What is API 653 (aboveground storage tank inspection)?

·10 sources

Short answer

API 653 is the American Petroleum Institute's standard for inspecting, repairing, altering and rebuilding steel aboveground storage tanks in service. It applies mainly to tanks built to API 650 or its predecessor, API 12C, from foundation and bottom to roof and nozzles, and also covers relocation. The current 5th edition dates from November 2014, with later addenda.

By , Editor·Researched and drafted by ·Checked by , Editor·Last checked ·Next review

Why does it matter?

In July 2001, hot work on a catwalk above a sulfuric acid tank farm at a refinery in Delaware City, Delaware, ignited flammable vapor in a corroded tank; the tank tore from its floor, one contract worker was killed, eight people were injured and about 99,000 gallons of acid reached the Delaware River 3. The tank's internal inspection, first scheduled for 1996, had been postponed again and again, although the site's own tank inspectors asked for it "as soon as possible" in 1999, 2000 and 2001 3. The US Chemical Safety and Hazard Investigation Board (CSB) found that the refinery scheduled tank inspections on default frequencies rather than on how corrosive each tank's contents were 3.

What does API 653 cover?

API Std 653, Tank Inspection, Repair, Alteration, and Reconstruction, is in its 5th edition (November 2014), which API's 2025 catalog lists with three addenda, the latest from November 2023, and one erratum 1. It is the in-service counterpart of API 650: it applies to welded steel storage tanks once they are operating, and sets the minimum the owner must do to keep them sound through inspection and through repairs, alterations, moves and rebuilds 1. The catalog also notes that it is written for organizations that have trained tank engineers and inspectors, and that flaws it gives no criteria for can be judged with API 579-1/ASME FFS-1 1.

How is an API 653 inspection program organized?

  • Outside and inside. A tank program combines inspections made from outside while the tank operates with internal inspections that need the tank taken out of service and emptied 3.
  • Timing follows the contents. Inspection frequency has to reflect how corrosive the stored liquid is, as the CSB stressed at Delaware City 3. US pipeline rules also bar the standard's risk-based option for setting internal inspection intervals on breakout tanks 6. See How are inspection intervals set for vessels, piping and tanks?.
  • Tank bottoms. API covers cathodic protection of tank bottoms in RP 651 (5th edition, August 2024) and bottom linings in RP 652 (5th edition, May 2020) 1. Where a US pipeline operator protects the bottom of a breakout tank larger than 500 barrels with cathodic protection, the system must be installed to RP 651 8.
  • Inspection practice. API RP 575 (5th edition, September 2024) supplements API 653 with inspection practice for atmospheric and low-pressure tanks 1.
  • Repairs and testing. For US pipeline breakout tanks, repair, alteration and reconstruction must follow API 653, and the standard decides whether a hydrostatic test is needed afterward 7. See What is a hydrostatic test?.
  • Inspectors. API certifies aboveground storage tank inspectors in a program that API states is ANSI-accredited 2.

Who requires API 653?

  • Pipeline breakout tanks. The Pipeline and Hazardous Materials Safety Administration (PHMSA) requires atmospheric and low-pressure steel breakout tanks (tanks that absorb surges or hold liquid for onward pipeline transport) to be inspected to API 653 5,6. Its incorporation list names the 3rd edition, from December 2001, with addenda to 2008 5. If structural conditions block access to a tank bottom, its integrity may be assessed under a plan in the operator's maintenance manual 6.
  • Oil spill prevention. The Environmental Protection Agency's (EPA) spill prevention rule requires each aboveground container to be tested or inspected for integrity on a regular schedule and after material repairs, with the type, frequency and inspector qualifications set by industry standards and comparison records kept 9.
  • Process safety. OSHA's process safety management standard lists storage tanks among the equipment its mechanical integrity element covers 10.

