What is a design basis?
A design basis is the controlled set of requirements and data that a design must meet. It covers purpose and capacity, feed and product specifications, site and environmental conditions, design life, codes and standards, and safety philosophy. In US process plants, federal rule 29 CFR 1910.119(d) requires much of this information, including the codes used, to be documented.
By Jun Zhong, Editor·Researched and drafted by Beacon's AI newsroom·Checked by Jun Zhong, Editor·Last checked ·Next review
Why does it matter?
During the US Occupational Safety and Health Administration (OSHA) refinery emphasis program that began in June 2007, inspectors found that many refineries had no written record of why their relief systems were designed as they were 1. That record is part of the process safety information US rules require, and OSHA notes that it keeps staff informed of the current relief design so that later process changes can be made appropriately 1,2. A design basis plays the same role for the whole plant. A 2015 peer-reviewed paper on critical infrastructure projects stresses that it must be set accurately in the early phases, because changing a design early is usually cheaper than rebuilding 3.
What goes into a design basis?
The table groups the usual contents; each group is named in at least one public rule or study 4,5,2,7,6,3:
| Group | Typical contents | Where a public rule or study names it |
|---|---|---|
| Purpose and performance | Functions, capacity, key performance parameters | US Nuclear Regulatory Commission (NRC) definition of design bases: functions and the values chosen for controlling parameters 4; DOE conceptual design report: functions, requirements, key performance parameters 5 |
| Process conditions | Feed and product compositions and specifications, normal and upset operating ranges | OSHA: safe upper and lower limits and the consequences of deviation 2; a public FEED: product specification and measured feed gas composition 6 |
| Site and environment | Location, ambient and weather data, sea state and seabed offshore, water supply | UK offshore design notification: meteorological, oceanographic and seabed data 7; a public FEED: water supply under 25-year drought conditions 6 |
| Codes, standards and philosophy | Design codes, owner specifications, design philosophy | OSHA: design codes and standards employed 2; UK design notification: standards and design philosophy 7 |
| Hazards and safety level | Accidental loads, relief and depressuring scenarios, target safety level | Peer-reviewed review: accidental conditions and the selected safety level 3; OSHA: relief system design and design basis 2 |
| Materials and life | Corrosivity data, materials philosophy, corrosion allowance, design life | OSHA: corrosivity data and materials of construction 2; design life used to set corrosion allowance and fatigue margins |
| Utilities and logistics | Steam, power, cooling, limits on transporting large equipment | A public FEED: steam and power sourcing, maximum shipping dimensions and weights 6 |
Sources as numbered. The grouping is Beacon's; "a public FEED" is a DOE-funded carbon capture FEED presented in 2020 6.
Who writes it, and when does it change?
The design basis is set early and then controlled. The Construction Industry Institute (CII) describes front end planning as the stage that sets the design basis through scope decisions 8, and in the public FEED example the design basis document was the first engineering milestone 6. The 2015 review adds that the basis has to be updated as new information arrives in later phases 3.
Control means changes are reviewed before they are accepted. The US Department of Energy (DOE) applies this to its "code of record" for nuclear facilities: a set of design and operating requirements started in conceptual design, kept under configuration control, revised only after the safety, cost and schedule impact is evaluated, and maintained until decommissioning 5. Under US process safety management, any change to process chemicals, technology, equipment or procedures other than a replacement in kind needs a management of change procedure that addresses its technical basis, and a modification large enough to change the process safety information needs a pre-startup safety review 2.
Old plants raise a special case. Where equipment was designed to codes or practices no longer in general use, OSHA requires the employer to determine and document that it is still designed, maintained, inspected, tested and operated safely 2.
How is a design basis different from related terms?
- Basis of design (BOD) is usually a synonym. UK offshore rules, for example, ask for the "basis of design" of any well connected to a new production installation 7.
- Design bases is the US nuclear term. NRC defines it as the information that identifies what a structure, system or component must do and the reference values for its controlling parameters, drawn from accepted practice or from analysis of postulated accidents 4.
- Relief system design basis is one part of the whole: the documented reasons a relief system was designed and sized as it was 1.
Where integrity problems show up
| Decision or step at this stage | What it affects later | In the Library |
|---|---|---|
| Recording corrosivity data and materials of construction | Damage mechanism reviews; California requires one for refinery processes and requires process safety information to exist before it 2,9 | What is a damage mechanism review? |
| Recording safe upper and lower operating limits | Later reviews of operating conditions that speed up or slow down damage 2,9 | What are integrity operating windows (IOWs)? |
| Recording the design codes and standards used | Later inspection, repair and rerating; equipment built to codes no longer in general use must be shown to be safe 2 | What is rerating of pressure equipment? |
| Recording the relief system design basis | Checking relief capacity after process changes; OSHA found many refineries lacked it 1 | What does a pressure relief valve do? |
| Updating process safety information after a significant modification | A pre-startup safety review before restart 2 | What is a pre-startup safety review (PSSR)? |
Sources: 29 CFR 1910.119 2; OSHA 3918, 2017 1; California Code of Regulations, Title 8, Section 5189.1 9.
Common questions
- Is a design basis the same as a basis of design?
- They name the same kind of document: one that fixes what the design must achieve and under which conditions. UK offshore rules use "basis of design", while the 2015 research paper uses "design basis".
- Does the design basis change after start-up?
- It can, but only through a controlled change. Under US process safety management, changes go through management of change, and the process safety information is updated. DOE keeps its nuclear code of record under control until decommissioning.
- Is a design basis the same as a FEED?
- No. The design basis is an input document; front-end engineering design (FEED) is the phase that develops the design from it. See [What is front-end engineering design (FEED)?](/library/front-end-engineering-design/).
Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.
Sources
- 1.Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918) · US Occupational Safety and Health Administration (OSHA)
- 2.29 CFR 1910.119, Process safety management of highly hazardous chemicals · eCFR, US Office of the Federal Register
- 3.Establishment of design basis in the initial phase of critical infrastructure projects (O. T. Gudmestad), International Journal of Critical Infrastructures 11(2): 183-194 (abstract) · Inderscience, via RePEc/IDEAS
- 4.10 CFR 50.2, Definitions (design bases) · eCFR, US Office of the Federal Register
- 5.DOE O 413.3C, Program and Project Management for the Acquisition of Capital Assets · US Department of Energy (DOE), Office of Project Management
- 6.Full-Scale FEED Study for a 816 MWe Capture Plant at the Prairie State Generating Company Using Mitsubishi Heavy Industries of America Technology (K. C. O'Brien, University of Illinois), DOE/NETL 2020 Integrated Review Meeting · US DOE National Energy Technology Laboratory (NETL) ·
- 7.The Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015 (SI 2015/398), Schedule 5, as made · legislation.gov.uk, UK National Archives
- 8.Front End Planning: Your Key to a Successful Project (WS213-01) · Construction Industry Institute (CII), University of Texas at Austin ·
- 9.California Code of Regulations, Title 8, Section 5189.1, Process Safety Management for Petroleum Refineries · California Department of Industrial Relations