What are technical queries and deviations in a bid?
A technical query is a written question that clarifies the bidding documents or a bid; a deviation is a point where the bid departs from the requirements. A technical deviation list sets out each departure. World Bank bidding documents reject bids with material deviations, and US federal rules (48 CFR 14.404-2) reject nonconforming bids unless alternates were allowed.
By Jun Zhong, Editor·Researched and drafted by Beacon's AI newsroom·Checked by Jun Zhong, Editor·Last checked ·Next review
Why does it matter?
A technical query answered after bids are opened cannot turn a non-compliant bid into a compliant one. World Bank bidding documents allow clarifications only if the price and substance of the bid stay the same, and state that a bid with a material deviation cannot later be made responsive by correcting it 2. US federal rules likewise bar using exchanges before the competitive range to cure deficiencies in a proposal 4. A deviation that is accepted becomes part of the contract, and in a process plant part of the safety records 3,7.
What is a technical query?
These definitions come from public procurement rules (World Bank documents and the US Federal Acquisition Regulation, FAR, at 48 CFR), used here to define terms; private oil and gas companies set their own procedures. FAR is cited as codified on 22 October 2026; many agencies apply rewritten Parts 13 to 15 (September 2025) as deviations 12.
On this page, "technical query" means a written question on technical content; public rules handle such questions differently depending on when they are asked and by whom 2,3,4:
| Stage | Who asks | What it may do | What it may not do | Reference |
|---|---|---|---|---|
| Before bids are due | Bidder | Ask for an explanation of the documents; the answer goes to all bidders without naming who asked | Change requirements except by a formal addendum or amendment | World Bank ITB 7 and 9 2; 48 CFR 52.214-6 and 14.208 3,5 |
| After bids are opened | Buyer | Ask a bidder to clarify its bid, in writing; confirm arithmetic corrections | Change the price or substance of the bid | World Bank ITB 29 2 |
| Negotiated proposals | Buyer | Clarify minor points; later, discuss deficiencies and weaknesses with offerors in the competitive range, who may then revise | Use early communications to cure deficiencies | 48 CFR 15.306 4 |
| Two-step sealed bidding, step one | Buyer | Ask for more information on proposals that could be made acceptable | Discuss a proposal with anyone except its submitter | 48 CFR 14.503-1 3 |
Before bids are due, oral explanations do not bind the buyer, and information given to one bidder must reach all bidders as an amendment if they need it 5. After opening, a bidder that misses the deadline for answering a clarification request may have its bid rejected, and clarifications the buyer did not ask for are not considered 2.
What counts as a deviation?
World Bank bidding documents use three terms 2:
- Deviation: a departure from the requirements in the bidding document. 2
- Reservation: setting limiting conditions, or withholding complete acceptance of the requirements. 2
- Omission: leaving out some or all of the required information or documents. 2
Any of these is material if accepting it would substantially affect the scope, quality or performance of what is bought, or would limit the buyer's rights or the bidder's obligations in a way the documents do not allow, or if correcting it would unfairly affect the other bidders 2. US sealed bidding uses a similar test: a bidder's condition is substantive when it affects price, quantity, quality or delivery, while a minor informality has only a negligible effect on those and can be cured or waived 3.
A technical deviation list is the bidder's item-by-item statement of these departures. US federal proposal instructions ask for the same information in general form: the first page of a proposal must state the extent of the offeror's agreement with the solicitation's terms 6. World Bank guidance notes that few bids are perfect in every respect, and points evaluators to deficiencies that would give a bidder an unfair advantage, such as lower quality that allows a lower price 1.
How are deviations handled during evaluation?
| Finding | Treatment under public rules | Reference |
|---|---|---|
| Material deviation, reservation or omission | Bid rejected; it cannot be made responsive later by correcting the deviation | World Bank ITB 32 2 |
| Bid does not conform to the specifications | Rejected, unless the solicitation allowed alternates and the alternate meets its requirements | 48 CFR 14.404-2(b) 3 |
| Bidder imposes conditions that change the requirements | Rejected; a low bidder may be asked to drop conditions only if they concern form, not substance | 48 CFR 14.404-2(d), (e) 3 |
| Nonmaterial nonconformity | May be waived; missing documents may be requested; price adjusted for comparison only | World Bank ITB 33 2 |
| Minor informality, such as too few signed copies | Cured or waived, whichever favors the buyer | 48 CFR 14.405 3 |
In negotiated procurement, the contracting officer must raise deficiencies and significant weaknesses with each offeror still in the competitive range, and offerors may revise their proposals in response 4. In US sealed bidding, any change in a bid that the buyer accepts must appear in the award, and the bid plus the award form the contract 3. On oil and gas projects using industry specifications, IOGP's JIP33 guidance is that a deviation from its specifications on an ongoing project is raised directly with the client 8.
