What is the EPA Risk Management Program (RMP) rule?

·7 sources

Short answer

The EPA Risk Management Program (RMP) rule, 40 CFR 68, covers facilities holding more than a threshold quantity of a listed toxic or flammable substance. They must assess hazards, run an accident prevention program, plan emergency response and submit a risk management plan to EPA, updated at least every five years.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

About 11,740 facilities had current risk management plans on file with the US Environmental Protection Agency (EPA) when the 2024 amendments were published, from refineries and chemical plants to oil and gas extraction sites 2. For the most hazardous processes, EPA describes the prevention program as fundamentally identical to the Occupational Safety and Health Administration (OSHA) process safety management standard, so the same mechanical integrity and inspection records serve both 3. The rule text has changed in 2017, 2019 and 2024, and EPA proposed further changes in February 2026, so which requirement applies depends on the date 3,4.

Who is covered by the RMP rule?

The rule implements Clean Air Act section 112(r)(7) and applies to a stationary source when a process there holds a regulated substance in an amount above that substance's threshold quantity 1,7. The substances and thresholds are listed in 40 CFR 68.130 1. Sources on the Outer Continental Shelf are excluded 1.

Sector (North American Industry Classification System, NAICS, code)Facilities with current RMPs, 2024 2
Petroleum and coal products manufacturing (324)156
Chemical manufacturing (325)1,502
Oil and gas extraction (211)719
Petroleum wholesalers (4247)367
All covered sectors11,740

Separate from Part 68, the General Duty Clause in Clean Air Act section 112(r)(1) requires owners and operators of stationary sources handling listed or other extremely hazardous substances to identify hazards, design and maintain a safe facility and limit the consequences of releases; neither the 2024 nor the 2026 rulemaking changed its scope 2,3,7.

What are RMP Programs 1, 2 and 3?

Each covered process is placed in one of three programs 1,3.

ProgramWhen it appliesPrevention requirements
1No accidental release with offsite deaths, injuries or environmental response in the past 5 years, no public receptor within the worst-case endpoint distance, and emergency response coordinated locally 1Minimal: worst-case scenario, accident history, certification 1
2Any process not eligible for Program 1 or Program 3 1Streamlined; no management of change, pre-startup review, contractor, employee participation or hot work elements 3
3Not eligible for Program 1, and either in one of ten listed NAICS industry codes or subject to OSHA's process safety management standard 1Full prevention program, which EPA calls fundamentally identical to process safety management 3

What does a risk management program contain?

  • Hazard assessment: offsite consequence analysis, including a worst-case release scenario, and a five-year accident history 1,3.
  • Prevention program: for Program 3, process safety information, process hazard analysis, operating procedures, training, mechanical integrity, management of change, pre-startup review, compliance audits, incident investigation, employee participation, hot work and contractors 1.
  • Emergency response: coordination with local responders and, where required, an emergency response program and exercises 1.
  • Management system and the plan itself: the risk management plan is submitted to EPA and updated at least every five years, or sooner after changes that alter the hazard analysis, the offsite consequence analysis or the program level 1.

How has the RMP rule changed since 2017, and what is its status now?

DateActionEffect
20 Jun 1996Original RMP rule (61 FR 31668)Compliance required from 21 Jun 1999 1,3
13 Jan 2017Amendments rule (82 FR 4594)Added safer technology, root cause, third-party audit and information provisions; key provisions paused, most never took effect 3,5
19 Dec 2019Reconsideration rule (84 FR 69834)Rescinded most of the 2017 prevention additions 3
11 Mar 2024Safer Communities by Chemical Accident Prevention rule (89 FR 17622), effective 10 May 2024Restored many 2017 requirements and added others 2,6
30 Dec 2024Notice denying a petition to reconsider the 2024 rule (89 FR 106479)2024 rule left in place 6
12 Mar 2025EPA announced it was reconsidering the 2024 ruleNo rule change by itself 5
24 Feb 2026Common Sense Approach proposed rule (91 FR 8970); comments accepted to 11 May 2026Proposes changes in 14 areas, including safer technology analysis, third-party audits, process safety information and recognized and generally accepted good engineering practice (RAGAGEP) 3,5

