What is process safety management (PSM)?
Process safety management (PSM) is a management system that prevents fires, explosions and toxic releases at processes using highly hazardous chemicals. In the United States it is the Occupational Safety and Health Administration (OSHA) standard 29 CFR 1910.119, issued in 1992, which sets 14 elements, from process hazard analysis to mechanical integrity and management of change.
By Jun Zhong, Editor·Researched and drafted by Beacon's AI newsroom·Checked by Jun Zhong, Editor·Last checked ·Next review
Why does it matter?
In the first year of OSHA's refinery National Emphasis Program (NEP), launched in 2007, inspectors issued 348 PSM citations at 14 refineries, and nearly 80% of the violations fell under 5 of the 14 elements: operating procedures, mechanical integrity, process hazard analysis, process safety information and management of change 4. OSHA singled out repeat violations of paragraphs (e)(5), (j)(2) and (j)(5), which exist so that deficiencies in critical equipment are found and fixed promptly 4. When the program started, OSHA counted 36 fatal or catastrophic refinery incidents involving these chemicals since May 1992, with 52 employee deaths 5.
Which facilities does PSM apply to?
Paragraph (b) defines a "process" broadly: any use, storage, manufacture, handling or on-site movement of a highly hazardous chemical, with linked or nearby vessels counted as one process 1. Under paragraph (a)(1), a process is covered when it holds 1:
- a toxic or reactive chemical listed in Appendix A at or above its threshold quantity; or 1
- 10,000 pounds (4,535.9 kg) or more, in one location, of a Category 1 flammable gas or a flammable liquid with a flash point below 100 °F (37.8 °C), with some exceptions for fuel and atmospheric storage. 1
Paragraph (a)(2) leaves out retail facilities, oil or gas well drilling and servicing, and normally unoccupied remote facilities 1. Construction work has its own PSM standard 2.
What are the 14 elements of PSM?
Paragraphs (c) to (p) set out the elements, which OSHA treats as one site-specific, integrated system 4.
| Paragraph | Element | What it requires, in short |
|---|---|---|
| (c) | Employee participation | Written plan; employees consulted and given access to PSM information |
| (d) | Process safety information (PSI) | Data on chemicals, process technology and equipment, compiled before the hazard analysis |
| (e) | Process hazard analysis (PHA) | Team study by a recognized method such as HAZOP; findings resolved; revalidated at least every 5 years |
| (f) | Operating procedures | Steps for each operating phase, limits and safety systems; certified current every year |
| (g) | Training | Initial and refresher training (at least every 3 years) for operators |
| (h) | Contractors | Selecting, briefing and overseeing contractors on or near the process |
| (i) | Pre-startup safety review | Checks before chemicals enter a new or significantly modified facility |
| (j) | Mechanical integrity | Procedures, training, inspection and testing, records, deficiency correction and quality assurance |
| (k) | Hot work permit | A permit for welding, cutting and similar work on or near the process |
| (l) | Management of change | Written procedures to review changes, other than replacements in kind, before they are made |
| (m) | Incident investigation | Investigation, started within 48 hours, of actual and near catastrophic releases |
| (n) | Emergency planning and response | A plant-wide emergency action plan that also covers small releases |
| (o) | Compliance audits | Certification at least every 3 years that procedures are adequate and followed |
| (p) | Trade secrets | Information needed for PSM shared even when it is confidential |
Source: 29 CFR 1910.119, paragraphs (c) to (p) 1.
Where did PSM come from, and how is it enforced?
OSHA proposed the standard in July 1990 and published it on 24 February 1992; its booklet on the rule cites earlier disasters such as Bhopal, India, in 1984 (more than 2,000 deaths) and Pasadena, Texas, in 1989 (23 deaths) 3. All initial process hazard analyses were due by 26 May 1997 1.
OSHA ran the refinery NEP from June 2007 to 2011 in federal areas and began a chemical plant pilot in 2009; a combined program for both took effect on 17 January 2017 6. States can go further: California's refinery rule, operative since 1 October 2017, adds a damage mechanism review, a hierarchy of hazard controls analysis and tracking of process safety performance indicators 11.
How does PSM relate to the EPA RMP rule and the UK COMAH Regulations?
The US Environmental Protection Agency (EPA) Risk Management Program (RMP) rule, 40 CFR Part 68, comes from section 112(r) of the Clean Air Act 8. A process subject to OSHA PSM falls under RMP Program 3 unless it qualifies for Program 1, and Program 3 mirrors the PSM elements in sections 68.65 to 68.87 7. RMP adds an off-site hazard assessment with worst-case releases and a five-year accident history, and a plan filed with EPA every 5 years 8.
