What documents are handed over when a project is completed?

·14 sources

Short answer

When a project is completed, the owner receives as-built drawings, equipment data and manuals, material certificates, and inspection and test records. Together they describe the facility as actually built. In US plants under the Occupational Safety and Health Administration's (OSHA) process safety rule, 29 CFR 1910.119, much of this information must be in place before start-up.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

A unit can be fully built and still not be ready for hazardous chemicals: under OSHA's process safety rule (29 CFR 1910.119), a pre-startup safety review must first confirm that it matches its design specifications and that its procedures are in place 1. For a new facility the review also confirms that a process hazard analysis was done, and that analysis needs written process safety information first, such as materials of construction, piping and instrumentation diagrams (P&IDs) and the relief design basis 1. Gaps left at handover can surface decades later: investigators found that the 1956 construction file for the gas pipeline segment that ruptured in San Bruno, California, in 2010 held cost accounting papers but no specifications, inspection records, as-built drawings or radiography reports 8.

What is in a handover package?

Federal process safety and pipeline rules, the construction clauses of the Federal Acquisition Regulation (FAR), the Unified Facilities Guide Specifications (UFGS) for US military construction and the CFIHOS information handover specification each name parts of a handover package 1,2,5,6,7. The table groups them by purpose.

Document groupWhat it recordsNamed in
As-built and record drawings, including P&IDsThe facility as installed, with every change from the design29 CFR 1910.119(d)(3) and Appendix C 1; FAR 52.236-21, Alternates I and II 5; UFGS 01 78 00 6
Process safety informationChemical hazards, process technology, materials of construction, electrical classification, relief and ventilation design, design codes, material and energy balances, safety systems29 CFR 1910.119(d) 1
Tag and document registersEvery tag in the facility; every document with its number, title and revisionCFIHOS master tag and document registers 7
Record of equipment and materialsManufacturer, model, serial number, composition, size and where each item is usedUFGS 01 78 00 6
Quality records and certificatesCertifications of code-built vessels and verified materials of construction29 CFR 1910.119, Appendix C 1
Pressure test recordsTest medium, pressure, duration, pressure charts, leaks and failures49 CFR 192.517 2
Operating and maintenance informationOperation and maintenance manuals, spare parts data and warranties; operating, maintenance and emergency proceduresUFGS 01 78 00 6; 29 CFR 1910.119(i) 1

Who prepares and checks the documents?

The contractor and its suppliers create most records; the owner sets out in the contract what it needs and reviews what arrives, and CFIHOS gives each party information management roles plus a joint project team 7. In US military construction specifications, the contractor keeps the marked-up as-built set current every week and open to monthly government review, and part of a progress payment can be held back if it falls behind 6.

A US Environmental Protection Agency (EPA) training handout on asset management lists two controls for records of newly acquired assets: tie the inventory to commissioning or handover, and use contract retainage 13. Under OSHA's rule, the owner of a covered process must also check that new equipment is suitable as fabricated and is installed to the design specifications and the manufacturer's instructions 1.

When are handover documents delivered?

  • During construction. As-built markups and the shared tag and document registers are updated as work proceeds 6,7.
  • Before start-up. The pre-startup safety review checks construction against the design and confirms procedures and training; OSHA's nonmandatory guidance adds that P&IDs should be complete by then 1. See What is a pre-startup safety review (PSSR)?.
  • At completion. Federal construction contracts that call for record shop drawings require the final approved set, with all changes up to acceptance 5. Under CFIHOS, as-built data and documents follow physical handover within a period set in the contract 7.
  • After start-up. Changes pass through management of change, and OSHA's guidance says drawings and procedures are then updated so the revisions become permanent 1.

Which handover records must be kept for the life of the asset?

RecordHow longRule
Gas pipeline pressure test records (tests under 192.505 to 192.507)Useful life of the pipeline49 CFR 192.517(a) 2
Diameter, wall thickness, seam type and grade of onshore steel gas transmission pipe, where the pipeline code calls for itLife of the pipeline, traceable, verifiable and complete49 CFR 192.607(b) 4
Date, location and description of repairs to hazardous liquid pipeUseful life of the pipe49 CFR 195.404(c)(1) 3
Hazardous liquid pipeline maps and records, including pipe diameter, grade, type and wall thicknessKept current49 CFR 195.404(a) 3
Damage mechanism review reports at California refineriesLife of the process unit8 CCR 5189.1(k)(14) 10

Sources: eCFR 2,3,4; 8 CCR 5189.1 10.

