What is an inspection and test plan (ITP)?

·13 sources

Short answer

An inspection and test plan (ITP) lists, in sequence, every inspection and test for an item and who must take part in each. For each step it names the procedure, acceptance criteria and record, and marks each party's role: hold, witness, review or monitor. The supplier, purchaser and any independent inspector sign the steps assigned to them.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

A pressure vessel is ready for its hydrostatic test but the purchaser's inspector has not arrived; whether the shop may start depends on how the inspection and test plan marks that step. If it is a hold point, work stops until the named party has inspected or agreed, and the US nuclear quality rule, one public model, requires such hold points to be written into the work documents 1. In oil and gas equipment purchasing, the industry's standardized procurement specifications place the purchaser's hold and witness points in a quality requirements document issued with the request for quotation 3. Unplanned and unrecorded checks let defects pass: the US National Transportation Safety Board (NTSB) found no records of radiography or pressure testing for the 1956 pipeline work that failed at San Bruno, California, in 2010 7. The US National Institute of Standards and Technology (NIST) noted in its 1990 pressure vessel guidelines that poor quality control during manufacture can erode the safety margin built into the design and can lie behind problems that appear later in service 13.

What does an ITP contain?

NASA's hardware quality rules describe the content in general terms: they expect work instructions to give the sequence of steps, the procedures and process specifications to use, inspection and test methods, acceptance criteria, and the hold and inspection points of both the supplier and the buyer 2. The US nuclear rule expects inspection and test records to name the inspector, the type of observation, the result and whether it was acceptable 1. A guide reviewed by the UK Chartered Quality Institute's construction group notes that there are no standard ITP codes, that each organization sets its own, and that an ITP can state how much each party checks, such as 100% witnessing by a main contractor and 10% inspection by the client 5.

Illustrative numbers, not from any real asset or standard table

Illustrative example, not from any real project, code or standard. Key: P perform, H hold, W witness, R review, M monitor.

StepActivityReference documentRecordManufacturerPurchaserIndependent inspector
1Review procedures and drawingsPurchase order, code, drawingsApproved document listPRR
2Check material certificates and markingMaterial specificationMill test certificates, receiving recordPRM
3Alloy check on alloy partsPMI procedurePMI reportPWM
4Weld with qualified procedures and weldersWelding procedures and qualificationsWeld mapPRM
5Post-weld heat treatmentHeat treatment procedureTime and temperature chartPRR
6Nondestructive examinationNDE proceduresNDE reportsPRW
7Hydrostatic testTest procedureTest record and chartPHH
8Final inspection and data reportCode, drawingsDimensional report, data reportPWH

What are hold, witness, review and monitor points?

PointWhat it meansCan work go on without the party?Public description
Hold (H)The next step waits until the named party inspects or gives consentNo10 CFR 50 Appendix B, Criterion X 1; NASA mandatory inspection points 2
Witness (W)The named party is invited to watch a test or processSet by the contract and the ITP's own rules 5NASA process and test witnessing 2
Review (R)The party checks documents or records, such as certificates or test dataYes, unless also marked as a hold 5NASA documentation and production record review 2
Monitor (M) or surveillancePeriodic or sample checks on how work is doneYesProcess monitoring 1; surveillance 2,5

On oil and gas orders that use the standardized procurement specifications of JIP33, a program the International Association of Oil & Gas Producers (IOGP) started in 2016, the quality requirements specification sets the purchaser's level of involvement in inspection and testing 3,4. It offers four conformity assessment levels, which JIP33 says follow a conformity assessment table in ISO 29001 3.

Who prepares and signs an ITP?

The organization doing the work usually prepares the ITP and checks every item itself; in the CQI guide that organization, frequently the trade contractor, is the one that owns the ITP 5. The buyer chooses its own points: under NASA's rules the buyer selects mandatory inspection points, while the supplier, who controls the schedule, usually says when they fall due 2. A third party is independent of both supplier and buyer 2; for ASME code items, the Authorized Inspector certifies the manufacturer's data report 6. Buyer surveillance adds to the supplier's own responsibility for a conforming product and does not replace it 2.