In Great Britain, the Control of Major Accident Hazards Regulations 2015 (COMAH), in force since 1 June 2015, implement most of the European Union's Seveso III Directive 9. Sites holding dangerous substances above threshold quantities must prevent major accidents and limit their effects on people and the environment. The UK Health and Safety Executive (HSE) enforces COMAH jointly with the environment agency for England, Wales or Scotland 9.
Where integrity problems show up
| Element or step | Integrity link | In the Library |
|---|---|---|
| Process safety information (d)(3) | Equipment data include materials of construction, relief design basis and design codes, and the employer documents that equipment follows recognized and generally accepted good engineering practice 1 | What is RAGAGEP (recognized and generally accepted good engineering practice)? |
| Process hazard analysis (e) | After the 2012 Richmond, California, refinery fire, the CSB recommended a damage mechanism hazard review within each PHA cycle 10; California's refinery rule now requires one and makes it available to the PHA team 11 | What is a damage mechanism review? |
| Pre-startup safety review (i) | Before chemicals are introduced, construction and equipment must be confirmed to match the design specifications 1 | What is a pre-startup safety review (PSSR)? |
| Mechanical integrity (j) | Vessels, tanks, piping, relief devices, shutdown systems, controls and pumps are inspected and tested, each test is recorded, and deficiencies outside acceptable limits are corrected 1; OSHA found these provisions violated repeatedly 4 | What is mechanical integrity (MI)? |
| Management of change (l) | A change other than a replacement in kind must be reviewed first, and the equipment data in PSI updated 1 | What is management of change (MOC)? |
| Compliance audit (o) | Every 3 years the employer certifies that procedures, integrity ones included, are adequate and followed 1 | What is a PSM compliance audit? |
Sources: 29 CFR 1910.119 1; OSHA refinery NEP first-year results 4; CSB Richmond report, 2015 10; California Title 8, Section 5189.1 11.
Common questions
- Is process safety management the same as process safety?
- Not quite. The CSB cites the Center for Chemical Process Safety definition of process safety as a discipline aimed at preventing fires, explosions and accidental chemical releases; PSM is the management system, and in the US the OSHA rule, that puts it into practice. How it differs from injury prevention is covered in [Process safety vs occupational safety: what is the difference?](/library/process-vs-occupational-safety/).
- Does PSM apply to oil and gas production?
- The standard excludes well drilling and servicing and normally unoccupied remote facilities. Other upstream processes are covered when they hold a listed chemical or enough flammable material; OSHA's own compliance guidance discusses hazard analyses for gas plants.
Beacon explains these concepts in its own words for education. It does not reproduce or replace the standards cited, and Winda is not affiliated with or endorsed by the organizations that publish them. Engineering decisions need the current edition of the standard and a qualified engineer.
Sources
- 1.29 CFR 1910.119, Process safety management of highly hazardous chemicals (including Appendix C, nonmandatory compliance guidelines) · eCFR, US Office of the Federal Register
- 2.Process Safety Management: Overview · US Occupational Safety and Health Administration (OSHA)
- 3.Process Safety Management, OSHA 3132 · US Occupational Safety and Health Administration (OSHA)
- 4.Refinery NEP First Year Inspection Results · US Occupational Safety and Health Administration (OSHA)
- 5.CPL 03-00-004, Petroleum Refinery Process Safety Management National Emphasis Program · US Occupational Safety and Health Administration (OSHA) ·
- 6.CPL 03-00-021, PSM Covered Chemical Facilities National Emphasis Program · US Occupational Safety and Health Administration (OSHA) ·
- 7.40 CFR Part 68, Chemical Accident Prevention Provisions (section 68.10 and Subpart D, Program 3 Prevention Program) · eCFR, US Office of the Federal Register
- 8.Risk Management Program (RMP) Rule Overview · US Environmental Protection Agency (EPA)
- 9.Introduction to Control of Major Accident Hazards (COMAH) · UK Health and Safety Executive (HSE)
- 10.Final Investigation Report: Chevron Richmond Refinery Pipe Rupture and Fire, Report No. 2012-03-I-CA · US Chemical Safety and Hazard Investigation Board (CSB) ·
- 11.California Code of Regulations, Title 8, Section 5189.1, Process Safety Management for Petroleum Refineries · California Department of Industrial Relations
- 12.Investigation Report: Refinery Explosion and Fire, Texas City, Texas, March 23, 2005, Report No. 2005-04-I-TX · US Chemical Safety and Hazard Investigation Board (CSB)