Where integrity problems show up

Decision or step at this stageWhat it affects laterIn the Library
Pressure test records kept with medium, pressure, duration and chartsCrack analyses of gas transmission pipe can use a past pressure test to size the largest flaw that could have survived itWhat is a hydrostatic test?, What is fitness-for-service (API 579-1/ASME FFS-1)?
Material certificates and verified materials of construction kept with the quality recordsWhere federal rules require it, onshore gas transmission operators whose material records are not traceable, verifiable and complete must test the pipe to confirm its propertiesWhat is material traceability?
A pre-service thickness survey included in the packageCorrosion rates based on nominal instead of measured thickness can carry large errors from mill tolerancesBaseline inspection
P&IDs, process flow diagrams, heat and material balances and piping specifications handed overThese are inputs for defining corrosion circuits and for damage mechanism reviewsWhat is a corrosion loop?
Relief system design and design basis included in process safety informationOSHA's refinery inspections found written process safety information that did not reflect missing relief devices, undersized relief valves or wrong set pointsWhat does a pressure relief valve do?

Sources: 49 CFR 192.712(d) 12; 29 CFR 1910.119, Appendix C 1; 49 CFR 192.607(c) 4; AIChE, 2011 9; Cal/OSHA, undated 14; 8 CCR 5189.1(k) 10; OSHA 3918, 2017 11.

Common questions

Is handover documentation the same as digital handover?
No. Handover documentation is what the owner receives; digital handover is how it is delivered, as structured data with documents linked to each tag and equipment item. See [What is digital handover and CFIHOS?](/library/digital-handover-cfihos/).
What if the original records no longer exist?
OSHA's rule lets missing process technology information be rebuilt during the process hazard analysis, and older equipment built to codes that are no longer current needs a documented finding that it is safe as designed, maintained and operated. Where federal rules require it, onshore gas transmission operators without traceable, verifiable and complete material records must verify properties by testing.

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.29 CFR 1910.119, Process safety management of highly hazardous chemicals (including Appendix C, nonmandatory compliance guidelines) · eCFR, US Office of the Federal Register
  2. 2.49 CFR 192.517, Records · eCFR, US Office of the Federal Register
  3. 3.49 CFR 195.404, Maps and records · eCFR, US Office of the Federal Register
  4. 4.49 CFR 192.607, Verification of Pipeline Material Properties and Attributes: Onshore steel transmission pipelines · eCFR, US Office of the Federal Register
  5. 5.48 CFR 52.236-21, Specifications and Drawings for Construction (Federal Acquisition Regulation) · eCFR, US Office of the Federal Register
  6. 6.UFGS 01 78 00, Closeout Submittals (Unified Facilities Guide Specifications) · US Army Corps of Engineers, Naval Facilities Engineering Systems Command and Air Force Civil Engineer Center, via the Whole Building Design Guide
  7. 7.CFIHOS Scope and Procedures (C-TP-001) (Version 2.0) · JIP36 CFIHOS, International Association of Oil & Gas Producers (IOGP) ·
  8. 8.Pacific Gas and Electric Company Natural Gas Transmission Pipeline Rupture and Fire, San Bruno, California, September 9, 2010 (NTSB/PAR-11/01) · US National Transportation Safety Board (NTSB)
  9. 9.The Importance of Mechanical Integrity Inspection for Successful Capital Projects (paper 84b, abstract), P. F. Schubert · American Institute of Chemical Engineers (AIChE), 2011 Spring Meeting and 7th Global Congress on Process Safety
  10. 10.California Code of Regulations, Title 8, Section 5189.1, Process Safety Management for Petroleum Refineries · California Department of Industrial Relations
  11. 11.Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918) · US Occupational Safety and Health Administration (OSHA)
  12. 12.49 CFR 192.712, Analysis of predicted failure pressure and critical strain level · eCFR, US Office of the Federal Register