What is a material take-off (MTO)?
A material take-off (MTO) is a list of the materials a project must buy, with descriptions and quantities, counted from its drawings and specifications. It is not the same as a quantity take-off for a cost estimate: estimating practice measures work net in place, while a material take-off counts the gross quantities to purchase.
By Jun Zhong, Editor·Researched and drafted by Beacon's AI newsroom·Checked by Jun Zhong, Editor·Last checked ·Next review
Why does it matter?
Bulk material surplus can exceed 10% when the take-off is made before the final drawings are complete, against 1% or less when it is made from final design drawings with an effective materials system in place, according to research by the Construction Industry Institute (CII) published in 1999 1. CII names design changes and errors in estimates and take-offs among the causes of surplus 1. The same take-off line that sets a quantity also sets the material grade, which decides how that part behaves once it is in service 5.
What does a material take-off contain?
Each line of a take-off pairs a quantity with a description. University estimating notes from King Fahd University of Petroleum and Minerals (KFUPM) describe take-off lines measured in a stated unit: a count (each), a length, an area, a volume or a weight 2. The description has to be detailed enough for the item to be priced or bought, and dimensions taken or calculated from the drawings are preferred to dimensions scaled off them 2.
The same notes break the project into parts such as buildings or areas, then assemblies, then individual items, with headings for trade, location and phase 2. CII research from 1987 describes materials management systems that handle both bulk materials and engineered equipment 3.
Illustrative numbers, not from any real asset or standard table
| Line | Description | Unit | Quantity |
|---|---|---|---|
| 1 | Line pipe, carbon steel, size, wall thickness and grade per piping specification, area A | m | 120 |
| 2 | Elbow, 90 degree, same material and size as line 1, area A | each | 14 |
| 3 | Stud bolts with nuts, per piping specification, area A | each | 64 |
| 4 | Gaskets, per piping specification, area A | each | 16 |
The table shows the structure of take-off lines only.
How is a material take-off different from a quantity take-off?
Both start from the drawings and specifications, but they answer different questions. The KFUPM notes distinguish them as follows 2.
| Quantity take-off | Material take-off | |
|---|---|---|
| Purpose | Pricing the work in a detailed cost estimate | Buying the materials |
| Basis of measurement | Net in place: the dimensions shown on the drawings, with no allowance for waste | Gross quantities to be purchased |
| What is counted | Work items, including some that use no material, such as curing concrete | Materials only |
| Enough to price the work? | Yes, that is its purpose | No: a line such as a volume of concrete of a given strength is enough to buy it, but not to price the work |
| Place in the process | First stage of a detailed estimate, followed by sorting, pricing and adding overheads and markup | Feeds requisitions and purchasing |
Source: KFUPM CEM 511 course notes, undated 2; CII, 1987 3.
When is the take-off done, and how accurate is it?
How accurate a take-off is depends on how complete the drawings are. CII's key findings from 1999 give the range: with an effective materials management system, surplus can usually be held to 1% or less when the take-off is made from final design drawings, but it can exceed 10% of bulk materials when the drawings are not yet final 1. CII also reports that an effective system cuts a typical bulk surplus of 5% to 10% down to roughly 1% to 3% of the bulk quantity bought 1.
Surplus has several causes besides take-off timing. CII lists design changes, errors in estimates and take-offs, poor site warehousing, duplicate purchases, inventory errors and weak field control of issued materials 1. The KFUPM notes add that accuracy is a trade-off against effort, with more careful measurement for costly items 2. See also What are long-lead items?.
Where does the take-off go next?
The take-off is the first link in the materials chain. CII describes integrated systems that connect take-off with requisitioning, purchasing, expediting, warehousing and issue of materials to the crafts 3, and an earlier CII study lists take-off, vendor evaluation, purchasing, expediting, warehousing and distribution as functions of one system 4.
The take-off quantities and descriptions feed the requisitioning step 3; the material requisition then adds the specifications, quality requirements and supplier documents for each order.
Where integrity problems show up
| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| Material grade and specification on each take-off line | A part of the wrong material can fail early in service: at Texas City, Texas, in 2005, a carbon steel elbow in hydrogen piping that called for 1.25% chromium steel ruptured after about three months 5 | What is positive material identification (PMI)? |
| Pipe size, wall thickness and grade carried into purchase records | On gas transmission pipelines, records of diameter, wall thickness, seam type and grade must be traceable, verifiable and complete for the life of the line, or the operator must verify them by testing 6 | What is material traceability?, What is a mill test certificate (EN 10204 3.1 and 3.2)? |
| Surplus bulk material kept after construction | If it is later used for maintenance in a process under the US Occupational Safety and Health Administration (OSHA) process safety management standard, maintenance materials and spare parts must suit the process 7; CII lists inventory errors and weak field control among causes of surplus 1 | What is mechanical integrity (MI)? |
Sources: US Chemical Safety and Hazard Investigation Board (CSB) safety bulletin 2005-04-B, 2006 5; 49 CFR 192.607 6; 29 CFR 1910.119(j)(6) 7; CII, 1999 1.
Common questions
- Is a material take-off a cost estimate?
- No. A material take-off lists what to buy. A detailed estimate starts from a quantity take-off and then sorts, prices and adds overheads and markup.
- Why does the take-off change during a project?
- Because the drawings change. CII lists design changes and errors in estimates and take-offs among the causes of surplus, and finds surplus is lowest when the take-off is made from final drawings.
- Who uses the material take-off?
- Requisitioning, purchasing, expediting, warehousing and the crafts who receive issued materials all work from it in an integrated materials management system.
Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.
Sources
- 1.Procurement and Materials Management: A Guide to Effective Project Execution (IR7-3), publication page with key findings · Construction Industry Institute (CII), The University of Texas at Austin ·
- 2.Measuring Quantities Generally (CEM 511 course notes) · King Fahd University of Petroleum and Minerals (KFUPM), Construction Engineering and Management
- 3.Materials Management Microcomputer Tutorial, Users Manual (Construction Industry Institute, 1987): abstract record · US National Institute of Standards and Technology (NIST), FireDOC
- 4.Costs and Benefits of Materials Management Systems (Construction Industry Institute Publication 7-1, 1986): abstract record · US National Institute of Standards and Technology (NIST), FireDOC
- 5.Safety Bulletin No. 2005-04-B: BP Texas City, TX Refinery Fire, Positive Material Verification: Prevent Errors During Alloy Steel Systems Maintenance · US Chemical Safety and Hazard Investigation Board (CSB) ·
- 6.49 CFR 192.607, Verification of Pipeline Material Properties and Attributes: Onshore steel transmission pipelines · eCFR, US Office of the Federal Register
- 7.29 CFR 1910.119, Process safety management of highly hazardous chemicals · eCFR, US Office of the Federal Register