Concept, pre-FEED, FEED and detailed design: what happens in each phase?

·9 sources

Short answer

Concept, pre-FEED, front-end engineering design (FEED) and detailed design are the successive design phases of a capital project. Concept tests whether the project is worth doing, pre-FEED compares options and selects one, FEED defines it for an investment decision, and detailed design produces build-ready documents. US Department of Energy Order 413.3C uses conceptual, preliminary and final design.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

If the top end of a project's cost range grows by more than 50% between alternative selection and the baseline, the US Department of Energy (DOE) must go back and reassess which alternative it chose 1. Early phases give ranges, not budgets: DOE asks for a rough-order-of-magnitude range when a need is approved, a cost range for the selected alternative after conceptual design, and a fixed performance baseline only after preliminary design 1. Each phase narrows the options, so a decision taken in one phase is expensive to reopen in the next 2. The same narrowing applies to integrity: materials, corrosion allowances and layouts are fixed phase by phase, and they set what can be inspected and changed during operation (see the integrity table below).

Concept, pre-FEED, FEED and detailed design at a glance

ConceptPre-FEEDFEEDDetailed design
Main questionIs there a need or opportunity worth pursuing, and is it feasible?Which option is best?What exactly will be built, at what cost and on what schedule?How will it be bought, built and tested?
Main outputsStatement of need, functional requirements, feasibility screeningOptions compared, one selected, conceptual design reportDesign basis, flow diagrams, piping and instrumentation diagrams (P&IDs), materials, hazard studies, cost estimate, schedule, permit inputsFinal drawings, technical specifications, bid documents, testing requirements and acceptance criteria
Cost maturity in DOE termsRough order of magnitude rangeCost range for the selected option (not a baseline)Performance baseline: scope, total project cost, completion dateBasis for bids and construction
Decision at the endStudy optionsSelect one optionCommit funds, approve baselineStart construction
Nearest DOE stage and gatePre-conceptual, to CD-0Conceptual design, to CD-1Preliminary design, to CD-2Final design, to CD-3
Nearest CII front end planning phaseFeasibilityConceptDetailed scopeAfter front end planning
Integrity contentProcess route and site set the major hazardsCorrosion and materials outlook for each optionMaterials, corrosion allowance, relief design basis, inspection accessLayouts, test and inspection requirements, records for handover

Sources: DOE Order 413.3C, August 2026 1; Construction Industry Institute (CII), 2014 3; NETL project record 4. Owners define their phases differently; the alignment of names across rows is Beacon's, by purpose, not a formal equivalence.

What happens in concept and pre-FEED?

Concept

  • DOE's pre-conceptual stage documents the functions and capabilities the project must deliver, and its mission need is written without naming a particular solution 1.
  • NASA's equivalent, Pre-Phase A, studies a broad range of concepts and stresses feasibility and desirability rather than optimization, while checking each option's implications through operation and disposal 2.

Pre-FEED

  • DOE's conceptual design must establish scope, feasibility, risks, cost and schedule ranges for the alternatives, and project criteria and design parameters; a conceptual design report records the alternatives and why one was chosen 1.
  • In oil and gas use, pre-FEED is the study that compares engineered options before FEED; a DOE-supported carbon capture FEED, for example, built on a completed pre-FEED study 4.
  • For a new UK offshore production installation, the design notification sent to the regulator must describe the chosen concept, the other options considered and the selection criteria 5.

What happens in FEED and detailed design?

FEED

  • DOE's preliminary design converts the concept into a more detailed design with more reliable cost and schedule estimates, and is complete when it supports a point estimate ready for independent review 1.
  • NASA notes that after preliminary design reviews almost all changes should be refinements, and that significant design changes become increasingly expensive from that phase on 2.
  • In US plants covered by process safety management, much of the process safety information that must exist before a process hazard analysis is produced here: diagrams, P&IDs, materials of construction and relief system design basis 6.