After Delaware City, the CSB recommended that API make its tank inspection standards treat holes, or thinning beyond the minimum acceptable thickness, in tanks that may hold flammable vapor as an imminent hazard needing immediate repair or removal from service. The CSB lists the recommendation as closed with acceptable action 4.

Where integrity problems show up

What it finds wellWhat it can miss or get wrongIn the Library
Holes and thinning in the roof and shell visible from outside: the CSB judged that a complete external inspection would probably have found the roof holes at Delaware City 3Partial checks: after 1994 inspectors there only spot-checked shell thickness near known leaks, and several holes in the roof and shell went unreported 3What should an inspection plan contain?
Floor and internal condition, seen when the tank is emptied for internal inspection 3A deferred inspection: the tank was emptied three times in 2000 and 2001 to change service, and none of those outages was used for the internal inspection 3How are inspection intervals set for vessels, piping and tanks?
Soil-side bottom corrosion where cathodic protection is installed and checked 1,8Bottoms that cannot be reached: PHMSA allows integrity to be assessed by an alternative plan when structure blocks access 6What is soil corrosion?, How does cathodic protection work?
A tank's condition against its current service 3A change of service without full review: converting tanks from fresh to spent acid, which can give off flammable vapor, was not adequately addressed by engineering and change management at Delaware City 3What is management of change (MOC)?

Sources: CSB report on Delaware City (2002) 3; API 2025 Publications Catalog 1; 49 CFR 195.432 and 195.565 6,8.

Common questions

What is the difference between API 650 and API 653?
API 650 sets requirements for building new welded tanks: material, design, fabrication, erection and testing. API 653 takes over once the tank is in service and governs where the two conflict.
Does API 653 cover pressurized tanks such as LPG storage?
Not in US pipeline rules: breakout tanks built to API 2510, the standard for liquefied petroleum gas (LPG) installations, are inspected and repaired under API 510 instead. See [What is API 510?](/library/api-510/).
Who can inspect tanks under API 653?
API runs a separate certification for aboveground storage tank inspectors. See [How do API 510, 570 and 653 inspector certifications work?](/library/api-inspector-certification/).

Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.

Sources

  1. 1.2025 Publications Catalog (entries for Std 653, Std 650, RP 575, RP 651, RP 652 and API 579-1/ASME FFS-1) (Std 653, 5th edition, November 2014, with Addenda 1 (April 2018), 2 (May 2020) and 3 (November 2023) and Errata 1 (March 2020); Std 650, 13th edition, March 2020; RP 575, 5th edition, September 2024; RP 651, 5th edition, August 2024; RP 652, 5th edition, May 2020) · American Petroleum Institute (API)
  2. 2.Individual Certification Programs · American Petroleum Institute (API)
  3. 3.Investigation Report: Refinery Incident, Motiva Enterprises LLC, Delaware City Refinery (Report No. 2001-05-I-DE) · US Chemical Safety and Hazard Investigation Board (CSB) ·
  4. 4.Motiva Enterprises Sulfuric Acid Tank Explosion (investigation page and recommendation status) · US Chemical Safety and Hazard Investigation Board (CSB)
  5. 5.49 CFR 195.2, Definitions, and 195.3, What documents are incorporated by reference partly or wholly in this part? · eCFR, US Office of the Federal Register
  6. 6.49 CFR 195.432, Inspection of in-service breakout tanks · eCFR, US Office of the Federal Register
  7. 7.49 CFR 195.205, Repair, alteration and reconstruction of aboveground breakout tanks, and 195.307, Pressure testing aboveground breakout tanks · eCFR, US Office of the Federal Register
  8. 8.49 CFR 195.565, How do I install cathodic protection on breakout tanks? · eCFR, US Office of the Federal Register
  9. 9.40 CFR 112.8, Spill Prevention, Control, and Countermeasure Plan requirements for onshore facilities · eCFR, US Office of the Federal Register
  10. 10.29 CFR 1910.119, Process safety management of highly hazardous chemicals · eCFR, US Office of the Federal Register