What is a pre-startup safety review (PSSR)?

·7 sources

Short answer

A pre-startup safety review (PSSR) is the check that a new or significantly modified process is ready before highly hazardous chemicals enter it. It confirms construction matches design and that procedures, hazard analysis and training are complete. The Occupational Safety and Health Administration (OSHA) requires it under 29 CFR 1910.119(i).

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

At a pesticide plant in Institute, West Virginia, in 2008, a pre-startup review recorded unfinished items as complete, and a runaway reaction during the restart killed two workers and injured eight 6. The US Chemical Safety and Hazard Investigation Board (CSB) found that the review had missed a valve that was never installed and another that was broken, and that procedures had not been updated for a new control system even though the checklist said they had 6. Both equipment problems contributed directly to the explosion 6.

When is a PSSR required?

OSHA's process safety management (PSM) standard requires a PSSR for every new facility, and for a modified facility when the change is large enough to alter its process safety information 1. The review must be finished "prior to the introduction of highly hazardous chemicals to a process" 1.

SituationPSSR required?Basis
New facilityYes, including a completed process hazard analysis (PHA) with recommendations resolved or implemented29 CFR 1910.119(i) 1
Modification that changes process safety informationYes, and the change must also meet management of change (MOC)1910.119(i) 1
Slight modification that does not change process safety informationNo PSSR intended; the change goes through MOCOSHA interpretation, 1996 4
Replacement in kind (meets the design specification)Excluded from MOC procedures1910.119(b), (l) 1
Restart after a turnaround or long shutdownChanges made during the shutdown go through MOC; a PSSR is needed before chemicals enter modified facilitiesAppendix C; OSHA interpretation, 2019 1,5

Sources: eCFR, 29 CFR 1910.119, up to date as of 22 October 2026 1; OSHA interpretation letters, 1996 and 2019 4,5.

Facilities under the Environmental Protection Agency (EPA) Risk Management Program follow the same four confirmations for Program 3 processes, applied before regulated substances are introduced 2.

What must a PSSR confirm?

OSHA item, 1910.119(i)(2)Related PSM elementWhat the CSB found at Institute, West Virginia (2008)
Construction and equipment match design specificationsProcess safety information (d); quality assurance for new equipment (j)(6)Equipment checkouts marked complete that were not; a missing valve and a broken valve; control circuits not verified 6
Procedures for safety, operation, maintenance and emergencies exist and are adequateOperating procedures (f)Procedures not revised for the new control system, although the checklist said they were 6
New facilities: PHA done and its recommendations resolved; modified facilities: MOC metPHA (e); MOC (l)Temporary changes that had not been evaluated 6
Training of each employee who operates the process is completeTraining (g)Operators not formally trained on the new distributed control system 6

Sources: 29 CFR 1910.119 1; CSB Report No. 2008-08-I-WV, 2011 6.

OSHA's appendix of non-mandatory guidance adds that for a new process the piping and instrumentation diagrams should be complete, procedures in place and staff trained before start-up, and that initial start-up and normal operating procedures should be evaluated as part of the review 1.

How is a PSSR carried out?

The rule states what the review must confirm, not how it is organized 1. Investigations show how it goes wrong in practice:

  • At Institute, West Virginia (2008), the review was not a formal multi-discipline process and did not directly involve operators; it used an eight-page yes, no or not-applicable checklist, did not verify modifications in the field, and listed open items with owners but no due dates 6.
  • At Texas City, Texas (2005), the refinery's own policy called for a formal review after turnarounds by a technical team led by the operations superintendent, checking safety systems, procedures, training, alarms and instrument calibration, with management sign-off 7. The CSB found that none of those steps were carried out before the unit was restarted, because the coordinator for that area did not know the policy applied 7.

The requirement goes back to Section 304 of the Clean Air Act Amendments of 15 November 1990, which listed pre-startup reviews of newly installed or modified equipment among the minimum elements OSHA's standard had to contain; the final standard followed on 24 February 1992 3.

Where integrity problems show up

Decision or step at this stageWhat it affects laterIn the Library
Confirming construction and equipment match designOSHA guidance keeps as-built drawings, vessel certifications and materials of construction in the quality assurance file used for mechanical integrity 1What documents are handed over when a project is completed?
Equipment checked and calibrated before chemicals enterAt Institute, equipment was not tested and calibrated before the restart 6What is mechanical integrity (MI)?
Open items given owners and due datesAt Institute, an open item on technical coverage for start-up had owners but no due date 6Punch list
Shutdown changes routed through MOC before restartPiping and instrumentation diagrams and procedures updated before chemicals return 1What is management of change (MOC)?
Pre-startup inspections and tests documentedEach inspection and test record must show date, person, equipment identifier and result 1What inspection records do codes require you to keep?

Sources: 29 CFR 1910.119 and Appendix C 1; CSB Report No. 2008-08-I-WV, 2011 6.

Common questions

What is the difference between a PSSR and management of change?
MOC controls a change before it is made, including its safety and health impact. A PSSR checks that the finished new or modified facility is ready before chemicals are introduced, and for modified facilities it confirms MOC was met.
Is a PSSR the same as ready for start-up (RFSU)?
No. A PSSR is a regulatory requirement under OSHA and EPA rules; RFSU is a project milestone defined by contract.
Is a PSSR needed after every turnaround?
Not under the rule itself, unless the work modified the facility enough to change its process safety information. Some sites require one anyway; the Texas City refinery's policy did.

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.29 CFR 1910.119, Process safety management of highly hazardous chemicals, including Appendix C · eCFR, US Office of the Federal Register
  2. 2.40 CFR 68.77, Pre-startup review · eCFR, US Office of the Federal Register
  3. 3.Process Safety Management (OSHA 3132) · US Occupational Safety and Health Administration (OSHA)
  4. 4.Standard interpretation, 1910.119: at what point a work site change would no longer be considered a modification but a new facility · US Occupational Safety and Health Administration (OSHA) ·
  5. 5.Standard interpretation, 1910.119(e)(6): updates to PHA, extended shutdown facility · US Occupational Safety and Health Administration (OSHA) ·
  6. 6.Investigation Report: Pesticide Chemical Runaway Reaction Pressure Vessel Explosion, Bayer CropScience, LP, Institute, West Virginia, August 28, 2008 (Report No. 2008-08-I-WV) · US Chemical Safety and Hazard Investigation Board (CSB)
  7. 7.Investigation Report: Refinery Explosion and Fire, Texas City, Texas, March 23, 2005 (Report No. 2005-04-I-TX) · US Chemical Safety and Hazard Investigation Board (CSB)