What is a factory acceptance test (FAT)?

·8 sources

Short answer

A factory acceptance test (FAT) is a set of tests at the supplier's works, before shipment, showing that equipment meets its purchase specification. The buyer often witnesses it. A site acceptance test (SAT) checks the equipment again after installation. IEC 62381:2024 covers FAT and SAT, with integration tests, for process automation systems.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

In a UK Health and Safety Executive (HSE) analysis of 34 control system incidents, 44% had their primary cause in the specification, before anything was built or tested 1. A FAT is designed to show that a system meets its specification 2, so it tests against the requirements as written; HSE's guidance starts planning these tests during design, when the designer can best judge which tests show that the user's needs are met 1. The same analysis put 6% of primary causes in installation and commissioning and 20% in changes after commissioning, and HSE notes that the small sample limits how far the split can be generalized 1.

What happens at a factory acceptance test?

The supplier runs the tests at its own facility, usually with its own staff, before the product is delivered 3. A test plan sets out the procedure and acceptance criteria for each test, a checklist lists the items to inspect, and tests can include process simulations 3. For automation systems, IEC 62381:2024 sets requirements and checklists for FAT and the related integration and site tests, and gives the owner, buyer and vendor a way to agree the scope and who does what 2. For safety-related control systems, HSE treats factory acceptance testing as part of safety validation and expects a log of results listing the test equipment, calibration data and every discrepancy 1.

Testing at the factory has practical reasons. US federal purchasing rules call for inspection at the source when checking elsewhere would need uneconomical dismantling or destructive tests, when shipping a nonconforming item or delaying its correction would cause considerable loss, or when the special instruments needed exist only at the source 4. A 2024 position paper from DECHEMA, the German chemical engineering society, notes that packaged units can be commissioned in the vendor's workshop, while on a plant built in place most commissioning happens at site 8.

How does a FAT differ from a site acceptance test?

Factory acceptance test (FAT)Site acceptance test (SAT)
WhereSupplier's works 3Owner's site 3
WhenBefore shipment 3After installation 3
What it showsThe product meets the purchase specification 2,3The equipment works in its intended environment and with existing systems 3
Integration testingFactory integration test (FIT), optional since the 2024 edition of IEC 62381 2Site integration test (SIT) 2
US federal purchasing parallelQuality assurance at source 4Quality assurance at destination, used for example when the test equipment exists only there 5

Sources: IEC publisher page for IEC 62381:2024 2; SKYbrary, 2024 3; 48 CFR 46.402 and 46.403 4,5.

The split is not always clean. HSE notes that when hardware and application software come from different subcontractors, the control system's validation may not be finished at the factory and is completed on site after installation 1. For complex software, HSE adds that final acceptance testing cannot usually be relied on to find design faults, so outputs are checked at each step of the design 1.

Where integrity problems show up

Decision or step at this stageWhat it affects laterIn the Library
Writing the requirements the FAT will test against44% of 34 control system incidents analyzed by HSE had their primary cause in the specification 1What is a safety instrumented system (SIS)?
Planning tests during design rather than after manufactureFor complex software, final acceptance tests cannot usually be relied on to find design faults 1What is a safety integrity level (SIL)?
Logging FAT results, calibration data and discrepanciesThe log forms the basis of the validation report 1What documents are handed over when a project is completed?
Confirming installed equipment matches the design before start-upUS process safety rules require a pre-startup safety review of construction and equipment against design specifications 6What is a pre-startup safety review (PSSR)?
Changing the system after commissioning20% of primary causes in the HSE analysis 1What is management of change (MOC)?

Sources: HSE, Out of control (HSG238), 2003 1; 29 CFR 1910.119(i) 6.

Common questions

Who attends a FAT?
The supplier's staff run it, and IEC 62381 gives the owner, buyer and vendor a common basis to agree scope and responsibilities. A UK quality profession guide notes that a main contractor may visit the factory and take part in FATs for work made off site.
What is a factory integration test (FIT)?
It is an optional test step that the 2024 edition of IEC 62381 added to the factory acceptance, site acceptance and site integration tests it already covered.
Is a FAT the same as a pre-startup safety review?
No. A pre-startup safety review under US process safety rules takes place at site before highly hazardous chemicals are introduced, and confirms construction, equipment, procedures, hazard analysis and training. See [What is a pre-startup safety review (PSSR)?](/library/pre-startup-safety-review/).

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.Out of control: Why control systems go wrong and how to prevent failure (HSG238) · UK Health and Safety Executive (HSE)
  2. 2.IEC 62381:2024, Automation systems in the process industry - Factory acceptance test (FAT), site acceptance test (SAT), and site integration test (SIT) (publisher page) (3.0 (2024)) · International Electrotechnical Commission (IEC) ·
  3. 3.Factory acceptance test (FAT) · SKYbrary Aviation Safety ·
  4. 4.48 CFR 46.402, Government contract quality assurance at source · eCFR, US Office of the Federal Register
  5. 5.48 CFR 46.403, Government contract quality assurance at destination · eCFR, US Office of the Federal Register
  6. 6.29 CFR 1910.119, Process safety management of highly hazardous chemicals · eCFR, US Office of the Federal Register
  7. 7.How to write an inspection and test plan (M. Buss; reviewed for the CQI Construction Special Interest Group) · Designing Buildings Wiki, on behalf of the Chartered Quality Institute (CQI) Construction Special Interest Group
  8. 8.Cost Engineering for Modular Plants: Position paper for the evaluation of different plant setups, construction, and operational concepts · DECHEMA Gesellschaft für Chemische Technik und Biotechnologie e.V.