Skip to content
Beaconby Winda
FactEngineering Design and Materials · Engineering documents

How does document control work on oil and gas projects?

·12 sources

Short answer

Document control gives each engineering document a unique number, tracks its revisions and approvals, and issues only the current version to its users. It also records what changed, when and why. In US plants covered by the federal process safety standard, 29 CFR 1910.119(l)(4) requires process safety information to be updated when a change alters it.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

Twelve years before the 2013 reboiler rupture at Geismar, Louisiana, a hazard review had noted that the plant's piping and instrumentation diagrams (P&IDs) did not show valves added in 2001 1. The US Chemical Safety and Hazard Investigation Board (CSB) found that the drawing update should have been required through management of change (MOC), and that the pre-startup safety review (PSSR) should have checked a marked-up P&ID of the approved change 1. The reboiler was heated while isolated from its pressure relief device; the CSB recorded two fatalities and 167 reported injuries 1. Which version of a drawing people trust is the question document control exists to answer.

What does document control cover?

Project document control borrows from configuration management, which the US National Aeronautics and Space Administration (NASA) describes as five functions: planning, identification, change management, status accounting and verification 3. On a process plant project these functions apply to drawings, lists, datasheets and vendor documents. The Capital Facilities Information Handover Specification (CFIHOS), an industry specification for handing over project information, defines many of the registers involved 4,9.

StepWhat it doesPublic reference
IdentifyGives each document a unique number and lists every numbered deliverable in one registerNASA 3; CFIHOS master document register 4
Record statusKeeps current and past versions and the status of each proposed changeNASA status accounting 3
Review and approveChecks a drawing before work proceeds; reasons are given when it is not approved48 CFR 52.236-21 5
DistributeGives the people doing the work the current issue and removes outdated copies48 CFR 52.236-21 5; university text 6
Control changeLogs proposed changes and technical deviations and their outcomeCFIHOS change control register 4
Verify and hand overConfirms records match what was built; delivers final drawings showing all changesNASA 3; 48 CFR 52.236-21, Alternate I 5; 29 CFR 1910.119, Appendix C 2

Revision volume is the practical challenge. A University of Michigan process control text notes that a P&ID typically goes through 15 to 20 revisions during process design, and that each revision has to reach everyone who uses it 6.

Which documents are controlled on a process plant project?

Under the process safety management standard of the US Occupational Safety and Health Administration (OSHA), covered plants keep written process safety information on chemical hazards, process technology and equipment 2. The equipment part includes materials of construction, P&IDs, electrical classification, relief system design and design basis, the design codes and standards used, and safety systems 2. OSHA's 2007 refinery inspection program asked each site for flow diagrams, P&IDs with their legends, plot plans, process narratives and the original design basis 7. CFIHOS, now run by the International Association of Oil & Gas Producers (IOGP), adds defined types such as the piping line list, the isometric diagram and design and manufacturer datasheets 4.

How do vendor and contractor documents fit in?

Vendor documents enter through the purchase order. CFIHOS defines a requisition as a request that names the relevant drawings and specifications and lists the documents the supplier must return 4. IOGP's Joint Industry Project 33 (JIP33) procurement specifications do the same through an information requirements specification 8.

US federal construction contracts show one review model. Under 48 CFR 52.236-21, the contractor checks and signs its shop drawings, the government approves or disapproves them with reasons, and work done before approval is at the contractor's risk 5. Approval does not relieve the contractor of errors in the drawings 5.

What happens to documents at handover and after start-up?

Before hazardous chemicals are introduced, the PSSR must confirm that construction and equipment follow the design specifications 2. OSHA's nonmandatory Appendix C adds that as-built drawings, coded vessel certifications and materials of construction should be verified and kept in the quality assurance records 2. CFIHOS exists so that owners receive the data and documents needed to operate, maintain and decommission a facility 9.

