ExxonMobil starts Uaru, the fifth Stabroek FPSO, lifting Guyana's installed capacity to 1.1 million b/d
ExxonMobil said on November 16 that production has started at Uaru, the fifth development on Guyana's Stabroek block, through MODEC's Errea Wittu FPSO, which is expected to reach its initial 250,000 b/d in the first quarter of 2027. The start-up lifts the block's installed capacity to 1.1 million b/d and brings a second FPSO supplier onto the block: the same day, MODEC awarded the integration of Hammerhead's FPSO, due in 2029.
By Jun Zhong, Editor·Researched and drafted by Beacon's AI newsroom
Where it stands
Uaru is producing but not yet at rate: ExxonMobil expects the Errea Wittu FPSO to reach its initial capacity of 250,000 b/d in the first quarter of 2027, and with it the Stabroek block's installed capacity reaches 1.1 million b/d 1 2. The start-up release gives no first-day rate, well count or gas disposition figures 1.
What happened
ExxonMobil announced the start-up on November 16 from Spring, Texas. Errea Wittu joins the Destiny, Unity, Prosperity and ONE GUYANA FPSOs on the block, and can store 2 million barrels; ExxonMobil Guyana operates with 45 percent, Hess Guyana Exploration holds 30 percent and CNOOC Petroleum Guyana 25 percent 1 2.
MODEC delivered the vessel in August on a new-built, full double hull with a larger topside deck, designed for 250,000 b/d of oil and 540 MMcf/d of gas treatment, spread-moored about 200 km offshore in 1,690 m of water; at that point it still had final offshore preparations and commissioning ahead of first oil 3. ExxonMobil calls it MODEC's entry into the Guyana market 1.
The block's next units follow on a set schedule: Whiptail in 2027, Hammerhead in 2029, and Longtail, the first gas and condensate development, which recently reached a final investment decision 2. On the same day as the start-up, MODEC awarded Seatrium the topsides integration, flare tower and crane pedestal fabrication and commissioning support for Hammerhead's FPSO, Essequibo 1899, designed for about 150,000 b/d in about 1,025 m of water; Seatrium also integrated Errea Wittu 4.
What it means
The next four months are the risk window. An FPSO ramping from first oil to nameplate is where topsides, gas compression and injection systems first see design loads, and Uaru's 540 MMcf/d of gas treatment is a large share of the job on a 250,000 b/d unit. The first quarter of 2027 target is the test to watch; any slip in reaching it will show first as flat Guyana export loadings, not as a statement.
The block now has two FPSO suppliers. Uaru and Hammerhead are MODEC units integrated by Seatrium, and ExxonMobil describes Uaru as MODEC's first in Guyana, so none of the four earlier FPSOs share its design lineage. For an integrity manager benchmarking the block, that means a second set of hull, mooring and topsides designs to baseline, with different inspection histories and spares, rather than a fifth copy of a known unit. For investors, Uaru's ramp-up is the volume behind Guyana's next leg of growth, while the gas side of the block, from reinjection to Longtail's route to market, is still being decided.
Next decision dates: Errea Wittu at 250,000 b/d in the first quarter of 2027, and Whiptail start-up in 2027.
Sources
- 1.ExxonMobil starts production at Uaru, raising Guyana's installed capacity to 1.1 million barrels per day · ExxonMobil ·
- 2.ExxonMobil starts Uaru production, lifting Guyana capacity to 1.1 MMbpd · World Oil ·
- 3.ExxonMobil Guyana receives Errea Wittu FPSO at Uaru field · Oil & Gas Journal ·
- 4.Seatrium wins integration contract for Hammerhead FPSO offshore Guyana · World Oil ·