Status as of 25 October 2026: the Federal Register shows no final rule on the 2026 proposal, and 40 CFR 68.10 (eCFR, up to date as of 22 October 2026) still sets the 2024 compliance dates: 10 May 2027 for most new prevention provisions, including root cause analysis and third-party audits; 15 March 2027 for certain field exercises; and 10 May 2028 for the new plan content 1,3. The proposal would keep 10 May 2027 for root cause analysis, employee participation and emergency response, and would give revised safer technology and audit provisions three years from a final rule 3.

Where integrity problems show up

RequirementWhat it means for integrity records or workIn the Library
Process safety information on equipment (40 CFR 68.65(d))Materials of construction, design codes, relief design and piping and instrument diagrams must be kept; older equipment built to codes no longer in general use needs a documented determination that it is still safe 1What is RAGAGEP (recognized and generally accepted good engineering practice)?
Mechanical integrity (40 CFR 68.73)Written procedures; inspections and tests that follow good engineering practice at a frequency set by manufacturers' advice and experience; each record must give the date, inspector, equipment identifier, test and result; deficiencies corrected 1What is mechanical integrity (MI)?
Code gap review in the process hazard analysis (40 CFR 68.67(c)(10), added 2024)Gaps between the codes a process was built to and the current versions must be identified; the 2026 proposal would rescind this item 1,3What is process safety management (PSM)?
Compliance audits at least every three years (40 CFR 68.79)Findings and corrections are documented and the two latest reports kept; after a reportable accident the next audit must be a third-party audit (compliance date 10 May 2027) 1What is a PSM compliance audit?
Incident investigation (40 CFR 68.81)Starts within 48 hours; reports kept five years; for reportable accidents, a root cause analysis completed within 12 months (compliance date 10 May 2027) 1What is management of change (MOC)?
Five-year accident history and plan updates (40 CFR 68.42, 68.190)Each reportable release, with date, chemical and quantity, enters the plan, which is updated at least every five years 1What inspection records do codes require you to keep?

Sources: 40 CFR Part 68, eCFR up to date as of 22 Oct 2026 1; 91 FR 8970, 2026 3.

Common questions

Is the RMP rule the same as OSHA process safety management?
No, but they overlap. OSHA's standard (29 CFR 1910.119, published 1992) is a workplace rule; EPA's rule adds offsite consequence analysis, emergency response coordination and a plan filed with EPA. EPA has kept the Program 3 prevention elements aligned with OSHA's so that a site runs one prevention program.
What is the difference between a risk management program and a risk management plan?
The program is the set of activities a facility carries out under 40 CFR 68; the plan is the summary document submitted to EPA.
Does the RMP rule apply offshore?
Not on the Outer Continental Shelf: 40 CFR 68.10 excludes those sources. Offshore safety management is covered by the [BSEE SEMS rule](/library/bsee-sems/).

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.40 CFR Part 68, Chemical Accident Prevention Provisions · eCFR, US Office of the Federal Register
  2. 2.Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act; Safer Communities by Chemical Accident Prevention (final rule), 89 FR 17622 · US Environmental Protection Agency, via Federal Register (govinfo) ·
  3. 3.Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act; Common Sense Approach to Chemical Accident Prevention (proposed rule), 91 FR 8970 · US Environmental Protection Agency, via Federal Register (govinfo) ·
  4. 4.Risk Management Program (RMP) · US Environmental Protection Agency (EPA)
  5. 5.Common Sense Approach to Chemical Accident Prevention Proposed Rule · US Environmental Protection Agency (EPA)
  6. 6.Risk Management Program Safer Communities by Chemical Accident Prevention Final Rule · US Environmental Protection Agency (EPA)
  7. 7.42 U.S.C. 7412(r), Prevention of accidental releases (United States Code, 2023 edition) · US Government Publishing Office (govinfo)