Detailed design

  • DOE's final design prepares the final drawings, technical specifications and contract documents for bids, with testing requirements and acceptance criteria; later scope changes need a compelling reason 1.
  • DOE requires design reviews by reviewers outside the project at the end of conceptual, preliminary and final design, and construction should not start until the design is mature enough to minimize change orders 1.
  • NASA holds critical design reviews before fabrication starts 2.

A common mix-up

DOE's "preliminary design" is not pre-FEED. It comes after the alternative is selected and ends with the cost and schedule baseline, so by purpose it sits closer to FEED 1. A related mix-up is treating an early cost range as a budget: DOE states that the range approved after conceptual design is not the performance baseline against which the project is judged 1. See What is front-end engineering design (FEED)?.

Where integrity problems show up

Decision or step at this stageWhat it affects laterIn the Library
Concept: choosing the design concept against the installation's major hazard scenarios (UK offshore)The safety case and the list of safety and environmental critical elements with their required performance 5What are safety and environmental critical elements (SECEs)?
Pre-FEED: considering corrosion and materials at the process design stage, including foreseeable upsetsWhether materials suit the real service; HSE notes that localized corrosion can cause failure far sooner than uniform wastage would suggest 8What is a corrosion risk assessment in FEED?
FEED: compiling process safety information, including materials, codes used and relief design basisHazard analyses, management of change and mechanical integrity all draw on it; OSHA found many refineries without relief design basis records 6,7What is a design basis?
Detailed design: routing piping for safe access and drainage, avoiding dead legsWhat can be reached for inspection, and where fluid can be trapped 9How do you design equipment so it can be inspected?
Detailed design: setting testing requirements and acceptance criteriaThe pre-startup safety review that confirms construction matches design specifications 1,6What is a pre-startup safety review (PSSR)?
Close-out: transition to operations plan and turnover documents (DOE CD-4)The records that later inspection and changes start from 1What documents are handed over when a project is completed?

Sources: SI 2015/398, Schedule 5 5; HSE COMAH technical measures documents (2025) 8,9; 29 CFR 1910.119 6; OSHA 3918 (2017) 7; DOE Order 413.3C (2026) 1.

Common questions

Can phases be combined or overlapped?
Yes. DOE allows combined approvals (CD-1 and CD-2, or CD-1 to CD-3) for design-build projects whose requirements are well defined early, and it allows long-lead procurement to be approved at or before the baseline decision.
Which phase sets the budget?
In DOE's process the performance baseline, covering scope, total project cost, completion date and key performance parameters, is approved after preliminary design (CD-2), and project success is measured against it.
Is pre-FEED the same as a feasibility study?
Not usually. CII separates feasibility from the concept phase that follows it; on Beacon's alignment, pre-FEED corresponds to the second, where options are engineered enough to be compared and one is selected.

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.DOE O 413.3C, Program and Project Management for the Acquisition of Capital Assets · US Department of Energy (DOE), Office of Project Management
  2. 2.SEH 3.0 NASA Program/Project Life Cycle (NASA Systems Engineering Handbook, NASA/SP-2016-6105 Rev2) · US National Aeronautics and Space Administration (NASA)
  3. 3.Front End Planning: Your Key to a Successful Project (WS213-01) · Construction Industry Institute (CII), University of Texas at Austin ·
  4. 4.Front-End Engineering and Design: Project Tundra Carbon Capture System (project information page, FE0031845) · US DOE National Energy Technology Laboratory (NETL)
  5. 5.The Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015 (SI 2015/398), Schedule 5, as made · legislation.gov.uk, UK National Archives
  6. 6.29 CFR 1910.119, Process safety management of highly hazardous chemicals · eCFR, US Office of the Federal Register
  7. 7.Process Safety Management for Petroleum Refineries: Lessons Learned from the Petroleum Refinery Process Safety Management National Emphasis Program (OSHA 3918) · US Occupational Safety and Health Administration (OSHA)
  8. 8.Corrosion / selection of materials (COMAH Technical Measures Document) · UK Health and Safety Executive (HSE) ·
  9. 9.Design Codes: Pipework (COMAH Technical Measures Document) · UK Health and Safety Executive (HSE) ·