After start-up, drawings stay live: a change covered by MOC that alters process safety information requires that information to be updated 2. OSHA inspectors check one P&ID against the equipment in the field 7, and OSHA reported in 2017 that P&ID deficiencies were often systemic and could point to a weak MOC program 10. After the Geismar incident, the operator added field checks of P&IDs before each hazard analysis 1.

Where integrity problems show up

Decision or step at this stageWhat it affects laterIn the Library
Added valves reach the P&ID through a hazard review, not MOC, and the PSSR does not check a marked-up drawingLater reviews use a drawing that does not match the plant; at Geismar, Louisiana (2013), a reboiler isolated from its relief device ruptured 1What is management of change (MOC)?, What is a pre-startup safety review (PSSR)?
P&ID updates miss a change made by closing valvesAt Sunray, Texas (2007), an idle control station became an unrecognized dead leg; water froze and cracked an elbow, and released propane ignited 12Dead leg
As-built drawings, vessel certifications and material records are verified and keptThey form the quality assurance record of mechanical integrity 2What are as-built drawings?
Installation date, material specification and original thickness are kept per piping circuitOSHA checks them, with later thickness readings and retirement thickness 7What should an inspection plan contain?, Baseline inspection
Design code, allowable pressure and temperature, materials, corrosion allowance and post-weld heat treatment are kept per vesselOSHA lists them among records used to assess vessels in service 11Corrosion allowance

Sources: CSB case study on Geismar, Louisiana, 2016 1; CSB report on Sunray, Texas, 2008 12; 29 CFR 1910.119 and Appendix C 2; OSHA CPL 03-00-004, 2007 7; OSHA Technical Manual, Section IV, Chapter 3 11.

Common questions

Is document control the same as management of change?
No. MOC reviews and authorizes a change to the plant itself; document control makes sure drawings and records show it. OSHA links the two: 29 CFR 1910.119(l)(4) requires process safety information to be updated when a change covered by MOC alters it.
What is a master document register?
CFIHOS defines it as a register, kept per individual document, of every deliverable that receives a document number, including drawings, lists, databases and models from contractors and vendors.
Who keeps P&IDs current after start-up?
The operator, through its MOC procedure. OSHA's Appendix C says changed P&IDs should be marked so revisions become permanent when drawings are updated, and records of changes kept where operators and hazard analysis teams can reach them.

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.Williams Geismar Olefins Plant Reboiler Rupture and Fire, Geismar, Louisiana (Case Study No. 2013-03-I-LA) · US Chemical Safety and Hazard Investigation Board (CSB)
  2. 2.29 CFR 1910.119, Process safety management of highly hazardous chemicals (including Appendix C) · eCFR, US Office of the Federal Register
  3. 3.NASA Systems Engineering Handbook, Section 6.5: Configuration Management · US National Aeronautics and Space Administration (NASA)
  4. 4.CFIHOS Core Reference Data Library (C-ST-001), document type list (V2.0) · IOGP JIP36, Capital Facilities Information Handover Specification (CFIHOS) ·
  5. 5.48 CFR 52.236-21, Specifications and Drawings for Construction (FEB 1997) · eCFR, US Office of the Federal Register
  6. 6.Chemical Process Dynamics and Controls, 4.1: P&ID General Information (P. Woolf et al., University of Michigan) · LibreTexts Engineering (CC BY 3.0)
  7. 7.CPL 03-00-004, Petroleum Refinery Process Safety Management National Emphasis Program · US Occupational Safety and Health Administration (OSHA) ·
  8. 8.JIP33: About; JIP33 FAQs · International Association of Oil & Gas Producers (IOGP)
  9. 9.About CFIHOS · IOGP JIP36, CFIHOS
  10. 10.Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918-08) · US Occupational Safety and Health Administration (OSHA)
  11. 11.OSHA Technical Manual, Section IV, Chapter 3: Pressure Vessel Guidelines (Appendix IV:3-1) · US Occupational Safety and Health Administration (OSHA)
  12. 12.Investigation Report: LPG Fire at Valero McKee Refinery, Sunray, Texas (Report No. 2007-05-I-TX) · US Chemical Safety and Hazard Investigation Board (CSB)