Where integrity problems show up
| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| A material grade deviation is accepted, or a substitution is not verified | At a refinery in Texas City, Texas, in 2005, a carbon steel elbow fitted by mistake during maintenance where 1.25% chromium steel was required failed by high temperature hydrogen attack after fewer than 3,000 hours 9 | What is positive material identification (PMI)? |
| Material test certificates are omitted or incomplete | Where required, US onshore steel gas transmission operators without traceable, verifiable and complete records must verify properties through tests and examinations 11 | What is a mill test certificate (EN 10204 3.1 and 3.2)?, What is material traceability? |
| Toughness test values are not supplied | For those pipelines, toughness values needed for certain pressure reconfirmation and fracture analyses must be kept for the pipeline's life; if missing, they must be verified by accepted methods 11 | What is material traceability? |
| A post-weld heat treatment requirement is waived | OSHA guidance reports cracking in amine and wet hydrogen sulfide service at or near welds, less often where welds were heat treated 10 | What is post-weld heat treatment (PWHT)? |
| Vendor documents are omitted | Process safety information must include materials of construction and design codes, and a pre-startup safety review checks equipment against the design specifications 7 | What is vendor document management? |
Sources: CSB Safety Bulletin 2005-04-B, 2006 9; 49 CFR 192.607(b), (c) 11; OSHA Technical Manual, Section IV, Chapter 3 10; 29 CFR 1910.119(d), (i) 7.
Common questions
- Is a technical query the same as a deviation?
- No. A query asks for an explanation; a deviation is where the offer differs from the requirements. A query can reveal a deviation, but after opening it cannot remove a material one.
- Who decides whether a deviation is acceptable?
- The buyer, under its own procedures and the solicitation's terms. In World Bank procurement the buyer judges responsiveness from the contents of the bid itself.
Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.
Sources
- 1.Procurement Guidance: Evaluating Bids and Proposals, Including Use of Rated Criteria for Procurement of Goods, Works, and Non-Consulting Services (Third Edition), Section VIII · The World Bank
- 2.Standard Procurement Document: Request for Bids, Non-Consulting Services (Management Services), Section I Instructions to Bidders, ITB 7, 9 and 29 to 33 · The World Bank
- 3.48 CFR Part 14, Sealed Bidding (FAR Part 14) · eCFR, US Office of the Federal Register
- 4.48 CFR Part 15, Contracting by Negotiation (FAR Part 15) · eCFR, US Office of the Federal Register
- 5.48 CFR 52.214-6, Explanation to Prospective Bidders · eCFR, US Office of the Federal Register
- 6.48 CFR 52.215-1, Instructions to Offerors: Competitive Acquisition · eCFR, US Office of the Federal Register
- 7.29 CFR 1910.119, Process safety management of highly hazardous chemicals · eCFR, US Office of the Federal Register
- 8.JIP33 FAQs · International Association of Oil & Gas Producers (IOGP), Joint Industry Programme 33
- 9.Safety Bulletin No. 2005-04-B, BP Texas City, TX Refinery Fire: Positive Material Verification: Prevent Errors During Alloy Steel Systems Maintenance · US Chemical Safety and Hazard Investigation Board (CSB) ·
- 10.OSHA Technical Manual, Section IV, Chapter 3: Pressure Vessel Guidelines · US Occupational Safety and Health Administration (OSHA)
- 11.49 CFR 192.607, Verification of pipeline material properties and attributes: Onshore steel transmission pipelines · eCFR, US Office of the Federal Register
- 12.FAR Overhaul: FAR Part Deviation Guidance · Acquisition.gov, US General Services Administration