Where integrity problems show up

Decision or step at this stageWhat it affects laterIn the Library
Reviewing material certificates before useNew line pipe tested up to 15% below its reported yield strength 9What is a mill test certificate (EN 10204 3.1 and 3.2)?
Alloy check for critical alloy parts, also after maintenanceA carbon steel elbow refitted in hot hydrogen service ruptured after about 3 months 10What is positive material identification (PMI)?
Reviewing heat treatment recordsCracking concentrates at welds without post-weld heat treatment in amine and wet hydrogen sulfide service 11; at Anacortes, Washington (2010), hydrogen attack was found only near such welds 12What is post-weld heat treatment (PWHT)?
Witnessing or reviewing nondestructive examinationSome failed girth welds on new pipelines had testing procedures not optimized or not completed 8Radiographic vs ultrasonic testing for welds
Holding for the pressure test and keeping its recordNo pressure test record existed for the 1956 San Bruno work; NTSB said such a test might have ruptured the defective pipe at installation 7What is a hydrostatic test?
Closing out records at the endConstruction records feed later safety assessment of the equipment 11What documents are handed over when a project is completed?

Sources: PHMSA Advisory Bulletins ADB-09-01, 2009 9 and ADB-10-03, 2010 8; CSB Safety Bulletin 2005-04-B, 2006 10; CSB Anacortes report, 2014 12; OSHA Technical Manual, Section IV, Chapter 3 11; NTSB/PAR-11/01, 2011 7.

Common questions

Is an ITP the same as an inspection plan?
No. An ITP covers manufacture and construction. An [inspection plan](/library/inspection-plan/) covers in-service inspection after start-up, which design and construction codes do not address and other documents such as API 510 cover (NIST, 1990).
What happens if a hold point is missed?
Under the nuclear rule, work may not pass a hold point without the designated representative's consent. NASA's rules send skipped mandatory inspection points to a project risk review.
Does an independent inspector replace the manufacturer's quality control?
No. NASA states that buyer and third-party surveillance come in addition to, not instead of, the supplier's own quality responsibilities. See [How is fabrication quality controlled for pressure equipment?](/library/fabrication-quality-control/).

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.10 CFR Part 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants · eCFR, US Office of the Federal Register
  2. 2.NPR 8735.2C, Hardware Quality Assurance Program Requirements for Programs and Projects (updated with Change 2) · US National Aeronautics and Space Administration (NASA)
  3. 3.JIP33 Frequently Asked Questions · International Association of Oil & Gas Producers (IOGP), JIP33
  4. 4.About JIP33 · International Association of Oil & Gas Producers (IOGP), JIP33
  5. 5.How to write an inspection and test plan (M. Buss; reviewed for the CQI Construction Special Interest Group) · Designing Buildings Wiki, on behalf of the Chartered Quality Institute (CQI) Construction Special Interest Group
  6. 6.The Authorized Inspector's Responsibility for Dimensional Inspection (National Board BULLETIN, Classic Series) · National Board of Boiler and Pressure Vessel Inspectors
  7. 7.Pacific Gas and Electric Company Natural Gas Transmission Pipeline Rupture and Fire, San Bruno, California, September 9, 2010 (NTSB/PAR-11/01) · US National Transportation Safety Board (NTSB)
  8. 8.Pipeline Safety: Girth Weld Quality Issues Due to Improper Transitioning, Misalignment, and Welding Practices of Large Diameter Line Pipe (Advisory Bulletin ADB-10-03), 75 FR 14243 · US Pipeline and Hazardous Materials Safety Administration (PHMSA), via Federal Register (govinfo) ·
  9. 9.Pipeline Safety: Potential Low and Variable Yield and Tensile Strength and Chemical Composition Properties in High Strength Line Pipe (Advisory Bulletin ADB-09-01), 74 FR 23930 · US Pipeline and Hazardous Materials Safety Administration (PHMSA), via Federal Register (govinfo) ·
  10. 10.Safety Bulletin No. 2005-04-B, BP Texas City, TX Refinery Fire: Positive Material Verification: Prevent Errors During Alloy Steel Systems Maintenance · US Chemical Safety and Hazard Investigation Board (CSB) ·
  11. 11.OSHA Technical Manual, Section IV, Chapter 3: Pressure Vessel Guidelines · US Occupational Safety and Health Administration (OSHA)
  12. 12.Investigation Report: Catastrophic Rupture of Heat Exchanger (Seven Fatalities), Tesoro Anacortes Refinery, Anacortes, Washington, April 2, 2010 (Report 2010-08-I-WA) · US Chemical Safety and Hazard Investigation Board (CSB)
  13. 13.NIST Special Publication 780, Guidelines for Pressure Vessel Safety Assessment (S. Yukawa) · US National Institute of Standards and Technology (NIST)