | Issued drawing set with specifications | Drawings, diagrams, schedules, performance and test data | Red-lined paper or PDF markups | Clean drawing files, or drawings produced from a record model |
Sources: FAR 52.236-21 2; UFGS 01 78 00, August 2026 1. FAR is the Federal Acquisition Regulation; UFGS are the Unified Facilities Guide Specifications for US military construction.
What should as-built drawings show?
What must be shown depends on the asset type and the governing rules 1,7,3.
- Buildings and site work. The US military closeout specification asks for the actual route, type, size and depth of buried utility lines, tied by offsets to two permanent surface features, plus structural changes, piping and electrical layouts, changed grades and alignments, and shop drawing details such as pipe sizes, insulation and foundations 1.
- Hazardous liquid pipelines. Federal rules require current maps and records showing where tanks, pump stations, pig launching and receiving facilities, valves, rights-of-way and safety devices are; every crossing of roads, railways, rivers, buried utilities and other pipelines; the maximum operating pressure; and the diameter, grade, type and wall thickness of all pipe 7.
- Process plants. OSHA's rule lists P&IDs among the required equipment information 3. OSHA's refinery review adds that P&IDs should show the physical sequence of equipment and how systems connect, that tags in the field should match the P&IDs, and that every P&ID at a site should use one notation system 4. See also What is a piping and instrumentation diagram (P&ID)? and What is a piping isometric drawing?.
How are as-built drawings kept current after start-up?
OSHA's process safety rule requires written procedures to manage changes to process chemicals, technology, equipment and procedures, other than replacements in kind 3. Its guidance says changed P&IDs and procedures should be noted so the revisions become permanent when drawings are updated, including after work done during shutdowns 3. A modification large enough to change process safety information needs a pre-startup safety review before the modified process restarts 3.
OSHA found that P&ID errors at refineries were often systemic and could point to a weak management of change program; among hazard analysis recommendations left unresolved was a call to update P&IDs 4. Missing records also cost money at the end of a plant's life: interviews for a 2004 study for the US National Institute of Standards and Technology (NIST) indicated that unreliable as-built information leads to much resurveying and exploratory work at decommissioning 8.
Where integrity problems show up
| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| Producing engineering drawings and P&IDs before a facility operates | At Pitkin, Louisiana (1998), a production facility built without them could not get an effective design review or hazard analysis, and a separator without adequate pressure relief was overpressured and failed | What does a pressure relief valve do? |
| Drawing every connection, including small sensing and instrument lines | In the Merrimack Valley (2018), work was planned from records that omitted sensing lines; investigators also found that construction changes did not go through management of change | What is management of change (MOC)? |
| Updating P&IDs with every change | Inaccurate P&IDs can mislead hazard analyses, procedure writing, work permits, new installations and troubleshooting | What is a hazard and operability study (HAZOP)? |
| P&IDs and process flow diagrams that match the plant | Corrosion circuits and damage mechanism reviews are built from them | What is a corrosion loop? |
| Recording pipe diameter, grade, type and wall thickness in pipeline records | Where federal rules require it, onshore gas transmission operators without traceable, verifiable and complete material records must test the pipe | What is material traceability? |
Sources: CSB report No. 1998-002-I-LA 6; NTSB/PAR-19/02, 2019 5; OSHA 3918, 2017 4; Cal/OSHA presentation, undated 10; 49 CFR 195.404 7; 49 CFR 192.607 11.
Common questions
- Are as-built drawings the same as record drawings?
- Not always. US military specifications treat as-builts as the contractor's marked-up working set and record drawings as the final compiled set. In process plant handover, "as-built" often means the final information set itself, as in CFIHOS.
- Is a P&ID an as-built drawing?
- A P&ID is a type of drawing; it is as-built once it has been checked against the installed plant and updated. OSHA requires P&IDs as process safety information and has cited refineries whose P&IDs were not accurate or current.
Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.
Sources
- 1.UFGS 01 78 00, Closeout Submittals (Unified Facilities Guide Specifications) · US Army Corps of Engineers, Naval Facilities Engineering Systems Command and Air Force Civil Engineer Center, via the Whole Building Design Guide
- 2.48 CFR 52.236-21, Specifications and Drawings for Construction (Federal Acquisition Regulation) · eCFR, US Office of the Federal Register
- 3.29 CFR 1910.119, Process safety management of highly hazardous chemicals (including Appendix C, nonmandatory compliance guidelines) · eCFR, US Office of the Federal Register
- 4.Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918) · US Occupational Safety and Health Administration (OSHA)
- 5.Overpressurization of Natural Gas Distribution System, Explosions, and Fires in Merrimack Valley, Massachusetts, September 13, 2018 (NTSB/PAR-19/02) · US National Transportation Safety Board (NTSB)
- 6.Investigation Report: Catastrophic Vessel Overpressurization, Sonat Exploration Company, Temple 22-1 Common Point Separation Facility, Pitkin, Louisiana, March 4, 1998 (Report No. 1998-002-I-LA) · US Chemical Safety and Hazard Investigation Board (CSB)
- 7.49 CFR 195.404, Maps and records · eCFR, US Office of the Federal Register
- 8.Cost Analysis of Inadequate Interoperability in the U.S. Capital Facilities Industry (NIST GCR 04-867), M. P. Gallaher, A. C. O'Connor, J. L. Dettbarn Jr., L. T. Gilday · US National Institute of Standards and Technology (NIST)
- 9.CFIHOS Scope and Procedures (C-TP-001) (Version 2.0) · JIP36 CFIHOS, International Association of Oil & Gas Producers (IOGP) ·
- 10.PSM - Refining Damage Mechanisms 101 (J. Riley), presentation · California Division of Occupational Safety and Health (Cal/OSHA), Pressure Vessel Unit
- 11.49 CFR 192.607, Verification of Pipeline Material Properties and Attributes: Onshore steel transmission pipelines · eCFR, US Office of the Federal Register