Quality assurance vs quality control in construction

·10 sources

Short answer

Quality assurance (QA) is the system that gives confidence work will meet requirements; quality control (QC) checks that each item actually does. Under US federal construction rules (Federal Acquisition Regulation (FAR) Part 46; 23 CFR 637), the contractor controls quality and the owner verifies and accepts it; 10 CFR 50 Appendix B treats QC as part of QA.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

The National Transportation Safety Board (NTSB) named "inadequate quality assurance and quality control" on a 1956 pipeline relocation as a probable cause of the San Bruno, California, rupture in 2010, which killed eight people 8. A pipe section with a seam weld flaw that was visible when it was installed went into service and the flaw grew for 54 years until the pipe failed 8. The NTSB's findings cover both layers: pipe made to no known specification reached the job, and a weld defect that was visible at installation was not rejected 8.

QA vs QC at a glance

Quality assurance (QA)Quality control (QC)
Federal highway definition (23 CFR 637.203)Every planned and systematic action needed to give confidence that a product or service will meet its quality requirementsThe operating techniques and activities a contractor or vendor uses to meet the contract requirements
FocusThe system: organization, procedures, design and document control, purchasing, records and audits (for example 10 CFR 50 Appendix B, Criteria I to VII, XVII and XVIII)The product: inspection, testing, measuring equipment and nonconforming items (for example Criteria X to XII and XV)
Question it answersIs the work planned, staffed and checked so that it will meet requirements?Does this weld, pour or component meet its acceptance criteria?
Who does it on US federal construction contractsThe government owner, through contract quality assurance that includes inspection and acceptance (FAR 46.101, 46.401)The contractor, who controls quality and keeps an inspection system and complete records (FAR 46.105, 52.246-12)
Activities in a highway QA programQC, independent assurance and acceptance, plus dispute resolution, accredited laboratories and certified staff 4Sampling, testing, inspection and corrective action to keep production under control 4
IndependenceAudits by trained people with no direct responsibility for the audited area (Appendix B, XVIII)Inspection by someone other than the person who did the work (Appendix B, X)
RelationshipIncludes QC (Appendix B; TRB, 2018)One part of QA

Sources: eCFR, 23 CFR 637.203, 48 CFR Part 46 and 52.246-12, 10 CFR 50 Appendix B, up to date as of 22 October 2026 1,2,3,5; Transportation Research Board (TRB) Circular E-C235, 2018 4.

When is quality assurance used?

  • Before work starts. Appendix B requires a written QA program set up at the earliest practicable time, naming the structures, systems and components it covers and the organizations involved 5.
  • In purchasing. The FAR calls for higher-level quality standards, such as ISO 9001 or ASME NQA-1, in contracts for complex or critical items 1.
  • For new process plants. The quality assurance paragraph of the Occupational Safety and Health Administration (OSHA) process safety standard requires the employer to make sure equipment is fabricated suitably for its service, installed to design specifications and manufacturer instructions, and supplied with suitable spare parts 6. OSHA's guidance adds that as-built drawings, coded vessel certifications and materials of construction belong in the QA documentation, and that supplier facilities may be audited 6.
  • At acceptance. Government quality assurance takes place before the owner accepts the work 1, and a highway agency's acceptance weighs its own sampling, testing and inspection results 4.

When is quality control used?

  • During fabrication and installation. The FAR construction clause requires the contractor to inspect enough to ensure the work conforms and to keep complete inspection records 2.
  • On special processes. Welding, heat treatment and nondestructive testing (NDT) are carried out by qualified people using qualified procedures 5.
  • At hold points. Where a contract sets mandatory hold points, work does not pass them until the owner's representative has witnessed or inspected it 5.
  • When something fails. Nonconforming items are identified, segregated and accepted, repaired, reworked or rejected under written procedures 5, and the contractor must replace or correct rejected work 2.

Is QA/QC one activity?

No. The TRB glossary discourages the combined term QA/QC because QA already contains QC, along with acceptance and independent checks 4. The split also has legal weight: under the FAR construction clause, government inspection does not relieve the contractor of responsibility for adequate quality control and does not amount to acceptance 2.

Internationally, the shared vocabulary is ISO 9000, the International Organization for Standardization (ISO) standard for quality management fundamentals and vocabulary; its fifth edition, ISO 9000:2026, was published in May 2026 and replaced the 2015 edition 7.

Where integrity problems show up

Decision or step at this stageWhat it affects laterIn the Library
QC of welds at installationAt San Bruno, a seam weld flaw visible at installation in 1956 grew until the pipe ruptured in 2010 8San Bruno pipeline rupture (2010): lessons for pipeline integrity
QC of NDT proceduresThe Pipeline and Hazardous Materials Safety Administration (PHMSA) found NDT quality control problems at some girth welds that later failed on lines built in 2008 and 2009 10What is weld mapping and weld traceability?
QA control of material identityAppendix B requires identification so that incorrect or defective material is not used 5; OSHA expects positive materials testing to be documented 9What is positive material identification (PMI)?
QA records retainedOSHA ties as-built drawings and certifications in QA documentation to the mechanical integrity program 6What documents are handed over when a project is completed?
QA hold points written into plansItems cannot bypass required inspections and tests 5What is an inspection and test plan (ITP)?

Sources: NTSB PAR-11/01, 2011 8; PHMSA ADB-10-03, 2010 10; 10 CFR 50 Appendix B 5; 29 CFR 1910.119 and Appendix C 6; OSHA 3918, 2017 9.

Common questions

Who is responsible for quality control on a construction contract?
Under the FAR, the contractor: it controls the quality of what it supplies, performs the inspections and tests the contract requires, and makes sure its suppliers have acceptable quality control systems.
Does owner inspection replace contractor QC?
No. The FAR construction clause says government inspections serve the government and do not relieve the contractor of its quality control duties.
Is an inspection and test plan QA or QC?
It connects both. Writing the plan and its hold points is part of the QA system, and carrying out each listed inspection or test is QC.

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.48 CFR Part 46, Quality Assurance (Federal Acquisition Regulation) · eCFR, US Office of the Federal Register
  2. 2.48 CFR 52.246-12, Inspection of Construction · eCFR, US Office of the Federal Register
  3. 3.23 CFR 637.203, Definitions (Quality Assurance Procedures for Construction) · eCFR, US Office of the Federal Register
  4. 4.Transportation Research Circular E-C235, Glossary of Transportation Construction Quality Assurance Terms, Seventh Edition · Transportation Research Board (TRB), National Academies
  5. 5.10 CFR Part 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants · eCFR, US Office of the Federal Register
  6. 6.29 CFR 1910.119, Process safety management of highly hazardous chemicals, paragraph (j)(6) and Appendix C · eCFR, US Office of the Federal Register
  7. 7.ISO 9000:2026, Quality management: Fundamentals and vocabulary (standard page; ISO 9000:2015 page shows it as withdrawn) (Edition 5, 2026-05) · International Organization for Standardization (ISO)
  8. 8.Pacific Gas and Electric Company Natural Gas Transmission Pipeline Rupture and Fire, San Bruno, California, September 9, 2010 (NTSB/PAR-11/01) · US National Transportation Safety Board (NTSB)
  9. 9.Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918) · US Occupational Safety and Health Administration (OSHA)
  10. 10.Pipeline Safety: Girth Weld Quality Issues Due to Improper Transitioning, Misalignment, and Welding Practices of Large Diameter Line Pipe (ADB-10-03), 75 FR 14243 · Pipeline and Hazardous Materials Safety Administration (PHMSA), Federal Register via GovInfo ·