FactProcurement and Supply Chain · Bidding and bid evaluation

How does procurement work on oil and gas projects?

·14 sources

Short answer

Procurement on an oil and gas project turns engineering requirements into equipment and materials that are bought, inspected, delivered and documented. The steps run from requisition and supplier selection through solicitation, technical and commercial evaluation, purchase order, expediting and inspection to document handover. Companies set their own procedures; some use IOGP's standardized JIP33 procurement specifications.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

The International Association of Oil & Gas Producers (IOGP) started Joint Industry Programme 33 (JIP33) in 2016 in response to industry-wide cost and schedule overruns of more than 40%, and aimed it at the specifications used to buy equipment 1. Until then, IOGP notes, each order came with its own operator requirements, frequently running to hundreds of pages and varying even between one company's projects 1. Procurement also carries safety duties: US process safety rules require new equipment, as fabricated, and later spare parts and maintenance materials to be suitable for their service 7.

What are the steps in project procurement?

No single public rule sets the steps for a private oil and gas project. World Bank rules, used here only for definitions, describe the procurement process as running from identifying a need through planning, specifications, selection and contract award to contract management 9. Research by the Construction Industry Institute (CII) on industrial projects describes materials management systems that tie together take-off, vendor evaluation, purchasing, expediting, warehousing and distribution 4,5.

StepWhat happensSourceIn the Library
1. Define the requirementEngineering lists quantities and writes specifications and data sheets4,9What is a material take-off (MTO)?, What is a material requisition?
2. Choose who may bidSuppliers are evaluated or prequalified4,5,8How are suppliers prequalified for oil and gas projects?
3. Solicit offersThe buyer issues a request for bids, quotations or proposals with the specification package2,8ITB vs RFQ vs RFP in oil and gas procurement
4. EvaluateTechnical evaluation first, then the commercial comparison of acceptable bids9What is technical bid evaluation in oil and gas?
5. Award and expediteThe order is placed, then followed to protect delivery dates4,5What is expediting in project procurement?
6. Inspect and receiveSurveillance and inspection at the supplier, then quality control on receipt1,6What is an inspection and test plan (ITP)?
7. Hand over informationSupplier documents and data go to the owner for operation and maintenance1,3What is vendor document management?

Timing of the take-off shows up in waste. CII research summarized in 1999 found that bulk material surplus can usually be held to 1% or less when take-off uses final design drawings, but can pass 10% when take-off is done earlier, and that an effective materials management system cuts the surplus of bulk materials from 5% to 10% down to about 1% to 3% 6.

Who takes part in procurement on an oil and gas project?

Engineering, procurement and construction (EPC) projects run for long periods and involve project owners, contractors, subcontractors and vendors 10. Under a lump-sum turnkey contract the contractor is responsible for executing the project, and a 2021 study notes that owners can use this form to pass project risk to the contractor 10. Which party buys which items, and who approves the technical evaluation, is set by each contract.

CII's 1999 guidance puts responsibility for conforming to the requirements on the supplier, with the buyer setting the level of surveillance and inspection and checking quality on receipt 6. JIP33's quality requirements specification states the supplier's quality system and the purchaser's involvement in inspection and testing 1.

How do requirements and documents travel with an order?

JIP33 packages purchase requirements into four documents: a supplement to an industry standard, an information requirements specification listing the documents and data the supplier must deliver, a quality requirements specification, and a procurement data sheet for project choices 1. IOGP advises naming the specifications in the basis of design, then carrying them through front-end engineering design (FEED), execution and the tendering packages 2. As of October 2026, JIP33 reports 60 published specifications intended to cover about 80% of procurement scope; companies add requirements for the rest 1,2.

At the other end, IOGP's CFIHOS (Capital Facilities Information Handover Specification) standardizes how operators, contractors, manufacturers and suppliers hand over data and documents so a facility can be operated, maintained and decommissioned 3. In plants covered by US process safety management, that information includes each item's materials of construction and design codes, and a pre-startup safety review must confirm that equipment matches the design specifications 7.

Where integrity problems show up

Decision or step at this stageWhat it affects laterIn the Library
Alloy components are verified on receipt but not after later handlingAt a refinery in Texas City, Texas, in 2005, a carbon steel elbow fitted during maintenance where 1.25% chromium steel was required failed by high temperature hydrogen attack after fewer than 3,000 hours; the site's procedure verified alloy parts at warehouse receipt and issue, not during maintenance 11What is positive material identification (PMI)?
Spare parts and maintenance materials are boughtUS process safety rules require them to be suitable for the process application 7What is material traceability?
Material records are left out of the information requirementsWhere required, US onshore steel gas transmission operators without traceable, verifiable and complete records must verify material properties through tests and examinations 13What is a mill test certificate (EN 10204 3.1 and 3.2)?
Post-weld heat treatment is dropped from a purchase specificationOSHA guidance reports cracking in amine and wet hydrogen sulfide service at or near welds, less often where welds were heat treated 12What is post-weld heat treatment (PWHT)?
Vendor documents are not handed overProcess safety information must include materials of construction and design codes 7What documents are handed over when a project is completed?

Sources: CSB Safety Bulletin 2005-04-B, 2006 11; 29 CFR 1910.119(d), (j)(6) 7; 49 CFR 192.607 13; OSHA Technical Manual, Section IV, Chapter 3 12.

Common questions

Is procurement the same as purchasing?
No. CII describes materials management as more than buying: it plans and controls every step so that price, quality and quantity targets are met when and where the material is needed.
Do JIP33 specifications replace API, ASME or ISO standards?
No. IOGP states that JIP33 specifications are used together with international standards such as API, ASME, ISO, IEC and IEEE, replacing individual operators' own purchase specifications rather than the standards.
Do public procurement rules apply to oil and gas companies?
Rules such as the World Bank Procurement Regulations apply to borrowers on World Bank-financed investment projects. This Library uses them to define terms such as request for bids, quotations and proposals; private companies set their own procedures.

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.JIP33 About us · International Association of Oil & Gas Producers (IOGP), Joint Industry Programme 33
  2. 2.JIP33 FAQs · International Association of Oil & Gas Producers (IOGP), Joint Industry Programme 33
  3. 3.About CFIHOS · International Association of Oil & Gas Producers (IOGP), Joint Industry Programme 36 (CFIHOS)
  4. 4.Costs and Benefits of Materials Management Systems (Publication 7-1), catalog record and abstract · Construction Industry Institute (CII), via NIST FireDOC
  5. 5.Project Materials Management Handbook, catalog record and abstract · Construction Industry Institute (CII), via NIST FireDOC
  6. 6.Procurement and Materials Management: A Guide to Effective Project Execution (IR7-3), abstract and key findings · Construction Industry Institute (CII)
  7. 7.29 CFR 1910.119, Process safety management of highly hazardous chemicals · eCFR, US Office of the Federal Register
  8. 8.Procurement Regulations for IPF Borrowers (Seventh Edition) · The World Bank
  9. 9.Procurement Guidance: Evaluating Bids and Proposals, Including Use of Rated Criteria for Procurement of Goods, Works, and Non-Consulting Services (Third Edition) · The World Bank
  10. 10.AI and Text-Mining Applications for Analyzing Contractor's Risk in Invitation to Bid (ITB) and Contracts for Engineering Procurement and Construction (EPC) Projects (S.J. Choi, S.W. Choi, J.H. Kim, E.-B. Lee), Energies 14(15), 4632 · MDPI (peer-reviewed journal); authors at Pohang University of Science and Technology (POSTECH) ·
  11. 11.Safety Bulletin No. 2005-04-B, BP Texas City, TX Refinery Fire: Positive Material Verification: Prevent Errors During Alloy Steel Systems Maintenance · US Chemical Safety and Hazard Investigation Board (CSB) ·
  12. 12.OSHA Technical Manual, Section IV, Chapter 3: Pressure Vessel Guidelines · US Occupational Safety and Health Administration (OSHA)
  13. 13.49 CFR 192.607, Verification of pipeline material properties and attributes: Onshore steel transmission pipelines · eCFR, US Office of the Federal Register
  14. 14.Attributes of Materials Management Systems (SD-1), abstract and key findings · Construction Industry Institute (CII)